Free PMP Exam Sample Question

From the Certification Insider Blog
by
Cornelius Fichtner help you with your PMP Exam Prep (https://www.project-management-prepcast.com) as well as earn free PDUs (www.pm-podcast.com/pdu). Passing the PMP Exam is tough, but keeping your PMP Certification alive is just as challenging. Preparing for the exam requires an in-depth study of the PMBOK Guide and dedicated study discipline. And once you are PMP certified, then you are required to earn 60 Professional Development Units (PDUs) every 3 years to keep your certification alive. Let me help you make this journey easier with tips and tricks on how to prepare for and pass the exam as well as efficiently earning your PDUs once you are certified.

About this Blog

RSS

Recent Posts

Episode 549: How to Bring Clarity to Chaotic Projects

Episode 548: From Project Delivery to Value: How Project Managers Create Real Business Impact

Episode 546: The Real Reason Project Requirements Keep Changing

Episode 544: The Four Pillars of Project Success

Episode 543: Catch Project Trouble Early and Protect Your Delivery

Categories

AGILE, Agile, Agile, Agile Projects, Annual Plan and Portfolio, Artificial Intelligence, Audit, Best PMP Exam Simulators, Business Analysis, Business Analysis, Business Analysis Practitioner, Business Management, CAPM, Career Development, CCRS, Change Management, Communication Management, Communications Management, Earning PDUs, Education, Emotional Intelligence Tools, Entrepreneur, Free PDUs, Interpersonal Skills, Knowledge Areas, Knowledge Management, Leadership, Lessons Learned, Lessons Learned Management, Management, meeting management, Millennial Project Managers, Multiple Projects, NASA, Opportunity Cost, PDU, PDU Podcast, PDUs, PDUs: Business Acumen, PDUs: Not Applicable, PDUs: Power Skills, PDUs: Ways of Working, PgMP®, Planning, PM Exam Simulator, PM Formulas, PM Podcast, PM PrepCast, PMBOK, PMBOk 8, PMBOK Guide, PMBOK® Guide, PMI, PMI Agile Certified Practitioner (PMI-ACP)® Exam, PMI Audit, PMI Educational Foundation, PMI Global Congress, PMI Talent Triangle, PMI Talent Triangle/PDUs: Not Acceptable, PMI-ACP, PMI-ACP Certified, PMI-ACP Eligibility, PMI-ACP Exam, PMI-ACP Exam Formulas, PMI-ACP Exam Prep, PMI-ACP®, PMO, PMO, PMO, PMP, pmp, PMP Audit, PMP Cerficiation, PMP Certification, PMP ebook, PMP Exam, PMP exam coach, PMP Exam Overview, PMP Exam Prep, PMP exam prep material, PMP Exam Prep Video, PMP exam sample question, PMP Exam Tip, PMP Lessons Learned, PMP Mock Exam Free, PMP Mock Exam Online, PMP Re-certification, PMP sample question, PMP Study Materials, PMP training, PMP®, podcast, Portfolio Management, Positive Leadership, Power Skills, Process Groups, Professional Development Units, project, Project Assumptions, Project Business, Project Business Management, Project Integration Management, Project Leadership, Project Management, Project Management Basics, Project Management Institute, Project Management Methodology, Project Management Podcast, Project Management Principles, Project management professional, Project Management Skills, Project Management Trends, project manager, Project Manager Skills, Project Manager Soft Skills, Project Managers, Project Metrics, Project Planning, Project Schedule, Project Sponsorship, Project Success, RAM, RBS, Resource Breakdown Structure, Responsibilities, Responsibility Assignment Matrix, Risk Management, Risky Projects, Roles, sample PMP exam, Situational Project Management, soft skills, Strategy implementation, study, Study Techniques, Study Tips, Teams, Technical Project Management, The Agile PrepCast, Virtual Communication, Work-Life Balance

Date

linkedin twitter facebook Request to reuse this  


The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:



You are managing a water supply network deployment project. During project planning you are considering two approaches to lay the pipe network. Approach A will most likely cost $50,000 (±5%). Approach B will most likely cost $25,000 (±40%). Which approach will you select if your project stakeholders' risk tolerances are low and if you want to select the less risky approach?

A.) Neither approach since they are not definitive estimates.
B.) Approach B since it ranges from $15,000 to $35,000.
C.) Approach A since it ranges from $47,500 to $52,500.
D.) A combination of approach A and B.
 

Hint:

Estimates are never definitive.


All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

ANSWER AND EXPLANATION:


The correct answer is C
Explanation: Please note that the question doesn't ask for the approach that is more financially feasible. Instead, the question asks you to identify the approach that has the lower risk. The larger the range of an estimate, the larger the risk. Since approach B is a wide range estimate, it is more risky. Approach C has a narrow estimate, which makes this approach less risky.
Reference: PMBOK Guide 4th Edition, page 284
  Edit

Posted on: December 04, 2011 04:19 AM | Permalink

Comments (1)

Please login or join to subscribe to this item
avatar
Mark Price Perry Business Driven PMO Evangelist| BOT International Orlando, Fl, United States
Great question. I always get the English wrong - not the project management. For example, what does tolerance mean - the willingness to tolerate, the capacity to endure, etc. I have often found myself saying that I have a high "tolerance" for a given risk, when in fact I meant that I have a high "intolerance".