Proactive dependency management with agile approaches

From the Easy in theory, difficult in practice Blog
by
My musings on project management, project portfolio management and change management. I'm a firm believer that a pragmatic approach to organizational change that addresses process & technology, but primarily, people will maximize chances for success. This blog contains articles which I've previously written and published as well as new content.

About this Blog

RSS

Recent Posts

Leading Through Crisis Means Leading Through Context

"It's the end. But the moment has been prepared for." - retirement lessons from the Doctor

Just because they are non-critical, doesn't mean they are not risky!

Just because they are non-critical, doesn't mean they are not risky!

How will YOU avoid these AI-related cognitive biases?

Categories

Agile, Artificial Intelligence, Career Development, Change Management, Communications Management, Decision Making, Governance, Hiring, Kanban, Lessons Learned, Personal Development, PMO, Portfolio Management, Project Management, Resource Management, Risk Management, Risk Management, Schedule Management, Scheduling, Tools

Date

linkedin twitter facebook Request to reuse this  

Categories: Agile, Project Management


When we are managing projects using a predictive delivery approach, dependency identification and tracking is done as part of the BPUF (Big Planning Up Front) exercise using the activities from a work breakdown structure and the collective wisdom of our team members and key stakeholders. If a major scope or solution approach change is identified afterwards, the impacts of addressing new dependencies is usually considered in the analysis of the change request.

But on those projects which follow an adaptive lifecycle, this gets a bit trickier. Given the emergent nature of requirements and design, we are only able to see dependencies to the extent of our team's "headlights" which might just be showing us the next two weeks of work. A team might have "Have all dependencies been identified and captured?" as a guideline within a Definition of Ready (DoR) but that doesn't always mean that it is possible to satisfy that dependency just-in-time.

We always strive to build a whole team which possesses all of the skills and authority needed to deliver the full scope of the product or project.

But sometimes, we need a subject matter expert for a small subset of the product features and if we don't identify that need early enough, we won't be able to deliver those features in a timely manner. In addition, building a whole team in larger organizations is often challenging as there are established delivery or control partner teams who must contribute to specific product features but won't necessarily be available at a moment's notice.

One way to reduce the risks associated with dependencies being identified too late is the combination of upfront story mapping with ongoing look ahead planning.

Story mapping provides an opportunity to bring together key delivery and control partners to review the high-level stories which the Product Owner and team are identifying. Giving these external partners a chance to indicate which stories they are interested in will help the team know who they need to line up as the time approaches to complete one of those stories. Based on how high those stories show up in the story map, they will understand how soon they might need to be engaged. Team members can also start to identify and capture the inter-dependencies between individual stories to help the Product Owner with backlog prioritization.

As stories with dependencies start to move up the backlog, as part of a look ahead planning activity, the team can proactively contact the external partners to request their participation a sprint or two into the future.

Planning is an ongoing activity with adaptive approaches so without this, an external partner your team needs is likely to respond with the old cliche: "A lack of planning on your part does not constitute an emergency on my part."

 


Posted on: April 07, 2019 07:00 AM | Permalink

Comments (10)

Please login or join to subscribe to this item
avatar
Tarik Chougua Project Manager| CEPEO Ottawa, Ontario, Canada
Thank you.

avatar
Girija Ramakrishnan Chennai, Tamilnadu, India
Very good points, Kiron. In my current projects this is what exactly we are trying to do.

Thanks for sharing !!

avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Thanks Girija & Tarik!

avatar
REZA MOKARRAM AYDENLOU Tehran, Iran (Islamic Republic of)
Thank you very much for your efforts.it's very good Topic.

avatar
Glenn Chundrlek Project Manager| Belcan Loveland, Oh, United States
This is why a Scrum Team needs a Product Owner who has the ability and willingness to do these planning activities. I think they should be a major component of the backlog review.

avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Thanks Reza! Totally agree, Glenn - a PO is accountable for the content and priority of the backlog and ensuring that the right discussions are happening is a shared responsibility between the PO and team.

avatar
Drew Craig Sr. Agile & Product Coach| Vanguard Philadelphia, Pa, United States
Thanks, Kiron! Dependency identification and tracking are vital to ensure avoid surprises along the way. I appreciate these insights.

avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Thanks Andrew!

avatar
Suzi MS United Kingdom
Thanks for the sharing interesting post!

avatar
Liliya Sablukova, MBA, PMP, CGFO Sarasota, FL, United States, United States
Thank you.

Please Login/Register to leave a comment.

ADVERTISEMENTS

"Things should be made as simple as possible, but not any simpler."

- Albert Einstein

ADVERTISEMENT

Sponsors