5 Tips to Onboard New Team Members
|
By Yasmina Khelifi, PMI-ACP, PMI-PBA, PMP A few years ago, I replaced a contractor who was an expert in his field. We met once a week, and he answered my questions. But the domain was new to me. He was an expert, and I was not—so I thought it was normal that I didn't understand it. He didn't write documents for me. So when he left, I spent difficult months catching up on things. Fortunately, I worked with a helpful technical expert. Then I wrote the necessary documents. We also developed a short training course. Since then, I have had to onboard colleagues, and I could use this documentation. I belong to many teams at work (and in the volunteering setting), and I’d like to share some thoughts on how this kind of transition can be better handled. Let's call Moa, your new team member. 1. Think of the needs of the newbie. When you onboard someone new, you first need to understand what they need. This is not about you; this is about Moa. You need to take into consideration some questions: a. Big picture vs. task only: Some people need to have the big picture to understand. Others need to understand only their sandbox. b. Learning methods: How does Moa learn and memorize?
c. Learning rhythm: What is Moa’s rhythm to learn? I am a bit impatient and need to know what is expected from me from the outset. If I don’t know it, I become anxious. Sometimes I get feedback like “Relax! You have time.” It doesn’t reassure me. On the contrary, it makes me nervous and a bit upset because by these words, I feel like people are not listening to my needs. d. Face-to-face meetings: If Moa is a remote team member, you’ll have to talk with his manager to plan a face-to-face meeting quickly after he joins. Perhaps a longer visit will be advantageous (and a great opportunity to gather the whole team together). 2. Define the best approach. Once you have had these first conversations, you can tailor an onboarding plan. Onboarding doesn’t stop the first week—it is a journey that can take several months and can take different forms:
3. Demystify languages. You will also be Moa’s “translator.” The language of your team includes:
These are the kinds of things you cannot get from training. Perhaps you have a glossary, or you can create one. 4. Uncover the unspoken rituals. When it comes to rituals, people often think of coffee breaks or after-work social gatherings. But rituals also encompass practical things about ways of working. Perhaps Moa is more interested in those items than the coffee breaks. You can anticipate answering the following questions:
5. Start early…and include everyone. With the overload at work and deadlines to catch up, your team member sometimes isn't in a hurry to train Moa. That doesn’t mean they don’t want to help him. But onboarding someone takes more time than expected. We all manage things without writing them down. Or a process is written, but after a while, we adapt it without updating the written process. Because of that, a 30-minute conversation can last longer than expected. Moa may ask many questions, like me. Welcoming a new member is not only the responsibility of the manager. It is even more important if Moa already works in the company. The onboarding process can start before with a handover period. Moa can begin to meet his colleagues and exchange with them. Onboarding new members is a key process in the life of a team. It is an opportunity to strengthen ties, and also a learning opportunity for everyone. What other things do you plan to onboard new team members?
|
4 Pitfalls of an External Product Owner
|
By Christian Bisson Within the realm of agile project management, the composition of a team greatly impacts its success. While all team members play a vital role, the inclusion of an external product owner (as opposed to an internal one) poses challenges that can hinder teams’ potential to deliver value to users. In this post, I will highlight four potential pitfalls of having a product owner external to the team, with real-life examples underscoring the benefits of an integrated team approach.
1. Misalignment and Unclear VisionWhen a product owner is external to the team, misalignment and an unclear vision can arise. The absence of direct day-to-day collaboration stifles the shared understanding of project goals, priorities, and user needs. This lack of alignment makes it difficult for the team to make informed decisions and deliver a product that meets customer expectations. Example: Imagine a software development project where the product owner is external and has limited interaction with the team. This separation hinders effective communication and prevents the product owner from gaining in-depth knowledge of the project domain. As a result, misaligned priorities and a fuzzy vision emerge, leading to a disconnect between the team's efforts and the desired outcomes.
2. Inefficient Prioritization and Decision MakingAn external product owner often leads to inefficient prioritization and decision-making processes. Without a direct line of communication, the product owner's expertise and insights may not reach the team effectively. As a result, crucial decisions regarding scope, timelines and trade-offs may be delayed or misinterpreted, leading to project inefficiencies and missed opportunities. Example: In a marketing campaign project, an external product owner who lacks real-time interaction with the team may struggle to grasp the evolving market trends and user preferences. Consequently, delays in decision making occur, preventing timely adjustments to the campaign strategy, ultimately impacting its effectiveness and return on investment.
3. Communication Gaps and Feedback DelaysWith an external product owner, communication gaps and feedback delays become commonplace. The limited availability and reduced involvement of the product owner hinder continuous communication and the timely exchange of information. This results in a slower feedback loop, preventing the team from promptly addressing concerns, adapting to changing requirements, and delivering high-quality increments. Example: In a mobile app development project, an external product owner may have competing priorities and limited availability for sprint reviews. As a result, feedback on delivered iterations may be delayed, preventing the team from incorporating valuable insights—and potentially leading to inefficient use of development resources.
4. Detached from User-Centric MindsetWhen the product owner is external, the team risks losing touch with a user-centric mindset. The direct contact between the product owner and end users diminishes, inhibiting the team's understanding of user needs, preferences and pain points. Without this critical insight, the team may struggle to develop solutions that truly resonate with the target audience. Example: Consider an e-commerce project where an external product owner has limited interactions with actual customers. The team, lacking direct access to user feedback and insights, may fail to anticipate user behavior, resulting in an e-commerce platform that falls short of meeting customers' expectations and inhibits business growth.
ConclusionIn the agile realm, the inclusion of an external product owner introduces several pitfalls that can hinder project success. Misalignment, inefficient decision making, communication gaps, and a detached user-centric mindset are among the challenges an integrated team approach aims to mitigate. By recognizing the drawbacks of an external product owner, agile teams can foster collaboration, transparency, and a deep understanding of customer needs, ultimately leading to more successful project outcomes. The above points assume there is one external product owner for the team. However, if there are multiple external product owners in a team, all the challenges mentioned earlier become even more significant. It not only amplifies the existing issues, but also adds to the tension and confusion within the team. |
Predicting Completion in Agile Projects
Categories:
Agile
Categories: Agile
| By Dr. Lynda Bourne
The generally accepted way of assessing progress on a project, and predicting its completion, is to use a critical path method schedule. However, the CPM paradigm does not work across a wide range of projects where there is no predetermined sequence of working that must be followed. There may be a high level “road map” outlining the desired route to completion and/or specific constraints on the sequencing of parts of the work but in most agile projects, the people doing the work have a high degree of flexibility in choosing the way most of the work is accomplished. The focus of this post is to offer a practical solution to the challenge of assessing progress, and calculating the likely completion date in agile projects. WPM as an Alternative to ES and CPM The function of WPM is to assess progress and calculate a predicted completion date in a consistent, repeatable, and defensible way by comparing the amount of work achieved at a point in time with the amount of work planned to have been achieved at the same point in time. Then based on this data, you calculate an expected completion date. The Theoretical Basis of WPM WPM Terminology
From this information, the work performance measures are calculated as follows:
Applying WPM to a Project Using Scrum
This leaves 16 weeks for productive work; therefore, the first stories should be delivered at the end of the first productive sprint, Week 4, and all stories by the end of Week 18. This means the rate of planned production between the start of Week 2 and the end of Week 18 is 86/16 = 5.375 story points per week. Based on these assumptions, at the end of Week 4 (two weeks of production), we can expect 10+ story points to be complete, and at the end of Week 18 all 86 story points complete. The rest of the planned distribution is simply a straight line between these two points. We know sprints will not take exactly two weeks every time (some will overrun, and occasionally some will finish early), and we also know the number of story points generated in each sprint will vary. But on average, if the two sprint teams together are not completing a bit over 5.3 story points per week, every week, the project will finish late. Once this basic rate of production has been determined for the project, WPM measures the actual work delivered (WA) and shows the time variance at time now (TN) and uses this information to predict the expected completion (EC). For example, at the end of Week 8, three sprints should have been completed by both teams, and we are expecting 30 story points complete. But only 23 have been delivered. Velocity calculation will indicate more sprints will be needed, and the burndown chart will show the work is behind plan. But what does this mean from a time perspective? A look at the planned rate of production will show 23 story points should have been finished during Week 7 (the actual fraction is 7.3). Therefore, the work is 0.7 weeks (3.5 working days) late. The work performance index (WPI) is 0.9125. Dividing the original duration (20 weeks) by the WPI suggests the revised duration for the project is 21.9178 weeks; the variance at completion is -1.9178 weeks, or 13.4 calendar days late. If these calculations look similar, they are based on the well-tried formula used in earned value management and earned schedule—all I’ve done is shift the metric to a direct measure of the work performed. Conclusions The two requirements to implement WPM are:
The metric used can be a core deliverable (e.g., 2,000 computers replaced in an organization), or a representation of work such as “story points,” or the monetary value of the components to be delivered to the client. Peripheral and support activities can usually be ignored when establishing the WPM metric; they rarely impact the project delivery independently. Failures in the support areas typically manifest in delays to the primary delivery metric. Questions? |
Supercharging an Organization’s Performance to Achieve its Mission
Categories:
Social Responsibility,
Portfolio Management,
Tools,
Best Practices,
Strategy,
Mentoring,
Metrics,
Career Development,
Stakeholder Management,
Innovation,
Change Management,
Leadership,
Lessons Learned,
Program Management,
Benefits Realization,
Complexity,
Information Technology,
Teams,
PMO,
Communications Management
Categories: Social Responsibility, Portfolio Management, Tools, Best Practices, Strategy, Mentoring, Metrics, Career Development, Stakeholder Management, Innovation, Change Management, Leadership, Lessons Learned, Program Management, Benefits Realization, Complexity, Information Technology, Teams, PMO, Communications Management
|
By Peter Tarhanidis, Ph.D. There is a dramatic increase in the strategies corporations implement to meet the needs of their stakeholders. Driving value from all parts of an organization and its functions may seem like repetitive exercises—and even feel more like a medieval gauntlet with only a few successful programs. HBR (2021) wrote that by 2027, about 88 million people will be working in project management—with economic activity reaching $20 trillion USD. Also noted: Only 35% of projects are successful, leaving immense waste of resources. There are many reasons projects fail. HBR (2021) states of the 70% of failed projects, and after exhaustive root-cause analysis across all industries, one can identify common themes such as undervaluing project management skills and methods, and poor performance. Yet organizations that apply project management methods recognized their performance had a 2.5 more times chance to be successful, and organizations can waste 28 times less resources. As such, when applied, the implementation of PM methods works. Yet in a world filled with a variety of project taxonomies, many organizational boards are now contemplating the need to implement environmental, social and corporate governance (ESG) and corporate social responsibility (CSR) programs. Forbes states the benefits of ESG and CSR initiatives include:
Therefore, to ensure success for ESG and CSR programs, an organization’s top leaders need to prioritize and align across all the organization’s businesses. Leaders can use the balanced scorecard to achieve this alignment, and can extend its use across the entire project portfolio. This theory was developed by Kaplan and Norton, which state the balanced scorecard method converts the organization’s strategy into performance objectives, measures, targets and initiatives. Linking the concept of cause and effect, the balanced scorecard covers four perspectives:
Marr (N.B.) reported over 50% of companies have used this approach in the United States, the United Kingdom, Northern Europe and Japan. One clear benefit has been to align the organization’s structure to achieve its strategic goals. In conclusion, applying project management methods and aligning an organization’s performance through the balanced scorecard can unlock ESG and CSR benefits that can supercharge a company’s efforts to achieve its mission. References |
Uncover Your Working Identities as a Project Manager
|
By Yasmina Khelifi, PMI-ACP, PMI-PBA, PMP What’s the next step in your project management career? For some people, it’s hard to know what your mission is. For others, they like their jobs and also have side projects. And for some, their side projects become their day jobs. I’m reading Working Identity, a very insightful book by Dr. Herminia Ibarra, an organizational psychologist. The book is about career transitions and how to find the next step in your career. The author describes a career transition framework in three steps, based on her research and in-depth interviews:
Reading this book, I wanted to share some thoughts about working identities as a project manager. Why is this important? According to me, it helps you build your career in the project management world and develop your elevator pitch. It also helps you to be more self-aware and self-confident in your abilities. Possible selves as a project manager I observed how other PMs behaved and what was valued by the organization. There were project manager role models in the organization. I remember I tried to be stricter than I wanted to sometimes because I observed other people behave that way, so and I thought it was the right way to act. But were they the role models I wanted to identify with? I wanted to take more time to onboard people. I developed documents, a glossary and an annex. No one asked me to do so, but for me it was the right approach. But I was not sure if it was the best path to follow. So my formative years were full of questions, wrong assumptions and hesitations. I did not have a mentor in project manager, but I got feedback from my managers, my peers and my colleagues. I got more negative feedback than positive—or at least I listened more to the negative feedback:
These first working experiences contributed to the perception I had of myself, the labels and competences I thought I had—or needed to work on. As years passed, I gained more self-confidence and developed different selves. I was initially a technical project manager, and I was proud of being technical and keeping up with the team. I’m now more of a leader project manager—facilitating solutions, creating collaborations across the globe. If people tell me, “You’re not technical,” I reply: “I have a technical background, but don’t expect to become a technical expert.” And I’m comfortable with that answer. Let us apply the framework described in the book to help inform how you move forward in your project management career: 1. Crafting experiments Do you want to work in a new industry? Perhaps you can volunteer in an organization there? By exploring new paths, you’ll better define what you enjoy (and don’t). Sometimes, we have long dreamt of ideal roles and work. But in reality, they are not always the right fit. 2. Shifting connections Don’t limit yourself to just project management communities. I’m part of a coaching community and a marketing one. Are you afraid of not fitting in? Don’t worry—you’ll learn step by step. Exchange ideas and experiences with people by chatting (online or in person). 3. Making sense We are all comprised of multiple traits, and we run multiple projects at work and in life. We have to acknowledge our diversity. What working identities do you have as a project manager?
|










