The DrunkenPM meets Personal Kanban
|
For the past 18 years I have been developing my skills at helping people manage the work they have to do into a state of ninja-like perfection-ish. As I have progressed in my career I have had the good fortune to work on projects of varying size, duration and cost. Some have been successful, but more have not – and that is okay because those are the ones where I’ve learned the most. To demonstrate my proficiency in my chosen profession I have obtained multiple certifications to prove I know how to manage work in both a traditional approach and an Agile approach. I’ve even spent years teaching others how to get those same certifications. Along the way I also got an MBA to demonstrate… whatever it is an MBA is actually supposed to demonstrate beyond that I am willing to be in debt until I go to my grave. And I’ve given up thousands of hours of personal time leading volunteer organizations that focus in managing work and teaching people how to get better at it. After all that, I feel it is fair to say I am fairly well versed in how to manage projects and I’m pretty good at it. My experiences have taught me many things… most of them the hard way. And with this, I have found only one single truth that spans all of it:
In fact, I think it is fair to say I pretty much suck at managing my own work. I’m not saying I am not good at getting things done. I get stuff done all day long, and usually, it is the most important stuff. But I’m not good at managing it.
When I started working in project management, this was not a problem. It was 1995. I did not have a cell phone. I had one email account and I could log into AOL from home or work via my 14.4 modem. There was literally only so much information I could access in a day. Compared to now, the information overhead I faced on a daily basis was pretty light. My weekly to do list usually looked something like this: This is a sheet of notebook paper folded in half 3 times, so that each side contains 8 boxes just like the one above. When the section of the paper got too crowded, I’d copy the open items to a new section and start again. A single sheet of paper torn from a notebook could usually take care of my list of to-dos for 2-3 weeks. (This was how we did things back in the olden days before the Palm III.)
As much as I love MI-5, I didn’t think I’d be able to cope with losing Tom, Zoey and Danny again, so I decided to do something about it. And, since one of the main things I do for a living is teaching Agile, I decided to practice what I preach and started getting set up to give Personal Kanban a try. I’m writing this after 5 weeks of my own attempt at Personal Kanban. I've been holding a retrospective once a week and keeping a journal on how it is going. My current plan is to keep working with it and experimenting with different practices to see what works for me and what doesn’t. I’ll be posting back to this blog about once every two weeks with updates on what I’ve learned and what I’m going to try next.
A friend of mine once told me that when he met with new clients about Agile Transformation, he tried to focus on making sure they understood that Agile was not going to make them faster, but it would make the broken ugly things so obvious that they’d have no choice but to deal with them. I’ve seen that happen over and over in my own work. I am happy (and totally annoyed) to report that the exact same thing happens when you apply the practices at a personal level.
If you are interested in learning more about how to apply Kanban to managing your personal work, you might try Personal Kanban by Jim Benson and Tonianne DeMaria Barry. |
How to Avoid Overcommitment During Sprint Planning
|
Awhile back I was working on an Agile coaching gig with Tom Smallwood. We were working with a team that moving to Scrum and was having a particularly difficult time meeting their commitments. Stories were being estimated in Story Points using the Fibonacci sequence and they were breaking stories down into tasks that were then estimated in ideal engineering hours. Stories were (mostly) small enough to go from card on wall to potentially shippable in about 2 days. Tasks were kept to between 4 and 12 hours. Unfortunately, despite following the basic guidelines we were giving them, they were still WAY over committing each Sprint.
Tom was the first one to notice that even though they were all confident in their ability to get the work done at the end of a Sprint Planning meeting, what they were confident about was in fact, completely impossible. What was happening was that each person was assumed to have a capacity of 8 ideal engineering hours per day. Since we were working in two-week iterations, this meant each person was on the hook for 80 hours of productive working time in a Sprint.
The way we addressed this initially was to ask them to plan for no more than 6 productive working hours per person each day. This helped, but it still wasn't cutting it. The problem was that each person had more that they were responsible for than just the project we were working on. (Yes, this is not ideal, but it was reality at the time.)
The solution we came up with was very simple and it is one I have used on every team I worked with since. It adds an extra step to the Sprint Planning ceremony, but it has been invaluable in helping teams understand their capacity and preventing over commitment.
(Disclaimer - this involves using relative Story Point Estimation for Stories and Ideal Engineering Hours for Tasks. There are many who do things differently and have great success - which is awesome... what follows is just what I have found to work well for me and the teams I've worked with.)
What we added was a step in the 2nd half of Sprint Planning. After the team has taken the User Stories (estimated in Story Points) and broken them down into Tasks (estimated in Ideal Engineering Hours), we would go around the circle and ask each team member to estimate how many ideal engineering hours he/she could commit to being responsible for in the upcoming Sprint. One of the most critical parts of this is the idea that the commitment being made is not to the PO, but to the other members of the development/engineering team. So, if I tell my team I'm good for 35 hours, then my team can count on me to be responsible for 35 hours of task work. If I commit to that and do not contribute that amount of time, my team members will have to cover for the work I've not done. While this should go without saying, I have found it to be helpful to mention when starting this part of Sprint Planning.
So, going around the circle, each team member has to be aware of how much time they can commit to contributing. This means they need to account for a lot of the things that get in their way.
Here is how I normally coach people to think through this:
In a two-week iteration, you begin with 10 working days. However, I normally block out 1 day for Sprint Planning, 1 day for the Sprint Review and Sprint Retrospective, 1/4 day for the 8 remaining days during which the team will hold a 15 minute daily standup and 1/4 day for an Estimation/Story Meeting. While blocking out 1 whole day for Sprint Planning and 1 whole day for the Sprint Review and Sprint Retrospective meetings is more than the Scrum Guide calls for, I have found that it is more realistic to working under the assumption that the team will get little else done on those days.
If the Sprint is 2 weeks long, we start with 10 working days. Once we block out the time mentioned above, we end up at 7.5 working days.
If we assume each person can be productive for a maximum of 6 hours per day, then: 6 hours/day * 7.5 days = 45 So, the absolute Maximum Possible Productive Hours (MPPH) for any individual in a two- week Sprint is 45 hours.
We then ask each person to total up the amount of time they expect to lose during the upcoming Sprint to the following events that are not part of the Scrum Framework:
* Getting pulled away from a project to deal with emergencies that are not related to the project is a dysfunction that will impair the team's ability to realize the full benefits of Scrum. However, in several organizations I have worked with, it is a constant reality. When things break, and the money stops flowing, it's all hands on deck.
The total of the above is the Interruption Time (IT) that each team member must subtract from his or her MPPH. The amount of time left is the Revised Maximum Possible Productive Hours (RMPH).
If the individual is only working on a single project, then the RMPH is the amount of time that individual should feel comfortable sharing with their team members as their Committable Productive Time (CPT).
If the individual is split on multiple projects, then they should multiply the percentage of their time that is allocated to the project by the RMPH. They should then subtract an additional 10% from the result (for context switching) to get their Committable Productive Time (CPT).
Here is an example of the above...
Interruption Time:
Interruption Time (IT) = 25 hours
45 (MPPH) - 25 (IT) 20 (RMPH)
If I am split across 2 projects at 50% each...
20 (RMPH) *50% allocation 10 hours -10% (context switching) 9 hours of Committable Productive Time
In talking through this, it is very common to see jaws drop. However, if each person on the team is doing this, then the team will have a realistic understanding of its' work capacity in a given Sprint. While the idea of having to tell someone responsible for your performance review that in a two-week period that you can only be counted on for 9 hours of time may be scary, it is honest. If we are practicing Scrum and sticking with transparency (one of the 3 legs of Scrum), and we are being responsible to our fellow team members, this is the most responsible, transparent thing we can do.
Once each team member has shared their CPT, they are totaled up and this is the Team's Committable Productive Time (TCPT). As long as the total number of estimated ideal task hours does not exceed the TCPT, then the team should feel comfortable making a commitment to the Product Owner for the Stories they will complete during the Sprint. If the number of estimated ideal task hours does exceed the TCPT, then the team may have to negotiate with the Product Owner to reduce the work being planned for the Sprint before they make a commitment.
I have also seen teams break things down even further into number of hours for development, testing, etc., but what is above is typically as deep as I go with it.
It adds an extra step, but it helps the team members inspect and adapt their own workload and capacity. This will also better enable them to meet their commitment in a Sprint; IMHO, the benefits of this far exceed the few extra minutes it will take for a team to make sure they are not overcommitting.
|
Catching up... Podcastapalooza
|
I'm ludicrously behind in keeping the blog up to date... working on that... here is a list of all the podcasts I've done for Projects At Work since The last posting about Mitch Lacey. There is a lot of great Agile stuff here... |
Podcast Interview with Mitch Lacey, author of The Scrum Field Guide
Categories:
Projects At Work,
lacey,
mitch lacey,
field guide,
scrum field guide,
agile transformation,
podcast,
Scrum,
Agile
Categories: Projects At Work, lacey, mitch lacey, field guide, scrum field guide, agile transformation, podcast, Scrum, Agile
|
My Projects at Work podcast interview with Mitch Lacey, author of The Scrum Field Guide.
Also, check out my review of the book here. |
Book Review: The Scrum Field Guide: Practical Advice For Your First Year
| Check out my review of Mitch Lacey's new book The Scrum Field Guide: Practical Advice For Your First Year
on Projects At Work. |






And now, as I am writing this, blog posting about having too much to do,
if it does not go in Things and on those occasions where I am not able to access electronics, I have my overpriced
This past December I found myself in the bizarre position of having to take a whole month off from work. It was that or lose the vacation time. While I’d expect this would sound like a truly wonderful opportunity to most people, it scared the crap out of me. The problem was, I had so many things I wanted to do during my vacation that I was pretty sure I’d end up just curling up in a ball on the couch and watching all 10 seasons of 