Six sins with work boards

From the Easy in theory, difficult in practice Blog
by
My musings on project management, project portfolio management and change management. I'm a firm believer that a pragmatic approach to organizational change that addresses process & technology, but primarily, people will maximize chances for success. This blog contains articles which I've previously written and published as well as new content.

About this Blog

RSS

Recent Posts

Leading Through Crisis Means Leading Through Context

"It's the end. But the moment has been prepared for." - retirement lessons from the Doctor

Just because they are non-critical, doesn't mean they are not risky!

Just because they are non-critical, doesn't mean they are not risky!

How will YOU avoid these AI-related cognitive biases?

Categories

Agile, Artificial Intelligence, Career Development, Change Management, Communications Management, Decision Making, Governance, Hiring, Kanban, Lessons Learned, Personal Development, PMO, Portfolio Management, Project Management, Resource Management, Risk Management, Risk Management, Schedule Management, Scheduling, Tools

Date

linkedin twitter facebook Request to reuse this  


Regardless of what type of work your team does, work boards can be a helpful tool. But just because they can be helpful doesn't mean they are always implemented well.

The most common mistake is when teams don't keep their work boards up to date with the actual status of work that is being done. Increasing transparency is a great way for stakeholders to understand what is going on and to increase their level of trust in teams. But if the information being presented is out of date or inaccurate, it reduces the team's credibility and increases the likelihood of these stakeholders asking for separate, redundant status updates. When a work item changes status the work board should be updated immediately. For example, if the team has capacity to pull a new work item from their work queue, the item should be moved on the board just before work actually commences on that item.

Another challenge relates to whose responsibility it is to keep the board up to date. The moment it becomes the job of a coordinator or lead to do so, we reintroduce the overhead of having someone chase team members for status updates. I have seen Scrum Masters who will take time out during a daily Scrum/standup event to update the team's work board after a team member has mentioned that it doesn't accurately show the status of their work items. Everyone on the team is responsible for updating the work board based on the work they are doing.

If the work board columns are aligned with the roles of team members, that is not ideal. A work board's columns should reflect the progressive value being added to a work item till it is complete and very rarely would this evolution map cleanly to the team member's individual roles. The Goldilocks' principle also applies to the columns. Have too few, and stakeholders may not get sufficient visibility into work item status and work items might stall for longer than desired without impediments being addressed. Set up too many and it encourages silo-thinking on the part of team members and can result in increased work in progress.

Having a dedicated blocked column is also not a good idea. Blocked is not a normal step in the evolution of a work item and by moving partially completed work items over to a separate column it can affect flow as a natural tendency of a team might be to pull more work items from the queue rather than unblocking the stalled work item. A better approach would be to highlight blocked items within their active work columns.

The next sin relates to work item aging. Ideally, once the team has completed a reasonable number of work items, they will be able to determine what is a reasonable amount of time for a work item of a certain size to remain active. If there isn't some way for the team and stakeholders to see how long a work item has remained in an active column (i.e. something other than Not Started or Done), then it is hard to proactively determine whether it has been aging longer than it should.

Finally, cluttering a work item card with too much information increases the potential for stakeholder confusion and for inaccurate data. At the bare minimum, a work item card should contain the description of the work to be done, key dates (e.g. requested, started), whether it is blocked or not, and which team members are working on it. Anything beyond this can be helpful, but also increases the effort required for team members to keep information current and accurate.

Work boards can be a powerful tool to help a team visualize their work flow, but as always, with great power comes great responsibility.


Posted on: December 05, 2022 09:00 AM | Permalink

Comments (8)

Please login or join to subscribe to this item
avatar
Luis Branco CEO| Business Insight, Consultores de Gestão, Ldª Carcavelos, Lisboa, Portugal
Dear Kiron
Very interesting the theme that brought to our reflection and for debate
Thanks for sharing and for the six sins with work boards

avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Thanks Luis!

avatar
Stéphane Parent Self Employed / Semi-retired| Leader Maker Prince Edward Island, Canada
Thanks, uncle Ben! :)

avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Uncle Ben's advice applies in some many contexts, Stéphane!

avatar
Eduard Hernandez
Community Champion
Product Operations Program Manager Barcelona, Cataluña, Spain
Had to Google what the Goldilocks' principle was. Always good to learn new things ;-)

Regarding Tools, MS has done a good job in adding the Planner functionality in SharePoint/Teams.

avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Thanks Eduard!

avatar
Mayte Mata Sivera PMO Leader | Speaker | Author Ut, United States
Great read and advice. Thank you for sharing this valuable information.

Work boards are essential imho!

Please Login/Register to leave a comment.

ADVERTISEMENTS

It's the old gag: people that pay for things never complain. It's the guy you give something to that you can't please.

- Will Rogers

ADVERTISEMENT

Sponsors