The generally accepted way of assessing progress on a project, and predicting its completion, is to use a critical path method schedule. However, the CPM paradigm does not work across a wide range of projects where there is no predetermined sequence of working that must be followed. There may be a high level “road map” outlining the desired route to completion and/or specific constraints on the sequencing of parts of the work but in most agile projects, the people doing the work have a high degree of flexibility in choosing the way most of the work is accomplished.
The focus of this post is to offer a practical solution to the challenge of assessing progress, and calculating the likely completion date in agile projects.
WPM as an Alternative to ES and CPM
Work performance management (WPM) is designed as an alternative approach to project controls. It uses the same concept as earned schedule, but offers a simple, practical tool that uses project metrics that are already being used for other purposes.
The function of WPM is to assess progress and calculate a predicted completion date in a consistent, repeatable, and defensible way by comparing the amount of work achieved at a point in time with the amount of work planned to have been achieved at the same point in time. Then based on this data, you calculate an expected completion date.
The Theoretical Basis of WPM
WPM has been designed to fill an identified gap in the current controls systems used on agile projects. It is based on the same premise used in earned schedule and earned duration, and is expected to achieve a similar level of reliability by comparing the amount of work planned to be accomplished to the amount of work actually achieved in the period through to a data date (time now). However, unlike ES and ED, WPM focuses on the core elements of the work.
WPM Terminology
The terminology used for the data points in WPM is:
- WP = Work Planned measured in an appropriate unit – cumulative over time
- WA = Work Accomplished measured on the same basis as WP
- PC = Planned Completion project duration in time units (days, weeks, months)
- TN = Time Now the number of PC time units to the date of assessment
- TE = Time Earned the number of PC time units to the point where WA = WP
From this information, the work performance measures are calculated as follows:
- WPV = Work Performed Variance TE - TN,
negative values show the schedule slip in PC time units - WPI = Work Performed Index TE/TN,
values less than 1.0 show less work has been accomplished than planned - EC = Expected Completion the expected project duration in PC time units calculated by PC/WPI = EC
Applying WPM to a Project Using Scrum
Scheduling the work should be as realistic as possible, but in many situations a straightforward pragmatic approach will suffice. Take for example a 20-week software project that has 27 stories of various size, a total of 86 story points, and the resource planning to use two scrum teams. In the absence of any other information, you could assume:
- The first two weeks are needed for team development, planning and other start-up processes
- Sprints are expected to take two weeks each
- The last two weeks will be for contingencies, bug fixes and other finalization work
This leaves 16 weeks for productive work; therefore, the first stories should be delivered at the end of the first productive sprint, Week 4, and all stories by the end of Week 18.
This means the rate of planned production between the start of Week 2 and the end of Week 18 is 86/16 = 5.375 story points per week. Based on these assumptions, at the end of Week 4 (two weeks of production), we can expect 10+ story points to be complete, and at the end of Week 18 all 86 story points complete. The rest of the planned distribution is simply a straight line between these two points.
We know sprints will not take exactly two weeks every time (some will overrun, and occasionally some will finish early), and we also know the number of story points generated in each sprint will vary. But on average, if the two sprint teams together are not completing a bit over 5.3 story points per week, every week, the project will finish late.
Once this basic rate of production has been determined for the project, WPM measures the actual work delivered (WA) and shows the time variance at time now (TN) and uses this information to predict the expected completion (EC).
For example, at the end of Week 8, three sprints should have been completed by both teams, and we are expecting 30 story points complete. But only 23 have been delivered. Velocity calculation will indicate more sprints will be needed, and the burndown chart will show the work is behind plan. But what does this mean from a time perspective?
A look at the planned rate of production will show 23 story points should have been finished during Week 7 (the actual fraction is 7.3). Therefore, the work is 0.7 weeks (3.5 working days) late. The work performance index (WPI) is 0.9125.
Dividing the original duration (20 weeks) by the WPI suggests the revised duration for the project is 21.9178 weeks; the variance at completion is -1.9178 weeks, or 13.4 calendar days late.
If these calculations look similar, they are based on the well-tried formula used in earned value management and earned schedule—all I’ve done is shift the metric to a direct measure of the work performed.
Conclusions
WPM is designed to be a simple robust performance measurement system that will provide an accurate assessment of the project’s status from a time management perspective. It can assess how far ahead or behind plan the work currently is—and based on this information, the likely project completion date based on the assumption work will continue at the current rate
The two requirements to implement WPM are:
- A consistent metric to measure the work planned and accomplished
- A simple but robust assessment of when the work was planned to be done
The metric used can be a core deliverable (e.g., 2,000 computers replaced in an organization), or a representation of work such as “story points,” or the monetary value of the components to be delivered to the client.
Peripheral and support activities can usually be ignored when establishing the WPM metric; they rarely impact the project delivery independently. Failures in the support areas typically manifest in delays to the primary delivery metric.
Questions?
Has anyone seen or used something like this in the “real world”? I would love to hear if you have.