Project Management

Certification Insider

by
Cornelius Fichtner help you with your PMP Exam Prep (https://www.project-management-prepcast.com) as well as earn free PDUs (www.pm-podcast.com/pdu). Passing the PMP Exam is tough, but keeping your PMP Certification alive is just as challenging. Preparing for the exam requires an in-depth study of the PMBOK Guide and dedicated study discipline. And once you are PMP certified, then you are required to earn 60 Professional Development Units (PDUs) every 3 years to keep your certification alive. Let me help you make this journey easier with tips and tricks on how to prepare for and pass the exam as well as efficiently earning your PDUs once you are certified.

About this Blog

RSS

Recent Posts

Episode 554: PMBOK Guide 8th Edition, All Six Principles for the PMP Exam

Episode 552: PMP Exam Content Outline

Episode 551: What Movies Teach Project Managers

Episode 549: How to Bring Clarity to Chaotic Projects

Episode 548: From Project Delivery to Value: How Project Managers Create Real Business Impact

Categories

AGILE, Agile, Agile, Agile Projects, Annual Plan and Portfolio, Artificial Intelligence, Audit, Best PMP Exam Simulators, Business Analysis, Business Analysis, Business Analysis Practitioner, Business Management, CAPM, Career Development, CCRS, Change Management, Communication Management, Communications Management, Earning PDUs, Education, Emotional Intelligence Tools, Entrepreneur, Free PDUs, Interpersonal Skills, Knowledge Areas, Knowledge Management, Leadership, Lessons Learned, Lessons Learned Management, Management, meeting management, Millennial Project Managers, Multiple Projects, NASA, Opportunity Cost, PDU, PDU Podcast, PDUs, PDUs: Business Acumen, PDUs: Not Applicable, PDUs: Power Skills, PDUs: Ways of Working, PgMP®, Planning, PM Exam Simulator, PM Formulas, PM Podcast, PM PrepCast, PMBOK, PMBOk 8, PMBOK Guide, PMBOK® Guide, PMI, PMI Agile Certified Practitioner (PMI-ACP)® Exam, PMI Audit, PMI Educational Foundation, PMI Global Congress, PMI Talent Triangle, PMI Talent Triangle/PDUs: Not Acceptable, PMI-ACP, PMI-ACP Certified, PMI-ACP Eligibility, PMI-ACP Exam, PMI-ACP Exam Formulas, PMI-ACP Exam Prep, PMI-ACP®, PMO, PMO, PMO, PMP, pmp, PMP Audit, PMP Cerficiation, PMP Certification, PMP ebook, PMP Exam, PMP exam coach, PMP Exam Overview, PMP Exam Prep, PMP exam prep material, PMP Exam Prep Video, PMP exam sample question, PMP Exam Tip, PMP Lessons Learned, PMP Mock Exam Free, PMP Mock Exam Online, PMP Re-certification, PMP sample question, PMP Study Materials, PMP training, PMP®, podcast, Portfolio Management, Positive Leadership, Power Skills, Process Groups, Professional Development Units, project, Project Assumptions, Project Business, Project Business Management, Project Integration Management, Project Leadership, Project Management, Project Management Basics, Project Management Institute, Project Management Methodology, Project Management Podcast, Project Management Principles, Project management professional, Project Management Skills, Project Management Trends, project manager, Project Manager Skills, Project Manager Soft Skills, Project Managers, Project Metrics, Project Planning, Project Schedule, Project Sponsorship, Project Success, RAM, RBS, Resource Breakdown Structure, Responsibilities, Responsibility Assignment Matrix, Risk Management, Risky Projects, Roles, sample PMP exam, Situational Project Management, soft skills, Strategy implementation, study, Study Techniques, Study Tips, Teams, Technical Project Management, The Agile PrepCast, Virtual Communication, Work-Life Balance

Date

Free PMP Exam Sample Question

linkedin twitter facebook Request to reuse this  

The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:



You managed a project with over 60 team members to design a new sports car. In the project kickoff meeting you assured the team that good performers would be rewarded. At the project closing meeting, you only awarded incentive bonuses to two team members. A client who was present asked why only two team members were provided reward bonuses. What did you miss while defining rewards and recognition?

A.) You didn’t realize recognizing cultural differences may offend people.
B.) You defined objectives on work that was supposed to performed.
C.) You set criteria for rewards that made the team over confident.
D.) You made the targets unachievable on the project.
 

Hint:

Team recognition should be based on individual tasks that are achievable and clear.


All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.
 

ANSWER AND EXPLANATION:

The correct answer is D
Explanation: The entire team worked together to complete the project but only two members were rewarded. This implies that the targets were unachievable and that the expectations set by you were unrealistic.
Reference: PMBOK Guide 4th Edition, page 234

Posted on: November 11, 2011 12:17 AM | Permalink | Comments (0)

Free PMP Exam Sample Question

linkedin twitter facebook Request to reuse this  

The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:


You are managing a software development project. Your project team has developed a software product with many features but poorly organized documentation. Which of the following is correct in this scenario?

A.) It has low grade but high quality
B.) It has high grade but low quality
C.) It has high grade and high quality
D.) It has low grade and low quality

 

Hint:

Grade and quality are not the same. Grade is a category assigned to products, whereas quality is "the degree to which a set of inherent characteristics fulfill requirements".


All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.
 

ANSWER AND EXPLANATION:

The correct answer is B
Explanation: It has high grade and low quality. Quality is the degree to which a set of inherent characteristics fulfill requirements. Grade is a category assigned to products or services having the same functional use but different technical characteristics.
Reference: PMBOK4 - pg:190

Posted on: November 05, 2011 08:56 AM | Permalink | Comments (0)

Recommended PMP Exam Prep Video:Finding the Best Answer to PMP Exam Sample Questions

linkedin twitter facebook Request to reuse this  

The PMP Exam is not an easy exam. You have to find the correct answer to 200 multiple choice questions within 4 hours. That's just 1.2 minutes for each. And sometimes it looks like more than one of them are correct. In this free episode of The PM PrepCast: http://bit.ly/tv2H2g we discuss 2 concepts and 4 techniques of how to approach questions and finding the "best" answer.

Learn and enjoy!

Posted on: November 03, 2011 09:55 AM | Permalink | Comments (0)

Free PMP Exam Sample Question

linkedin twitter facebook Request to reuse this  

The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:



What is risk tolerance?

A.) Risks created by tolerating customer behavior.
B.) Willingness to accept varying degrees of risk.
C.) Risks created by zero tolerance.
D.) Being tolerant if stakeholders are willing to accept risks.
 

Hint:

Look for the “least strange” answer.


All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.
 

ANSWER AND EXPLANATION:

The correct answer is B
Explanation: Do you feel that A, C and D are odd? Correct, they are and they were included intentionally. Sometimes you can expect to find some “funny” answer choices.
Risk tolerance is the stakeholders' willingness to accept varying degrees of risk. Choice B is the only correct answer to this question.
Reference: PMBOK4 - pg:276

Posted on: October 29, 2011 04:55 AM | Permalink | Comments (0)

Recommended PMP Exam Prep Video:PMP Exam Preparation Made Easy

linkedin twitter facebook Request to reuse this  


Are you looking for an easy, complete, effective, portable and most importantly inexpensive way to prepare for the PMP exam? This video presentation will help you: http://bit.ly/teynI8

Learn and enjoy!

Posted on: October 27, 2011 08:23 AM | Permalink | Comments (0)
ADVERTISEMENTS

"If a man will begin with certainties, he shall end in doubts; but if he will be content to begin with doubts, he shall end in certainties."

- Francis Bacon

ADVERTISEMENT

Sponsors