Applying project management to an election run (part three)

From the Easy in theory, difficult in practice Blog
by
My musings on project management, project portfolio management and change management. I'm a firm believer that a pragmatic approach to organizational change that addresses process & technology, but primarily, people will maximize chances for success. This blog contains articles which I've previously written and published as well as new content.

About this Blog

RSS

Recent Posts

Leading Through Crisis Means Leading Through Context

"It's the end. But the moment has been prepared for." - retirement lessons from the Doctor

Just because they are non-critical, doesn't mean they are not risky!

Just because they are non-critical, doesn't mean they are not risky!

How will YOU avoid these AI-related cognitive biases?

Categories

Agile, Artificial Intelligence, Career Development, Change Management, Communications Management, Decision Making, Governance, Hiring, Kanban, Lessons Learned, Personal Development, PMO, Portfolio Management, Project Management, Resource Management, Risk Management, Risk Management, Schedule Management, Scheduling, Tools

Date

linkedin twitter facebook Request to reuse this  


The final (pre-election) article in my series covering my election run for city councilor of Ward 4 in Welland, Ontario shares some of the key risks I've identified with this project and how I'm responding to them.

In general, most projects will have two broad categories of risks - those which relate to the delivery of the project itself and those which relate to the outcomes from the project. Delivery risks will affect the ability of the team to complete the project within normal constraints such as scope, schedule, cost, quality and team member availability. Outcome risks will impact the realization of expected benefits.

For each category, I will provide the key risks I've identified, their qualitative impact and likelihood of realization and the risk responses I've implemented or plan to implement.

Delivery Risks

Increased costs due to inflation or increased demand might cause the project to exceed its approved budget. The impact of the risk is high and the probability is moderate given the current economic conditions. I am attempting to mitigate this risk by identifying multiple suppliers for the products and services I'll be procuring to ensure I'm getting good prices and will reduce its impact (if the risk is realized) by cutting back on what I will be purchasing.

Another risk related to products and services is that supply chain delays might increase the likelihood of not receiving procured items on time before the election date. The impact of this risk is high but the probability is low as the items being procured are readily available. The same response as in the previous risk will address this risk.

Given the large number of bylaws and regulations related to the election, there is a chance that I or one of the volunteers supporting my campaign might break one of the rules resulting in fines, disqualification from the election or other penalties. The likelihood of occurrence is moderate and the impact would be high. My mitigation risk response has been to thoroughly study all the official election documentation and to seek clarification from election officials whenever I run into a scenario which is not explicitly permitted or prohibited.

Ward 4 has over 6500 residents (as per the previous 2018 election data). I'm planning to go door-to-door introducing myself to homeowners on a number of the main streets within the ward in early September once the start date for posting lawn signs has passed. I'm not planning to visit any given house more than once. As such, there is a risk that if a large number of residents are not home when I visit, the effectiveness of this activity will be reduced. The impact is high but the probability is low given both the demographics of the city and kids will be back to school which means fewer families would be out of town on vacation. I will try to reduce the likelihood of occurrence by concentrating my visits in the early evening and on weekends.

Outcome Risks

Given that under 35% of the eligible voters participated in the last municipal election, there is a high probability, high impact risk that even if I am successful in creating sufficient awareness about myself, sufficiently few residents will turn out to vote which could favor the incumbents more than a newcomer. To mitigate the likelihood of this risk being realized, a key component of my campaign is to raise awareness about the upcoming election and to encourage residents to vote.

Finally, there is the risk that in spite of my campaign, I might get insufficient votes to be one of the two winners in my ward. The impact would, of course, be high and the likelihood of realization is moderate. My entire campaign is a response to address this risk so hopefully it will be successful!


Posted on: July 31, 2022 07:00 AM | Permalink

Comments (4)

Please login or join to subscribe to this item
avatar
Luis Branco CEO| Business Insight, Consultores de Gestão, Ldª Carcavelos, Lisboa, Portugal
Dear Kiron
The topic that you brought to our reflection and debate was very interesting.

Thank you for sharing and for your risk identification

What is the probability that one (or several volunteers):
- Not being able to support you in the period when you need them most? (illness, accident, switching to competitors, etc.)
What will the impact be?
What is the response to this risk?

Are there other risks that you have not identified?

I want you to be elected

avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Thanks Luis -

As with all projects, there are many other risks which have been considered but aren't what I'd call "key risks". If this election had been held during the peak of the pandemic, I would have definitely added some health-related risks.

I'm not asking a lot from the current volunteer team and I do have a number of other friends and contacts who have offered to help, hence I wasn't too concerned about availability challenges.

Kiron

avatar
INDUMATHI KANNAYIRAM PROJECT MANAGER| DELTASTAR POWER PROJECTS SERVICES LLC Abudhabi, U.A.E, United Arab Emirates
Thanks

avatar
Stéphane Parent Self Employed / Semi-retired| Leader Maker Prince Edward Island, Canada
I like your two-prong approach to risk management. I hope you have no black swan!