Cornelius Fichtner help you with your PMP Exam Prep (https://www.project-management-prepcast.com) as well as earn free PDUs (www.pm-podcast.com/pdu). Passing the PMP Exam is tough, but keeping your PMP Certification alive is just as challenging. Preparing for the exam requires an in-depth study of the PMBOK Guide and dedicated study discipline. And once you are PMP certified, then you are required to earn 60 Professional Development Units (PDUs) every 3 years to keep your certification alive. Let me help you make this journey easier with tips and tricks on how to prepare for and pass the exam as well as efficiently earning your PDUs once you are certified.
Recent Posts
Episode 549: How to Bring Clarity to Chaotic Projects
Episode 548: From Project Delivery to Value: How Project Managers Create Real Business Impact
Episode 546: The Real Reason Project Requirements Keep Changing
Episode 544: The Four Pillars of Project Success
Episode 543: Catch Project Trouble Early and Protect Your Delivery
Categories
AGILE,
Agile,
Agile,
Agile Projects,
Annual Plan and Portfolio,
Artificial Intelligence,
Audit,
Best PMP Exam Simulators,
Business Analysis,
Business Analysis,
Business Analysis Practitioner,
Business Management,
CAPM,
Career Development,
CCRS,
Change Management,
Communication Management,
Communications Management,
Earning PDUs,
Education,
Emotional Intelligence Tools,
Entrepreneur,
Free PDUs,
Interpersonal Skills,
Knowledge Areas,
Knowledge Management,
Leadership,
Lessons Learned,
Lessons Learned Management,
Management,
meeting management,
Millennial Project Managers,
Multiple Projects,
NASA,
Opportunity Cost,
PDU,
PDU Podcast,
PDUs,
PDUs: Business Acumen,
PDUs: Not Applicable,
PDUs: Power Skills,
PDUs: Ways of Working,
PgMP®,
Planning,
PM Exam Simulator,
PM Formulas,
PM Podcast,
PM PrepCast,
PMBOK,
PMBOk 8,
PMBOK Guide,
PMBOK® Guide,
PMI,
PMI Agile Certified Practitioner (PMI-ACP)® Exam,
PMI Audit,
PMI Educational Foundation,
PMI Global Congress,
PMI Talent Triangle,
PMI Talent Triangle/PDUs: Not Acceptable,
PMI-ACP,
PMI-ACP Certified,
PMI-ACP Eligibility,
PMI-ACP Exam,
PMI-ACP Exam Formulas,
PMI-ACP Exam Prep,
PMI-ACP®,
PMO,
PMO,
PMO,
PMP,
pmp,
PMP Audit,
PMP Cerficiation,
PMP Certification,
PMP ebook,
PMP Exam,
PMP exam coach,
PMP Exam Overview,
PMP Exam Prep,
PMP exam prep material,
PMP Exam Prep Video,
PMP exam sample question,
PMP Exam Tip,
PMP Lessons Learned,
PMP Mock Exam Free,
PMP Mock Exam Online,
PMP Re-certification,
PMP sample question,
PMP Study Materials,
PMP training,
PMP®,
podcast,
Portfolio Management,
Positive Leadership,
Power Skills,
Process Groups,
Professional Development Units,
project,
Project Assumptions,
Project Business,
Project Business Management,
Project Integration Management,
Project Leadership,
Project Management,
Project Management Basics,
Project Management Institute,
Project Management Methodology,
Project Management Podcast,
Project Management Principles,
Project management professional,
Project Management Skills,
Project Management Trends,
project manager,
Project Manager Skills,
Project Manager Soft Skills,
Project Managers,
Project Metrics,
Project Planning,
Project Schedule,
Project Sponsorship,
Project Success,
RAM,
RBS,
Resource Breakdown Structure,
Responsibilities,
Responsibility Assignment Matrix,
Risk Management,
Risky Projects,
Roles,
sample PMP exam,
Situational Project Management,
soft skills,
Strategy implementation,
study,
Study Techniques,
Study Tips,
Teams,
Technical Project Management,
The Agile PrepCast,
Virtual Communication,
Work-Life Balance
Date

The Precedence Diagramming Method (PDM) is a tool for scheduling and sequencing events in a project plan based on their relationships with other events. The model allows you to visually map activities and their dependencies. Within this model there are four types of dependencies or logical relationships that are possible: finish-to-start (FS), finish-to-finish (FF), start-to-start (SS), and start-to-finish (SF). The start-to-finish relationship seems to be the model that causes the most confusion for students of the PMP exam, perhaps because there are not many good examples of this relationship. Start-to-finish occurs when “the completion of the successor activity depends on the initiation of the predecessor activity,” or, said so that normal folks can process it: Activity A must start before Activity B can finish.
Think about how you would implement a new system and turn an old system off. You can complete (i.e., turn off) the old system as soon as the new system has started in production—but not before then. Let’s try an example or two and see if it clicks:
Say you’re building a new gas pipeline. You would first finish construction and implementation of the new pipeline before you would begin shutting down and breaking down the old pipeline. Similarly, implementation of a new accounting system has to be completed before you can begin turning off the old system. Make sense?
Don’t spend too much time sweating over this particular model, however. Even though it’s not a difficult concept, the start-to-finish relationship is rarely used.