Project Management

Project Management View from Rail Transit Programs and Projects

by
A collection of articles sharing project processes, design and construction experience, best practices, and lessons learned along with operational knowledge related to executing programs and projects in the rail transit industry.

About this Blog

RSS

Recent Posts

Transitioning Constructed Products from Projects to Owner's Operations

Lessons to be Learned.  What Happens When the Buyer is Not the Owner, Operator and Maintainer of the Company?  

Managing Warranty After Achieving Contract Milestones

What Happens After the Buyer and Seller Agree on a Punchlist?

What is a Punchlist?

Categories

Acceptance, Analytics, ANSI, Asset Management, Best Value, Best Value Contractor Selection, Best Value Selection Criteria, Buyer, Certifications, Commissioning, Communications Management, Construction, Construction Completion, Construction Deliverables, construction manager, Construction Monitoring, Construction Submittals, Consultant, Consultant Contract, Contract Acquisition, Contract Completion, Contract Deliverables, Contract Delivery, Contract Development, Contract Integration, Contract Management, Contract Milestones, Contract Quality, Contract Requirements, Contract Submittals, Contracts, Decision Making, Definitions, Design, Design Bid Build, Design Build, Design Build Delivery, Design Deliverables, Design Services, Design Submittals, Design-Bid-Build, Division 1 Specifications, Document Control, Earned Value Management, Engineering, Estimating, Estimator, Ethics, Factory Acceptance Test, Final Acceptance, Final Completion, General Conditions, General Provisions, General Terms and Conditions, Good Practices, Government, Hard Risks, Hazards, Human Resources, Information For Bidders, Inspection, Inspection and Testing, Inspection Test Plan, Integration, Integration Management, Invitation For Bid, Key Performance Indicators, Knowledge Management, Maintenance, Management Integration, Managerial Time, Managing Change, Managing Changes, Master Project Schedule, Meeting Minutes, Mega Projects, NCR Process, Negotiations, Non Conformance Report, O&M Manuals, Oversight Reports, PM Fundamentals, PMBOK, PMI, PMO, Procurement Management, Professional Obligations, Program Management, program manager, Progress Reports, Project Charter, Project Controls, Project Engineer, Project Engineering, Project Integration, Project Interfacing, Project Management, Project Management Institute, project management office, Project Management Plan, Project Manager, Project Managerr, Project Planning, Project Records, Project Schedules, Project Team, Project Teams, ProjectManagement, Public Relations, punchlist, Quality, Quality, Rail Car Purchase, Rail Transit, Rail Transit Organization, Rail Transit Project, Rail Transit Projects, Railroad, Reliability, Resource Management, RFI Logs, risk, Risk Allocation, risk allocation, Risk Allocations, Risk Management, Risk Management, Safety, Schedule Interfaces, Schedule Management, Schedule Milestones, Scheduler, Scheduling, Scope of Work, Security, Seller, Site Acceptance Test, Soft Risks, Special Inspections, Specifications, Submittal Logs, Submittal Process, Substantial Completion, System Integration, System Integration Test, Systems, Systems Purchase, Testing/Test Management, Threats, Transformation, Transformational Projects, Transportation, Vulnerability, Work Area, Work Areas

Date

What is a Punchlist?

linkedin twitter facebook Request to reuse this  

A punchlist is most common in the construction industry.  But it may be an overused term on prime contracts between Buyers and Sellers - when a simple To-Do-List might be more appropriate description for a tool construction managers (CM) use to monitor contractor progress toward achieving contract milestones.  

Punchlist is not normally part of the definitions in the construction contract Form.   As a result, Punchlist means different things to Sellers and Buyers.

Definition

From various sources of expertise, punchlist is described as:

  • American Institute of Architects (A201-2017):  @ Substantial Completion – a comprehensive list of items to be completed prior to final payment.
  • Design Build Institute of America (535): @ Substantial Completion - (ii) the remaining items of work that have to be completed before final payment.  
  • PMI PMBOK Construction: the work items that are identified during a final inspection that need to be completed.
  • Construction Coverage (website):  is a document created in the final stages of a construction project to provide a list of items that must be addressed before construction is considered complete and payment is issued.
  • Merriam-Webster (dictionary):  a list of usually minor tasks to be completed at the end of a project.

Punchlist is interdependent with the progress of work by the Seller and the milestones specified by the Buyer in the Contract.  The milestones are typically contained in the General Conditions/Provisions (GCs) of a contract document.  Punchlist creation is associated with substantial completion and punchlist completion is associated with construction completion.   

Work Flow

Punchlist work flow:

  1. Seller and Buyer's CM confirm to Buyer Project Manager work is substantially completed
  2. Buyer's CM/Project Manager coordinates inspections by the Buyer's project team members and other stakeholders and creates a punchlist
  3. Buyer's CM submits the punchlist for review and final edits by the project team and stakeholders
  4. Buyer's Contracting Officer acknowledges substantial completion to Seller, submits the punchlist for Seller's corrective action by the construction completion date 
  5. Seller and Buyer's CM confirm to Buyer's Project Manager all work is completed and achieved construction completion
  6. Buyer's CM/Project Manager coordinates final inspections by the Buyer's project team members and other stakeholders to verify all items on the punchlist are completed
  7. Buyer's Contracting Officer acknowledges construction completion and instructs Seller to demobilize and perform site restoration by the final completion/contract completion milestone.

Most US standard contract Forms, cite the requirements for substantial completion and construction completion in the General Conditions/Provisions regarding section related to Performance Schedule and Payments.   

Punchlist Content

The content of a punchlist should contain only minor touch-ups and repairs to installed/constructed work that is described by specific in-scope observations and the locations to be corrected for completion.   A punchlist that contains base scope items not yet installed or tested and operational is not acceptable and not suitable for meeting the completion milestone.   Items observed that are not in-scope will be deleted from the punchlist and be addressed by the Buyer through other project processes for changes to work. 

In addition to contract milestones and payments, an acceptable punchlist that the Buyer determines meets the substantial completion requirements is often tied to incentives and liquidated damages.   Meeting substantial completion is also related to other contract requirements. 

Punchlist Interfaces

Interfaces with other contract requirements in the work flow include:  Item 4-After substantial completion, Seller and Buyer can initiate reconciliation of incentives and liquidated damages.  Buyer can suspend consideration of all potential changes, instruct Seller to demobilize and to perform site restoration by the final completion/contract completion milestone, request Seller to submit deliverables such as O&M Manuals, As-Built Drawings Package and Warranties, and if applicable, release performance bonds.   Item 5-After construction completion, Seller and Buyer can initiate the contract closeout.  Item 7-After demobilization, Seller can reduce insurance coverage.

TIP:   A punchlist should only be submitted once by Seller and reviewed by Buyer for completeness an accuracy.  Thereafter, it is locked down.  No items can be addressed.  Items can only be verified as completed and closed.  

TIP:  All items on the punchlist should be addressed and closed by the Sellers within a period that avoids the risk of further damage or new conditions that requires corrective action. 

TIP:    For Buyer’s, including their construction managers, that require in-progress punchlists to assess the contractor’s physical work relative to the construction substantial completion milestone, a more granular definition of punchlist may be neededHere are some proposed definitions that can provide guidance to Buyer and Seller as the punchlist changes with the progress of construction.

  • In-Progress/Preliminary Punchlist:   List of remaining work and corrections prepared and submitted prior to the milestone for substantial completion, and it may contain items that are part of the base scope but not yet installed and tested.  This Punchlist is submitted as information, and it represents Buyer and Seller  in-progress inspection observations from multiple parties.   This Llist is monitored until substantial completion is achieved by the Seller.   
  • Formal Punchlist:  List of remaining work and corrections is mutually prepared by the Buyer, Buyer’s construction manager, and Seller after substantial completion, which represents the work is ready for it intended use, all tests are completed and all work is operational.   This Punchlist is submitted for review and comments by Buyer.   Concurrently, Buyer will schedule a walkthrough inspection by the Buyer and all end user representatives to compile a complete punchlist.  This List with comments resolved will be the official list of remaining work.
  • Final Punchlist:  List of items confirmed completed by the Seller and confirmed completed by Buyer or Buyer’s construction manager.  This Punchlist is submitted for Buyer Sign-Off along with a request by Seller  for final walkthrough.   The Buyer arranges for all parties to attend for sign-off that all items on the punchlist.    Sign-off of this Punchlist is the predecessor to Buyer’s acceptance of the Seller’s work, which is an interdependency of criteria for completing the contract closeout.   

TIP:   An observation listed on the punchlist should identify the inspecting agency/inspector name and date, cite the specific location (s) and the drawing/specification/code, and describe the needed correction to meet with the contract requirements, approved shop drawings or other industry standards for the type of work.

TIP:  The punchlist observations should be actionable and the description begin with words such as repair, replace, adjust, touch-up, polish, remove, rebalance and clean.  Items with words such as install, test, paint, fill, energize, backfill and connect may indicate that base scope is not yet completed. 

Posted on: September 05, 2022 01:40 PM | Permalink | Comments (4)

Know the Contract  -  Part 14, Contract Completion/Closeout

linkedin twitter facebook Request to reuse this  

This is the 14th in a series of discussions that is intended to prompt Project Teams to be aware of the entire contract document, including Information For Bidders (IFB), General Provisions/General Conditions/Terms and Conditions (GCs) and the Technical Requirements [Specifications and Drawings.] 

Part 14 of Know the Contract is Contract Completion/Closeout.   Closeout is the successor to all other work performed under the Contract and it is final set of activities between the Buyer and Seller.    While the requirements for Closeout may be scattered throughout the Contract document, the most important are described in the GC’s sections related to Schedule and Payments.   At this phase of the Contract, the Buyer’s Contracting Officer is the primary arbiter for determining that all requirements are met by the Seller and confirmed by the Buyer’s Project Manager.   

Part 6-Schedule Performance and Part 7-Progress & Milestone Payments of this series describe the content in the typical contract Form.   Satisfying these requirements precede completing the Closeout process and documentation, and includes substantiating completion of testing and start-up; training; delivering spare parts; submitting operation & maintenance manuals, software, as-built drawings, asset management data and warranty; and closure of all quality management  processes and deliverables. 

Regardless of the contracting method, such as Design-Bid-Build, Design Build and CM At Risk, the Closeout of the contract is governed by the GCs as well as any Special Conditions and terms negotiated for contract award.   The typical activities and topics include:

  • Settling all change orders, requests for extension of time due to Buyer actions,  differing site conditions or claims for extra work and damages
  • Reconciling all incentives payments and damage accruals from exceeding or delaying established milestone dates for completion of work
  • Confirming receipt of all GC deliverables, including photographs, monthly progress reports and schedules, manpower utilization reports, certified payroll and prevailing wage records,  and prompt payment records.
  • Resolving all claims, disputes, legal actions, or pending attorney actions between Buyer and Seller, including all contract issues with Seller’s subcontractors, vendors and suppliers
  • Verifying all payments and release of retainage to prime contractor, subcontractors, vendors and suppliers 
  • Processing all contract modifications and final contract amount
  • Transferring all contract records in paper and digital format

During the Closeout phase, the Buyer may develop Lessons Learned from the Seller’s performance on the Contract.  The Lessons Learned will be utilized by the Buyer to consider changes in requirements as well as management processes and documentation on future Contracts.  Some of the topics from Lessons Learned may include:

  • Effectiveness of the contracting delivery method and the Buyer’s and Seller’s organizational structure to support the work
  • Realism in Buyer’s duration for contract milestones and effectiveness of incentives and liquidated damages
  • Evaluation of Seller’s prime contractors, vendors and suppliers to meet the Buyer’s schedule deadlines
  • Buyer’s and Seller’s risk threats and opportunities mitigated and realized during the Contract
  • Change orders and claims encountered by Buyer that may be avoided by editing requirements in future Seller’s contracts.

TIP:  The responsible parties for Closeout are the Buyer’s Project Manager with support from the Buyer’s Contracting Officer and the Seller’s Project Manager with support from the Seller’s prime contracting/procurement official.

TIP:  While risking duplication of requirements, create a separate Division 1 specification covering the requirements and deliverables checklist for contract closeout.

TIP:   Most US contract Forms were written based on paper transactions throughout the Contract cycle.  Due to awareness of threats outside normal contract and project processes, security of products, deliverables and documentation is now part of controlling access to sensitive contract records.    As a result, EDMS has replaced paper documents and is used more effectively to segregate, store and restrict distribution of documents that contain sensitive information.      

TIP:  The use of electronic document control system (EDMS) has become a critical part of managing and executing the work at a project and contract level.   As a result, there may be a need to create requirements for content, format, compatibility and the transfer method of the Seller’s EDMS with the Buyer’s hardware, software and the organizational management of records.  

TIP:  Ensure Closeout requirements and terminology are well defined and are consistent with the process and requirements in the GCs.  Clarity of terms is essential for both the Buyer and Seller. 

TIP:  Buyer’s Contracting Officer should provide clear guidance to the Buyer’s Project Manager on the process, timeline and documentation required to satisfy the contract closeout.

Posted on: March 13, 2022 07:36 PM | Permalink | Comments (4)

CAMP Questions and Answers - Part 2

linkedin twitter facebook Request to reuse this  

This article complements the previous articles “What are good practices for Commissioning Acceptance and Maintenance Plan (CAMP)?” and Questions and Answers to CAMP – Part 1.  Here are Questions and Answers to CAMP – Part 2.

What are the CAMP deliverables?

Typical contract sections or project plans for CAMP deliverables are:

  • Receipt of Final Testing and Acceptance Sign-Off Documentation:  This consists of a complementary series of project documents, which demonstrate quality and managerial oversight of the work.    Based on the scope, this may include factory acceptance test results, site acceptance test results, inspections at substantial completion, final inspection at completion of punchlist, record of special inspections, and closure of Permits by the issuing agency.   This documentation is produced by construction management consultants and Agencies with permitting jurisdiction.
  • Certificate of Construction Completion: This is certification that all punchlist work is complete; start-up, training and burn-in is complete; and the overall Project Element is constructed as shown on the RFC design packages, shops drawings and material/product submittals.  Unless indicated otherwise, this Certificate is produced by the primary Construction Manager. 
  • Certificate of Construction Compliance/Code Compliance:  This is certification that all work meets the contract technical and quality requirements, the Design Build Quality Program, and all stipulations in construction Permits.   This Certificate is produced the Engineer of Record. 
  • Spare Parts:   This is found in the Division 2-16 Technical Specifications of the contract/purchase order.   The spare parts description and quantities will typically be itemized in the Buyer’s contract award price breakdown and in the Seller’s Detailed Contract Schedule/payment schedule.  
  • Training, O&M Manuals:   This is found in the Division 1 Technical Specifications of the contract/purchase order.    While the Seller’s  system and equipment suppliers typically have standard services and deliverables for off-the-self components, the Buyer’s may have extraordinary requirements to meet the operation standards, procedures and processes of the company. 
  • As-Built drawings  This is found in the Division 1 Technical Specifications of the contract/purchase order.     This item may also be expressed and defined by the Buyer with other labels such as red-lined contract drawings and record drawings.   It is typically an updated version of the conformed contract drawings from the Seller, which includes all contract changes and modifications, and it indicates the actual installed locations of the constructed assets.
  • Warranty:    This is found in the General Provisions, and it may be amplified in Division 2-16 Technical Specifications for large, high value technology systems and equipment.    By Contract, the Warranty starts at Buyer’s use/acceptance of the work, and it follows Final Inspection, and Punchlist activities.    Seller’s obligation  for warranty  is typically one year and as supplemented by manufacturer’s and Original Equipment Suppliers’ warranties, which may extend post-contract closeout for several years as described in the product data/specification reviewed during the Contract Submittal process. 
  • Software and Software Licenses:    The requirements scope for computer supported products with hardware and software are usually found in the Technical Specifications in Division 10-16, including (10) Specialties, (11) Equipment, (13) Special Construction, (14) Conveying Systems, (15) Mechanical/Plumbing, and (16) Electrical.   However, depending on the contract format, requirements may also be separated into new Divisions including (21) Fire Suppression, (23) HVAC, (25) Integrated Automation, (26) Electrical, (27) Communications, and (28) Electronic/Safety/Security.  
  • BIM/GIS Data and Asset Management Data:    This is found in the Division 1 Technical Specifications of the contract/purchase order.   While the data can be generated using the contract drawings, it is more accurate to complete after the As-Built drawings are submitted and accepted.  

Who is responsible for CAMP?

CAMP is a cross-functional process and it is correlated with various activities and the creation of various project records.  As established by the project in the Schedule Work Breakdown Structure, the CAMP process monitors work across several managerial silos.   In some Electronic Document Management Systems, the managerial silos or project phases include:

Design:   The development and refinement of project product requirements, and the creation of contract documents and performance metrics for the product meeting the Buyer’s criteria and business case results.

Construction:   The physical fabrication/manufacture of systems, brick & mortar assembly of a structure for the systems, and the integrated start-up and testing the entire product for Buyers acceptance.  

Quality:   The control and assurance on the product, processes and documentation meet the Buyer’s requirements for the project product, including design and construction submittals and deliverables and the content for CAMP.  

Commercial:   The management of project finances, contract payments and closeout, contract changes and of contractor performance to schedule milestones, which includes monitoring incentives for beating milestones and liquidated damages for missing milestones. 

What typical CAMP activities should be in the Detailed Contract Schedule?

A sample of the critical cross functional activities with responsibilities by Buyer/Seller are:

  1. Seller initiates CAMP package and compiles project records
  2. Seller and Buyer confirm readiness for substantial completion/operational use
  3. Seller/Buyer conduct and document QC/QA inspection and testing, including Site  Acceptance Test (Predecessor = B)
  4. Seller/Buyer conduct and document substantial completion inspection and punchlist (Predecessor = C)
  5. Seller requests progress payment for 100% earned value and Buyer issues progress payment (Predecessor = D)
  6. Seller submits CAMP package and notifies Buyer on readiness for final inspection (Predecessor = A, E)
  7. Seller/Buyer conduct and document final inspection and completion of punchlist/work and burn-in (Predecessor = F)
  8. Seller submits contract closeout documents and requests release of retainage withheld from previously approved progress payments (Predecessor = G)
  9. Buyer confirms acceptance of CAMP package, including and all products and deliverables by contract requirements, and releases retainage to Seller  (Predecessor = F, G, H)
Posted on: March 16, 2020 05:22 PM | Permalink | Comments (0)

CAMP Questions and Answers - Part 1

linkedin twitter facebook Request to reuse this  

This article complements the previous article “What are good practices for Commissioning Acceptance and Maintenance Plan (CAMP)?”  Tailored to rail transit projects, this article follows with  Q&A on CAMP definitions, description of CAMP deliverables, integrated managerial functions supporting CAMP, and the general activities and sequence for CAMP.    Here are Questions and Answers to CAMP – Part 1.

When Does the CAMP Process Start?

CAMP starts with the design of the project and the creation of construction documents, and it continues through the closeout of the contract/project.   The process will consist of iterative development of a content a Matrix that lists the components that will form the constructed product as described in the project scope and objective.   The Matrix also lists the expected CAMP deliverables, such as Operation and Maintenance Manuals, Warranty, Training, As-Built Drawings, Spare Parts, Software, and GIS/Asset Management data.   Starting the work in the design will assure that at the time of the construction contract award, the Seller and Buyer have the same expectations for the CAMP deliverables.

What are the definitions for CAMP?

Commissioning:   This is the pre-requisite activities and deliverables for starting the CAMP package and deliverables for Acceptance, and it is the Buyer’s (Owner) process for verification of project/contract scope and the Seller’s (Contractor) compliance with requirements.    The activities typically include Factory Acceptance Testing (FAT), On-Site Acceptance Testing (SAT), In-progress Inspections, Start-Up and Burn-In.   Commissioning activities should be integrated into Project Control schedules and Quality Plans, which contain quality control test and inspection plans.

Acceptance:  This is a predecessor activity for contract closeout, and it refers to the Final Acceptance by the Buyer/Owner, which follows completion of Commissioning activities and  A) Final formal inspection of the Seller’s work.   B) Seller’s completion of punchlist work.   C) Buyer’s  confirming resolution of Submittals and Non-Conformance Reports (NCR).   D) Buyer’s receipt of Seller’s training, As-Built drawings, Spare parts, Warranty, Operation and Maintenance Manuals (Inspection and Maintenance).   E) BIM/GIS and Asset Management Data.   Contractually, Acceptance equates to Construction Completion, which its tied directly to commercial provisions, Final Payment and Warranty, and is a milestone for the Project Control schedule.  

Maintenance:   This is a post-contract closeout activity and it refers to Buyer’s readiness to conduct periodic inspections and maintain the Seller’s accepted work.  The Buyer’s readiness includes A) Allocating operating budget and assign management responsibility.  B) Purchase and inventory of special tools, consumable items and spare parts.  C) Assign new or reallocate operation/maintenance staff and resources.  D) Update company asset inventory and insurance. 

What are CAMP requirements?

The requirements for the items cited in the definitions above are typically embedded in the contract document.    Typical contract sections or project plans for CAMP technical requirements or inputs in rail transit are:

  • FAT/SAT:   This is found in the Division 2-16 Technical Specifications of the contract/purchase order.    It is most applicable to major systems and equipment, including signal systems, HVAC, substations, signal power motor generators, communications and supervisory control systems and control centers.   The Seller is required to submit detailed test procedures, and the test results for review and approval by the Buyer. 
  • Inspections:   This is implemented under the General Provisions and detailed in Technical Specifications of the contract/purchase order.   It is most applicable to work covered by government permitting and code compliance, and it is described in the Buyer’s construction  manager’s  (CM) monitoring plan and in the CM’s inspection and testing plan  for overseeing the Seller’s work.
  • Start-Up/Burn-In:   This is found in the Division 2-16 Technical Specifications of the contract/purchase order.   It is most applicable to power systems such as substations and signal power motor generators.   The Burn-in periods can range from 30 – 90 days after initial start-up under full load.   For replacement projects, the completion of the Burn-In for the new infrastructure is a predecessor activity in the Seller’s Detailed Contract Schedule for demolition of the old systems.  
  • Final Inspection:    This is found in the General Provisions of the contract/purchase order, usually under the Payment and Time/Contract Schedule Milestones.   Final inspection is typically an end-of-contract item.  However, Buyer and Seller may agree to incremental inspection, use and occupancy of portions of the work.   The Seller’s detailed contract schedule and the Inspection and Test  Plan will delineate the proposed sequence for completing portions of the work.  
  • Punchlist:   This requirement follows Final Inspection and it is a predecessor for achieving Time/Contract Schedule Milestone for Substantial Completion (SC) in the General Provisions of the contract/purchase order.   SC means the work is useful to the Buyer ahead of the completion of work and milestones such as Construction Completion and Contract Completion.
  • Resolution of Submittals and Non-Conformance Reports (NCRs):   This is part of the Buyer’s contract monitoring plan and the project quality plan.  These Plans assure that delivered and installed products reflect the current contract including all negotiated changes and contract modifications, and the completion of corrective actions on NCRs under the Seller’s Quality Management Plan.
Posted on: February 23, 2020 02:53 PM | Permalink | Comments (2)

Good practices for Commissioning Acceptance and Maintenance Plans (CAMP)?

linkedin twitter facebook Request to reuse this  

Until recently, Commissioning, Acceptance and Maintenance Plan (CAMP) deliverables on major projects were delegated to the contractor for determining format, content, level of detail and the submittal date.   Typically, the compilation of the associated deliverables was part of final acceptance of contract products by the Buyer and achieving the performance milestone by Seller for contract completion.   At contract completion, the withheld retainage by the Buyer, which can be 5% deducted from all Seller’s progress payments through 100% earned contract value, becomes part of the contract closeout.   As a result, contractors typically leave the CAMP deliverables until the end of the contract.

Contract closeout means the Buyer’s Project Manager (PM) can close the remaining administrative office, package the files for storage, and be reassigned to other projects on a full-time basis.  For the Seller’s PM, it means all financial reimbursement obligations are complete and they can close files and financial bookings, and reassign any remaining staff to other contracts.

However, there are numerous Lessons on contracts from closeout experiences that reflect poor quality and incomplete CAMP deliverables.  The situation is compounded by the urgency of the Buyer’s PM to closeout the contract and of the Seller’s PM to collect all retainage due from the already approved payments.  At this time on the contract lifecycle, CAMP deliverables can easily become secondary, as both PM’s are usually focused on closeout and moving on to new projects or contracts.

In order to mitigate the risk of poor quality and incomplete CAMP deliverables on rail transit projects, a major United States (USA) commuter railroad updated its requirements for consultant design contracts and contractor construction contracts.  The scope of work for design contracts specify that a CAMP Matrix be developed and submitted with each level of deliverables.   The Division 1 Specifications for the construction contracts specify the CAMP as a deliverable with scope, product and execution requirements that include the CAMP Matrix – developed by the design consultant.  

The CAMP Matrix includes the major systems constructed, and for deliverables, such as Training, Operation and Maintenance Manuals, Spare Parts, Software, Software Licenses, Warranty, and As-built drawings, which are itemized in the Divisions 2-16 Specifications of the construction contract.   Some Mega projects also include deliverables for BIM/GIS, Asset Management and service contract agreements.   As the Matrix progresses from the design contract and into the construction contract, more detailed descriptions of the components /systems of the constructed product are incorporated.  This creates better understanding of the CAMP deliverables. 

Since implementing in the late 2000’s, the USA commuter railroad has collected Lessons Learned on CAMP requirements, which are used during the development of new projects and contracts.   Enhancing the contracts was proven to enable Buyer’s PMs to better manage the Seller’s PMs and realize higher quality and comprehensive CAMP deliverables that met the real expectations of the Owner’s operating departments.   

The CAMP Matrix makes it clearer to both PM’s on the scope of deliverables and it provides the foundation for expanding the use into alternate delivery contracts such as Design Build (DB).   Thanks to designing CAMP into the deliverables, the Seller for DBB contract has well defined requirements and deliverables scope for CAMP.  In DB contract, the Seller will develop the CAMP scope during the design phase and compile the source documents from construction contract submittals from the DB prime and all its subcontractors and vendors/suppliers.  

Due to the size of scope and contract values on mega projects, the planned intermediate use of contract products for operational use ahead of the contract completion/final acceptance milestone is a practical necessity.   In the current rail transit environment in USA, the project leadership commitments to funding partners, stakeholders, politicians and influencers create urgency to place products in-service for Ribbon Cutting ceremonies and press conferences.   As a result, Owner’s assume responsibility for maintenance well ahead on the scheduled contract or project completion.  This requires that the usual end-of-contract CAMP activities become incremental and intermediate, and the project team needs to adjust project management staffing by Buyers and Sellers to expedite CAMP deliverables.

Good Practices for CAMP

  • Identify detailed CAMP roles, responsibilities, personnel interfaces and scope  interdependencies in Project Management Plans, Project Quality Plans, Contract Quality Plans, Construction Monitoring Plans, Integration Plans and Contract Management/Administration Plans
  • Integrate the CAMP requirements, including processes/work flows and schedules, into the technical specifications of contracts and contractors’ subcontract agreements and purchase orders
  • Insist CAMP activities and deliverables be defined in contract performance milestones and in the contractor’s Detailed Contract Schedule.
  • Define and dedicate manpower for Points Of Contact (POC) and signature approval authorities from the Owner, Buyer’s PM and Seller’s PM
  • Create performance monitoring metrics for reporting progress on CAMP deliverables to project management leadership and to Owners
  • Provide comprehensive portfolio of samples that can be used as Models for all deliverables and other written documentation necessary for the lifecycle of CAMP.

Topics for Further Consideration at Closeout:

  • Assigning a Value for Warranty - Payable after Warranty Period Ends:   The integration of formal and enforceable contract requirements for CAMP may necessitate a change in the contract performance milestones.   While impractical – based on current Owner/Contractor transactions, withholding a percentage of payments to cover the warranty period may be needed to assure equal priority by Buyer’s PM and Seller’s PM to the Owner’s requirements.  Equally, Owner’s need to dedicate a team to extend the management for warranty from the initiate incremental acceptance products up to one year after contract final acceptance or as otherwise defined in the contract, which is more typically construction completion.
  • Defining the Owner’s Project/Operating Role and Resources for Commissioning:  CAMP is part of the Seller’s contract.  But the actual commissioning includes the Owner’s activities to take responsibility for the contract product and undertake project and operating budget reimbursed actions to ready the organization to assign manpower and budget accordingly.   The Commissioning may need to extend to the end of the contractor’s Warranty period.

 

TIP:   CAMP deliverables should be tailored to the Owner’s expectations and to SAMPLES of CAMP documents accepted to the Owner on previous contracts.

TIP:   CAMP deliverables should utilize as many of the documents reviewed during construction contract Submittals, which typically include detailed instructions for start-up, operation and maintenance as well as a list of recommended consumable parts, replacement spare parts, inspections, warranty and trouble shooting information. 

TIP:  Owner/Buyer should compile a set of SAMPLE documents – proven acceptable to Owner POCs, that can be used by Buyer/Seller PMs to create and distribute CAMP deliverables. 

TIP:   Buyer’s CAMP Manager should have access to information across various functional silos of the project management organization and data management system software, including design (CAMP development), construction (CAMP implementation and training records), quality (Product/system tests, inspections and various reports) and commercial (Contract changes, requests for acceptance, payment for spare parts, and requests for release of retainage). 

TIP:   Since final acceptance of products initiates the start of the Seller’s warranty period, Seller’s PM, Buyer PM’s and Owner should create a post contract completion team to monitor the warranty lifecycle, which may occur while construction is on-going and extend after contract completion is achieved.

TIP:   Since receipt of spare parts is in the CAMP scope, Buyer’s and Seller’s PMs need to establish a formal process and documentation to manage the transfer of spare parts to support the incremental final acceptance of contract products.  

TIP:   Typical projects start with a Kick-Off Meeting, the completion of CAMP including the warranty period one-year after contract final completion, should be finalized by a Closeout Meeting between the Owner, Buyer’s PM and Seller’s PM.   As may be required, Owner’s final evaluation of Seller’s performance should record and assessment for CAMP and Warranty.

TIP:    Mega projects always start with a ground breaking ceremony where top officials from the Owner, Buyer’s PM team, Seller, Funding Partners, politicians and other influencers are smiling and holding shovels.   The CAMP deliverables and the completion of warranty – one year after full contract completion should be equally ceremonial, such as a press conference with similes, hand-shakes and words of satisfaction between the Owner, Buyer’s PM and Seller’s PM.  As may be required, Owner’s final evaluation of Seller’s performance should record and assessment for CAMP and Warranty.

Posted on: December 06, 2019 10:12 PM | Permalink | Comments (2)
ADVERTISEMENTS

"You can't build a reputation on what you are going to do."

- Henry Ford

ADVERTISEMENT

Sponsors