3 Ways to Improve Project Management In The Time of Labor Shortages
As part of starting my technology career, I augmented my undergraduate degree in computer science with a minor in economics. Over the years, I began to appreciate more the inherent wisdom of the demand and supply relationships as it pertains to labor forces. In particular, the laws of economic supply and demand are playing themselves to new heights in these uncertain times. We see it every day in the news: Jobs by the thousands of all types are going unfilled with nobody stepping forward to fill them. In our industry, we are seeing multiple factors converging to create difficult times for project and product managers. The exponential growth in technology, changing demographics in work forces as well as COVID-19 have all greatly impacted what we do on a day-to-day basis. For project and product delivery, I am observing that labor shortages that impact our delivery efforts take on two different forms:
As a project and product manager, these market conditions create a confounding set of risks that need some refreshed thinking in order to mitigate their impacts. Here are a few of my thoughts on ways we can manage around these challenging times: 1. Up Your Game on Scope, Schedule and Resource Management In addition to giving more emphasis to these areas than ever before, project managers need to look beyond their project for external threats. By taking more of a portfolio manager mindset and looking for external threats including other projects, they can better anticipate and address challenges to their own delivery commitments. For high-speed, iterative agile product delivery, labor shortages make for even more challenging times. One of the benefits of a dedicated set of resources for an agile product team is that over time they reduce the learning curve and improve decision-making efficiency. Swapping resources in and out of agile product delivery due to labor shortages creates damaging disruption to both schedule and quality. This environment compels agile product managers to be even more vigilant when it comes to managing scope, schedule and resources. 2. Get Back to Basics While the increased frequency and depth of examination improves stewardship and has helped with early detection of delivery volatility, in these times there may not be enough capacity to warrant this level of detail. To help mitigate impacts of labor shortages while not adversely impacting delivery, take a good hard look at the project and product metadata that is currently being produced. For the level of uncertainty and risk on your project or product, can the frequency of reporting, analysis and review meetings be reduced in order to spend more time on activities that directly impact delivery? For the depth of metadata, explore simplified methods for conveying progress against a plan. For example, the use of additional done/not done milestones to measure progress would take less effort than gathering timesheets to calculate total effort. Rationalizing where it makes sense, the frequency and breadth of supporting metadata creates more capacity for direct project and product activities. 3. Restore Real-Time Individual Engagement as a Norm Pre-pandemic, there was a lot of personal interaction in an office or site; these days, we rely on online collaboration tools as a primary means of connection and communication. Despite the ability as a group to remotely connect audibly and visually through the use of these tools, difficulties remain in terms of the effectiveness and efficiency of personal engagement, especially at an individual level. Individual connection has always been a means of identifying both new ideas as well revealing challenges that may not arise in a group setting; all the more reason to make it an increasingly frequent activity when managing projects and products. While modern times present new challenges, it’s still possible to connect on a person-to-person level. Outside of the normal cadence of group meetings, set up recurring individual connection sessions with team members. These can still be done with collaboration tools—but they have all the advantages of what private conversation can provide. I’m finding these individual meetings have a great propensity to really help us understand the underlying dynamics of project and product delivery. (If you happen to live in reasonably close proximity and abide by any local regulations, that doesn’t mean an espresso in person to stimulate conversation would be out of the question!) These are indeed challenging times, the likes of which I have never before seen in my project and product management career. Labor shortages as well as volatility from resource overcommitments are all causing us to rethink our day-to-day activities on how we interact with people. While we can long for the days when walking down the hall in an office to connect with a team member was the norm, we as project and product delivery managers still need to take steps to overcome these challenges in our drive for successful delivery outcomes. I welcome any comments on what others are doing to help reduce the impact of labor shortages with creative project and product management techniques. Share your insights below! |
The Planning Paradox
By Lynda Bourne How much detail is too much? Traditional views tend to favour a management approach built on the assumption more detail is better, and to a point this is undoubtedly correct, insufficient detail in a plan of any type is a sure way to fail – ‘just-do-it’ at the overall project level does not help. But looking at the ‘Coastline Paradox’ and using the length of a coastline as a synonym for the duration of a project suggests there is a point where too much detail is counterproductive. The coastline paradox states that as you increase the detail by using smaller units of measure, the measured length of the coastline increases. If you use a small enough unit of measure, the length becomes infinite. For a more detailed explanation see: The Coastline Paradox Explained https://en.wikipedia.org/wiki/Coastline_paradox So, what does this mean for project controls and project management? No one navigating a ship into a UK port would be happy using a map where the smallest measurement was 50 km, significantly more detail is needed, but they do not need absolutely everything about their intended destination. What’s needed is useful information at an appropriate level of detail, the same goes for you, when navigating your car in a strange city[1]: Finessing project plans to present useful information at the right level of detail is not easy, decisions have to be made! Take a typical risk register, if you tried listing every conceivable risk, the document would emulate the ‘coastline paradox’, and be of almost infinite length, which means the register is never finished and the project does not start. Conversely, miss one or two significant risks and the project team may have a very unpleasant experience, possibly causing the project to fail. Pragmatic guidelines about the risks to be considered are needed and these have to be tailored to the project. Similar guidelines are needed for the schedule, cost plan and all of the other sub-plans needed for a project. How much detail do you feel is appropriate for your projects? [1] Image source: Understanding Design, The challenge of informed consent. Dr. Lynda Bourne, 27th November 2014; maps of North Sydney |
How To Succeed At Deliverable Scheduling
By Kevin Korterud
When I first started as a technology project manager, it was not uncommon for a project to have just one deliverable. All of the tasks in the project created the path that led to the single deliverable, which in many cases was a program, report or screen. Life used to be so easy! As projects became more complex, the need grew for multiple project deliverables that lead to a complete solution. Deliverables now represent the “building blocks” that form a key foundational element of any project. Whereas scheduling tasks is a fairly straightforward process that involves capturing durations, resources and successor/predecessor networks, scheduling deliverables comes with its own set of complexities. Deliverables don’t always behave in a linear manner like tasks—so special considerations come into play with their scheduling. In addition, there are typically people and expectation factors that need to be part of a deliverable scheduling model. Here are three essential reminders for properly scheduling deliverables:
Whereas tasks are singular items that stand alone in a work plan, deliverables have a few extra packaging steps in their path to completion. One of the most dangerous scheduling mistakes to make with deliverables is to have a single task in a work plan that represents the deliverable. This is because of the variation in duration and effort that it takes to complete a deliverable. Deliverables have a natural path to completion that involves a package of tasks, whose dynamics differ from normal tasks in a work plan. Project managers need to include these extra tasks that chart the lifecycle of a deliverable from initiation to completion. For example, a sample set of deliverable task packaging would appear as follows:
You can tell from the above table that prior to scheduling deliverable task packages, project managers need to have a deliverable governance process in place. A deliverable governance process that identifies specific deliverable reviewers and a single approver are key to the effective scheduling of deliverables.
2. Deliverables May Require Task-like Linkages We are all familiar with creating predecessor or successor linkages between tasks to form a linear series of work needed to achieve an outcome. Those linkages serve to drive schedule changes as prevailing project conditions occur. Deliverables can require the same sort of linkages found in tasks. For example, if you have deliverables that lead to the creation of a marketing web page that involves multiple supplier deliverables, selected tasks in the deliverable package can contain task linkages. These linkages impose conditions which determine the pace at which related deliverables can be completed. Let’s say there are three design documents from different suppliers required to create an overall design document. The build of the overall design document cannot finish before those three supplier design documents are all approved. So in the work plan, delays and schedule movements in the supplier design deliverables will drive the true completion date of the overall design document.
In addition to the scenario of having deliverables with dependencies, it is just as likely to have a set of deliverables that do not have any dependencies at all. These deliverables need to be completed by the end of the project but do not directly figure into the final outcome of the project. These are often process improvement deliverables that are needed for future projects that are not ready for execution. When a project manager has a slate of unrelated deliverables, the optimal approach is to bundle them into agile-like sprints. The content of each deliverable sprint is determined by a balance of resource availability for the people who build, review and approve deliverables, as well as any form of relative priority. For example, if deliverable reviewers have low availability during a scheduled deliverable sprint, those deliverables can be pushed to a subsequent deliverable sprint. Priority can also determine the content of deliverable sprints. Higher priority deliverables would displace lower priority deliverables to future sprints, even if work has begun on those deliverables. For example, if there is a strong need for a certain tool to be used by multiple projects, those deliverables would move into the current deliverable sprint. The deliverable sprint process allows for agility, while balancing value created from the deliverables.
As I shared earlier, life was so much easier when projects created one deliverable. Different times demand different approaches to managing deliverable schedules—especially on large transformations where there could be hundreds of dependent and independent deliverables. The last thing anyone wants to do is insufficiently manage deliverables: Leaving out one of those “building blocks” might cause the house to fall over. What tips do you have for deliverable scheduling in today’s project ecosystem? Share your thoughts in the comments below.
|
Predicting the Future in Project Management
By Ramiro Rodrigues
In the 2009 film Knowing, a boy finds a time capsule filled with documents from decades ago. His father, an astrophysics professor, then discovers that the messages list some recent and impending major disasters, and even predict a global calamity in the near future.
Apocalyptic visions of an imminent end to the world have always brought joy to the film industry—but they bump into the same logical limitations that are still impossible to overcome. As far as we know, we do not have an effective technology capable of predicting the future. Whether it is related to weather forecasting, economics or sociology, we are not able to tell, at present, precisely what will happen at a specific moment in the future.
What we have always had is a great will to take a chance and get it right. Since the beginning of time, man has ventured to predict the future and, during these attempts, we’ve come up with an ocean of predictions that have been proven wrong. But we don't give up.
A New Model of Scheduling
In today’s organizations, modern project management has to meet the need for schedule development that seeks, in a deterministic fashion, to set the estimated dates of future events related to people, project deliveries and work that will be executed. This usually is a great Achilles' heel in the field of project management. The organizational frustration that results from estimated scheduled activities that turn out to be incorrect is very common.
Why don’t they happen as expected? There are different reasons, usually related to people and intrinsic characteristics of the expected activities. But in essence, they happen because it still is impossible to predict the future. Of course, there are some strategies that can help mitigate the risks of the deterministic forecast, but in the end, they are only predictions.
However, we must understand that organizations need to estimate when the returns on their investments will be accessible for use. Some executives will say that there is no progress without clear and foreseen goals.
That’s right. But how do we get out of this complex scenario in which future dates are determined but do not happen as planned?
One trend that has been applied by industries such as consulting, engineering and research & development is the probabilistic forecast of schedules. In this case, with the assistance of simple statistical concepts, the forecasts of the activities and of the project are viewed as a whole, with probability ranges to conclude them.
It is not solely a mathematical solution; the change is conceptual. The idea is no longer to set, within the organization, the delivery estimates at certain dates grounded on the expectation that they will come true. Rather, the goal is to present length ranges that provide the company with a perspective that there is, for instance, a 68 percent, 95 percent or 99.7 percent chance that the project delivery will take place during the expected dates.
This change in principle allows for the understanding that one can never be 100 percent sure of what will happen in the future but, at the same time, enables the management of the risks involved with reasonable control.
This planning model can bring, in the near future, more maturity and quality to the management of schedules and deliveries.
Do you use this model in your organization? Share your thoughts below. |
Plan for the Velocity of Change to Keep Increasing!
Categories:
Agile,
Best Practices,
Career Help,
Change Management,
Complexity,
Facilitation,
Generational PM,
Human Aspects of PM,
Human Resources,
Innovation,
Innovation,
IT,
Leadership,
Leadership,
Lessons Learned,
Portfolio Management,
Program Management,
Project Planning,
ROI,
Stakeholder,
Strategy,
Talent Management,
Teams
Categories: Agile, Best Practices, Career Help, Change Management, Complexity, Facilitation, Generational PM, Human Aspects of PM, Human Resources, Innovation, Innovation, IT, Leadership, Leadership, Lessons Learned, Portfolio Management, Program Management, Project Planning, ROI, Stakeholder, Strategy, Talent Management, Teams
By Peter Tarhanidis, Ph.D., M.B.A. Today, developments in emerging technology, business processes and digital experiences are accelerating larger transformation initiatives. Moore’s Law means that we have access to exponentially better computing capabilities. Growth is further fueled by technologies such as supercomputers, artificial intelligence, natural language processing, Internet of Things (IoT) and more across industries. Emerging Tech Business Process Maturity According to market research group IMARC, automation and the IoT are driving growth in business process management (BPM); the BPM market is expected to grow at a 10 percent compound annual growth rate between 2020 and 2025. Customer Experience Customer experience is redefining business processes and digitizing the consumption model to increase brand equity. Gartner reports that among marketing leaders who are responsible for customer experience, 81 percent say their companies will largely compete on customer experience in two years. However, only 22 percent have developed experiences that exceed customer expectations. Economic Forces The Way Forward I’ve developed a few guidelines to help navigate this change:
Change is now inherent and pervasive in the annual planning process for organizations. Given that, I like to ask: What is the plan to prepare staff and colleagues to compete in this hyper-transformation age? What observations have you made to keep up with this new era’s velocity of change? |