What's in YOUR sprint backlog?

From the Easy in theory, difficult in practice Blog
by
My musings on project management, project portfolio management and change management. I'm a firm believer that a pragmatic approach to organizational change that addresses process & technology, but primarily, people will maximize chances for success. This blog contains articles which I've previously written and published as well as new content.

About this Blog

RSS

Recent Posts

Leading Through Crisis Means Leading Through Context

"It's the end. But the moment has been prepared for." - retirement lessons from the Doctor

Just because they are non-critical, doesn't mean they are not risky!

Just because they are non-critical, doesn't mean they are not risky!

How will YOU avoid these AI-related cognitive biases?

Categories

Agile, Artificial Intelligence, Career Development, Change Management, Communications Management, Decision Making, Governance, Hiring, Kanban, Lessons Learned, Personal Development, PMO, Portfolio Management, Project Management, Resource Management, Risk Management, Risk Management, Schedule Management, Scheduling, Tools

Date

linkedin twitter facebook Request to reuse this  

Categories: Agile, Project Management


The Scrum Guide states that a sprint backlog "is the set of Product Backlog items selected for the Sprint, plus a plan for delivering the product increment and realizing the Sprint Goal. The Sprint Backlog is a forecast by the Development Team about what functionality will be in the next Increment and the work needed to deliver that functionality into a "Done" Increment."

We expect to find requirements, enhancements and even fixes in the sprint backlog, but is that it?

Remember that one of the three pillars of Scrum and a key principle of most agile approaches is transparency. Meaningful, significant work should be visible to all as agile doesn't encourage hidden factories. If we don't surface all major work being done by the team, it is understandable that a Product Owner or other stakeholders might assume that there isn't a lot of work being done in a sprint or that the team isn't being productive.

We can separate work which is worth being made visible into three broad categories:

  • Work items which directly add customer value to the product. Features, requirements, enhancements and fixes fall into this bucket. Learning activities such as spikes would also qualify.
  • Work items which indirectly enable or are required for product delivery. Environment support, deployment management, regulatory documentation are examples of this category.
  • Work items which improve the delivery process. Improvement ideas from retrospectives are one type of such work item

By sizing, prioritizing and tracking work items across all three of these categories, a Product Owner and team will gain a complete understanding of what they expect to work on in a given sprint. This encourages healthy trade-off conversations during sprint planning and will help the team identify opportunities for improvement which might otherwise have been missed. For example, if some team members are spending significant effort in keeping build and test environments operational, the Product Owner or other stakeholders might be more inclined to understand why this is needed and what they can do to reduce that effort.

There is a fourth category which you may not want to include in the sprint backlog, and that's the activities performed by the team which are completely unrelated to the product or project. This could be year end employee performance assessments, town hall meetings, operational work or (hopefully not!) even supporting another project. Assuming team members have some insights into how much of their availability over the next sprint will be consumed by this unrelated work, they should communicate that to the rest of the team during sprint planning to ensure a reasonable sprint commitment is made.

So, with thanks to Capital One, what's in YOUR sprint backlog?


Posted on: January 13, 2019 07:00 AM | Permalink

Comments (8)

Please login or join to subscribe to this item
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Kiron - I am not sure how adding the fourth category to the product backlog will add value to the product itself ? Do you mean having a separate sprint for doing so ?

avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Rami - the fourth category should NOT be added to the sprint backlog for that very reason :-)

Kiron

avatar
RAJESH K L Project Manager, PMP| Bharat Electronics, Bengaluru, India Bengaluru, Karnataka, India
Kiron, Good post. categorisation of work items to be added to sprint backlog will bring clarity to all stakeholders.

avatar
Drew Craig Sr. Agile & Product Coach| Vanguard Philadelphia, Pa, United States
Only value-add items! Our Sprint backlog is exposed through Jira and socialized regularly during throughout the Sprint. An item with no value has no point(s) :)

avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Thanks Andrew - but does that include activities which will indirectly improve value delivery?

avatar
Deepesh Rammoorthy ICT Project Manager ( PMP®AgilePM®Certified ScrumMaster® (CSM®))| Australian Red Cross Blood Service Tarneit, Vic, Australia
My current sprint backlog has items from the first two categories that you have outlined.

avatar
John Farlik Program & Project Management| SPX FLOW Waxhaw, Nc, United States
I've seen teams add that fourth category in completely different epics. For capacity planning purposes they could be put into the backlog. For example, if there is some work that the org identifies that is lower priority that can be done as there is capacity to do it--these may be some of the 4th category items Kiron is mentioning. Just a thought :)

avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Kiron, I thought so too but got confused with what you wrote so wanted to clarify :-)

Please Login/Register to leave a comment.