Project Management

Project Management View from Rail Transit Programs and Projects

by
A collection of articles sharing project processes, design and construction experience, best practices, and lessons learned along with operational knowledge related to executing programs and projects in the rail transit industry.

About this Blog

RSS

Recent Posts

Transitioning Constructed Products from Projects to Owner's Operations

Lessons to be Learned.  What Happens When the Buyer is Not the Owner, Operator and Maintainer of the Company?  

Managing Warranty After Achieving Contract Milestones

What Happens After the Buyer and Seller Agree on a Punchlist?

What is a Punchlist?

Categories

Acceptance, Analytics, ANSI, Asset Management, Best Value, Best Value Contractor Selection, Best Value Selection Criteria, Buyer, Certifications, Commissioning, Communications Management, Construction, Construction Completion, Construction Deliverables, construction manager, Construction Monitoring, Construction Submittals, Consultant, Consultant Contract, Contract Acquisition, Contract Completion, Contract Deliverables, Contract Delivery, Contract Development, Contract Integration, Contract Management, Contract Milestones, Contract Quality, Contract Requirements, Contract Submittals, Contracts, Decision Making, Definitions, Design, Design Bid Build, Design Build, Design Build Delivery, Design Deliverables, Design Services, Design Submittals, Design-Bid-Build, Division 1 Specifications, Document Control, Earned Value Management, Engineering, Estimating, Estimator, Ethics, Factory Acceptance Test, Final Acceptance, Final Completion, General Conditions, General Provisions, General Terms and Conditions, Good Practices, Government, Hard Risks, Hazards, Human Resources, Information For Bidders, Inspection, Inspection and Testing, Inspection Test Plan, Integration, Integration Management, Invitation For Bid, Key Performance Indicators, Knowledge Management, Maintenance, Management Integration, Managerial Time, Managing Change, Managing Changes, Master Project Schedule, Meeting Minutes, Mega Projects, NCR Process, Negotiations, Non Conformance Report, O&M Manuals, Oversight Reports, PM Fundamentals, PMBOK, PMI, PMO, Procurement Management, Professional Obligations, Program Management, program manager, Progress Reports, Project Charter, Project Controls, Project Engineer, Project Engineering, Project Integration, Project Interfacing, Project Management, Project Management Institute, project management office, Project Management Plan, Project Manager, Project Managerr, Project Planning, Project Records, Project Schedules, Project Team, Project Teams, ProjectManagement, Public Relations, punchlist, Quality, Quality, Rail Car Purchase, Rail Transit, Rail Transit Organization, Rail Transit Project, Rail Transit Projects, Railroad, Reliability, Resource Management, RFI Logs, risk, Risk Allocation, risk allocation, Risk Allocations, Risk Management, Risk Management, Safety, Schedule Interfaces, Schedule Management, Schedule Milestones, Scheduler, Scheduling, Scope of Work, Security, Seller, Site Acceptance Test, Soft Risks, Special Inspections, Specifications, Submittal Logs, Submittal Process, Substantial Completion, System Integration, System Integration Test, Systems, Systems Purchase, Testing/Test Management, Threats, Transformation, Transformational Projects, Transportation, Vulnerability, Work Area, Work Areas

Date

Factors, Metrics and Tips on Quality Management for the Non Conformance Report Process

linkedin twitter facebook Request to reuse this  

On a recent bridge project, the infiltration of water through the decking to the roadway underneath was obvious.   A field visitor to the bridge after a heavy rain expressed dissatisfaction and suggested the bridge was like a car wash.   Another stakeholder sent a terse Email indicating an inspection was wasting people’s time because the waterproofing non-conformance was not corrected.   

Here is a project manager’s perspective on the three primary steps in the non-conformance process: 

Opening:         At this step, the contractor and quality group determined there is a non-conformance of the product/deliverables to meet the contract requirements.   A Non-Conformance Report (NCR) is created and distributed for engineer and quality group review.  (This can be preceded by an Observation, which is reviewed and confirmed to be a non-conforming condition.) 

Pending:          At this step, the contractor, engineer and quality groups agree on the required corrective action to resolve the described non-conformance.  Procedures and as needed, updated drawings or sketches are approved and ready for execution.    

Closing:           At this step, the contractor and construction manager agree the corrective action is completed and after testing, it is confirmed the work product/deliverables meet the contract.  Quality records are available to substantiate closing the NCR.

The NCR is an output for controlling non-conforming conditions on projects, which are based on contract requirements as well as industry standards by International Organization for Standards (ISO) and Project Management Institute (PMI).  The NCR is an integral part of a Project Quality Management System Plan (QMS) and the project approved Quality Manual from each consultant, contractor, vendor, manufacturer and independent testing agency. 

A sample contract might include the following QMS attributes, which can be customized to the contract scope such as design, construction, construction management and testing agency:

  • Management Responsibilities
  • Design [and/or Construction] Control
  • Document Control
  • Purchasing
  • Supplied Items
  • Product Identification and Traceability
  • Process Control
  • Inspection and Testing
  • Inspection, Measuring and Test Equipment
  • Inspection and Test Status
  • Non Conformance
  • Corrective Action
  • Quality Records
  • Quality Audits
  • Training

While an NCR was written and the corrective action was agreed upon by the Engineer and product manufacturer regarding the bridge, there were delays in arranging the required work conditions for completing the corrective action.  Subsequently, the repair to the bridge waterproofing was not successful in resolving the drainage problem.  As a result, the same repair was scheduled for the future, which further increased the overall process duration.

There were no contract requirements or project level plans containing performance goals/durations for each step.    However, management for the contractor and PM oversight were questioning the number of open NCRs and the durations to closure.   Management perceived the durations for the NCRs were much too long.

The NCR process durations are a function of the work hours and conditions for each contract in a project.   As a result, each project and each contract may have different durations for the optimum project processes including NCRs. 

Factors affecting NCR durations:

  • Proximity and access to the work location
  • Priority of work by the Engineer and Quality team representatives
  • Prescribed durations for response dictated by project document control goals
  • Schedule for successor activities using the product and deliverable cited in NCR
  • Conditions, including temperature, weather, and safe work environment, required for implementing the corrective action
  • Availability of Independent Testing Agencies to physically confirm and generate a Report the corrective action are complete, successful and meet contract requirements.

Management of NCR performance should be based on historical data from previous experience with the process lifecycle provided by the Buyer’s organization on completed projects similar in scope, cost, schedule, complexity, contract types, and document control methodology.   Without prior experience, performance metrics may need to go through several trial periods based on the best estimate of the NCR work flow.

The estimated work flow should be developed, vetted and tested by the Buyer and Seller before implementing performance management/measurement of NCR durations.  An example for the NCR work flow and optimum activity timeframes for a rail transit project is below.  The process includes Field personnel identifying variances to requirements and  overseeing site work, Engineer to evaluate the NCR/Observation and determine the corrective action, Contractor to perform the corrective action and the Field personnel to confirm the corrective action meet requirements.  This example may be a useful framework across several industries.

Opening:         The activities in this phase are:

  • Report observation to Quality group-Day 1
  • Evaluate observation and determine if corrected by Construction group-Day 7 (NCR not required)
  • Determine work was completed without correcting the variance to requirements-Day 14
  • Initiate and complete NCR-Day 21

Pending:          The activities in this phase are:

  • Submit NCR to Engineer for review-Day 22
  • Conduct field inspection of conditions-Day 29
  • Develop corrective action/contract change-Day 59
  • Submit corrective action for Buyer review-Day 58
  • Obtain Buyer approval on corrective action-Day 72

Closing:           The activities in this phase are:

  • Notify Construction group to implement corrective action-Day 73
  • Obtain materials and equipment for work-Day 87
  • Complete corrective action work-Day 101
  • Issue NCR confirming completion-Day 108
  • Obtain Buyer approval on completion or work to requirements-Day 122

Accounting for the established review goals, processing time for document control, and the limited access to site locations, the optimum duration for NCR process = 122 days from initial Observation.   The potential metrics for monitoring performance are:   OPENING = 21 days from Observation.   PENDING = 51 days from NCR start.    CLOSING = 50 days from approval of NCR corrective action.

TIP:    PM should balance the work flow and activity timeframe to the specific project scope and durations common to the industry, the Buyer’s standard organization processes, and the review duration goals for document control/production.

TIP:    PM should evaluate the managerial and administrate effort by the Buyer and contractor to explain performance variances to goal durations, which may already be monitored and measurable by other means such as achieving contract and forecast milestones.  Typical milestones, including Substantial Completion, Construction Completion and Final Completion/Acceptance are dependent on closing NCRs and Observations. 

TIP:    Metrics and dashboards are proven management tools for monitoring project performance as well as organizational silos.  PM should assess the totality of the management dashboards so that the team, stakeholders, funding partners, community and political influencers remain focused on critical goals without distraction to tie up managerial resources explaining variances to goals on items that do not directly affect progress and achieving goals. 

TIP:    The performance on NCRs may not be as critical as other key indicators that more directly affect interdependencies on achieving operational use and final acceptance of the project product/deliverable by hard schedule dates and milestones.

TIP:   Project QMS and contractor/consultant Quality Manuals should clearly define the attributes for an Observation and Non Conformance.  Both work flows should provide checkpoints to eliminate nuisance and trivial items identified during routine in-progress inspections of work.  These items should be resolved by the Buyer’s and Seller’s supervision on-site.    

Posted on: August 22, 2020 04:37 PM | Permalink | Comments (3)
ADVERTISEMENTS

Wow! They've got the internet on computers now!

- Homer Simpson

ADVERTISEMENT

Sponsors