question
Network:382



Q :project manager has developed risk responses for the list of high-ranking risks created in the Perform Qualitative Risk Analysis process. She was planning to go on to the Control Risks process when she was reminded by another project manager that she forgot to do something important in the Plan Risk Responses process. Which of the following did she forget?

A- She has not created workarounds.
B- She has not analyzed secondary risks.
C- She has not created an overall risk ranking for the project.
D- She has not created a prioritized list of quantified risks
Sort By:
Network:233



Ans is C
Network:4297



Answer: B

Selected risk response strategies may cause additional (secondary) risks to occur.
Analyzing secondary risks is part of the Plan Risk Responses process.
Network:468



D
after qualitative she must perform quantitative risk analysis
Network:56



D. The question talks about Plan Risk Responses process. Qualitative analysis is done. Quantitative analysis was forgotten.
Network:244



B.
Network:1623



D.
Network:8423



Maybe you should post as poll in order to check the % of answers.
...
1 reply by NEHRU NAGAPPAN
Dec 28, 2016 12:20 PM
NEHRU NAGAPPAN
...
agree
Network:481



Dec 27, 2016 12:00 PM
Replying to Mayte Mata-Sivera
...
Maybe you should post as poll in order to check the % of answers.
agree
Network:64717



B.