CAMP Questions and Answers - Part 2
| This article complements the previous articles “What are good practices for Commissioning Acceptance and Maintenance Plan (CAMP)?” and Questions and Answers to CAMP – Part 1. Here are Questions and Answers to CAMP – Part 2. What are the CAMP deliverables? Typical contract sections or project plans for CAMP deliverables are:
Who is responsible for CAMP? CAMP is a cross-functional process and it is correlated with various activities and the creation of various project records. As established by the project in the Schedule Work Breakdown Structure, the CAMP process monitors work across several managerial silos. In some Electronic Document Management Systems, the managerial silos or project phases include: Design: The development and refinement of project product requirements, and the creation of contract documents and performance metrics for the product meeting the Buyer’s criteria and business case results. Construction: The physical fabrication/manufacture of systems, brick & mortar assembly of a structure for the systems, and the integrated start-up and testing the entire product for Buyers acceptance. Quality: The control and assurance on the product, processes and documentation meet the Buyer’s requirements for the project product, including design and construction submittals and deliverables and the content for CAMP. Commercial: The management of project finances, contract payments and closeout, contract changes and of contractor performance to schedule milestones, which includes monitoring incentives for beating milestones and liquidated damages for missing milestones. What typical CAMP activities should be in the Detailed Contract Schedule? A sample of the critical cross functional activities with responsibilities by Buyer/Seller are:
|
CAMP Questions and Answers - Part 1
| This article complements the previous article “What are good practices for Commissioning Acceptance and Maintenance Plan (CAMP)?” Tailored to rail transit projects, this article follows with Q&A on CAMP definitions, description of CAMP deliverables, integrated managerial functions supporting CAMP, and the general activities and sequence for CAMP. Here are Questions and Answers to CAMP – Part 1. When Does the CAMP Process Start? CAMP starts with the design of the project and the creation of construction documents, and it continues through the closeout of the contract/project. The process will consist of iterative development of a content a Matrix that lists the components that will form the constructed product as described in the project scope and objective. The Matrix also lists the expected CAMP deliverables, such as Operation and Maintenance Manuals, Warranty, Training, As-Built Drawings, Spare Parts, Software, and GIS/Asset Management data. Starting the work in the design will assure that at the time of the construction contract award, the Seller and Buyer have the same expectations for the CAMP deliverables. What are the definitions for CAMP? Commissioning: This is the pre-requisite activities and deliverables for starting the CAMP package and deliverables for Acceptance, and it is the Buyer’s (Owner) process for verification of project/contract scope and the Seller’s (Contractor) compliance with requirements. The activities typically include Factory Acceptance Testing (FAT), On-Site Acceptance Testing (SAT), In-progress Inspections, Start-Up and Burn-In. Commissioning activities should be integrated into Project Control schedules and Quality Plans, which contain quality control test and inspection plans. Acceptance: This is a predecessor activity for contract closeout, and it refers to the Final Acceptance by the Buyer/Owner, which follows completion of Commissioning activities and A) Final formal inspection of the Seller’s work. B) Seller’s completion of punchlist work. C) Buyer’s confirming resolution of Submittals and Non-Conformance Reports (NCR). D) Buyer’s receipt of Seller’s training, As-Built drawings, Spare parts, Warranty, Operation and Maintenance Manuals (Inspection and Maintenance). E) BIM/GIS and Asset Management Data. Contractually, Acceptance equates to Construction Completion, which its tied directly to commercial provisions, Final Payment and Warranty, and is a milestone for the Project Control schedule. Maintenance: This is a post-contract closeout activity and it refers to Buyer’s readiness to conduct periodic inspections and maintain the Seller’s accepted work. The Buyer’s readiness includes A) Allocating operating budget and assign management responsibility. B) Purchase and inventory of special tools, consumable items and spare parts. C) Assign new or reallocate operation/maintenance staff and resources. D) Update company asset inventory and insurance. What are CAMP requirements? The requirements for the items cited in the definitions above are typically embedded in the contract document. Typical contract sections or project plans for CAMP technical requirements or inputs in rail transit are:
|
Good practices for Commissioning Acceptance and Maintenance Plans (CAMP)?
| Until recently, Commissioning, Acceptance and Maintenance Plan (CAMP) deliverables on major projects were delegated to the contractor for determining format, content, level of detail and the submittal date. Typically, the compilation of the associated deliverables was part of final acceptance of contract products by the Buyer and achieving the performance milestone by Seller for contract completion. At contract completion, the withheld retainage by the Buyer, which can be 5% deducted from all Seller’s progress payments through 100% earned contract value, becomes part of the contract closeout. As a result, contractors typically leave the CAMP deliverables until the end of the contract. Contract closeout means the Buyer’s Project Manager (PM) can close the remaining administrative office, package the files for storage, and be reassigned to other projects on a full-time basis. For the Seller’s PM, it means all financial reimbursement obligations are complete and they can close files and financial bookings, and reassign any remaining staff to other contracts. However, there are numerous Lessons on contracts from closeout experiences that reflect poor quality and incomplete CAMP deliverables. The situation is compounded by the urgency of the Buyer’s PM to closeout the contract and of the Seller’s PM to collect all retainage due from the already approved payments. At this time on the contract lifecycle, CAMP deliverables can easily become secondary, as both PM’s are usually focused on closeout and moving on to new projects or contracts. In order to mitigate the risk of poor quality and incomplete CAMP deliverables on rail transit projects, a major United States (USA) commuter railroad updated its requirements for consultant design contracts and contractor construction contracts. The scope of work for design contracts specify that a CAMP Matrix be developed and submitted with each level of deliverables. The Division 1 Specifications for the construction contracts specify the CAMP as a deliverable with scope, product and execution requirements that include the CAMP Matrix – developed by the design consultant. The CAMP Matrix includes the major systems constructed, and for deliverables, such as Training, Operation and Maintenance Manuals, Spare Parts, Software, Software Licenses, Warranty, and As-built drawings, which are itemized in the Divisions 2-16 Specifications of the construction contract. Some Mega projects also include deliverables for BIM/GIS, Asset Management and service contract agreements. As the Matrix progresses from the design contract and into the construction contract, more detailed descriptions of the components /systems of the constructed product are incorporated. This creates better understanding of the CAMP deliverables. Since implementing in the late 2000’s, the USA commuter railroad has collected Lessons Learned on CAMP requirements, which are used during the development of new projects and contracts. Enhancing the contracts was proven to enable Buyer’s PMs to better manage the Seller’s PMs and realize higher quality and comprehensive CAMP deliverables that met the real expectations of the Owner’s operating departments. The CAMP Matrix makes it clearer to both PM’s on the scope of deliverables and it provides the foundation for expanding the use into alternate delivery contracts such as Design Build (DB). Thanks to designing CAMP into the deliverables, the Seller for DBB contract has well defined requirements and deliverables scope for CAMP. In DB contract, the Seller will develop the CAMP scope during the design phase and compile the source documents from construction contract submittals from the DB prime and all its subcontractors and vendors/suppliers. Due to the size of scope and contract values on mega projects, the planned intermediate use of contract products for operational use ahead of the contract completion/final acceptance milestone is a practical necessity. In the current rail transit environment in USA, the project leadership commitments to funding partners, stakeholders, politicians and influencers create urgency to place products in-service for Ribbon Cutting ceremonies and press conferences. As a result, Owner’s assume responsibility for maintenance well ahead on the scheduled contract or project completion. This requires that the usual end-of-contract CAMP activities become incremental and intermediate, and the project team needs to adjust project management staffing by Buyers and Sellers to expedite CAMP deliverables. Good Practices for CAMP
Topics for Further Consideration at Closeout:
TIP: CAMP deliverables should be tailored to the Owner’s expectations and to SAMPLES of CAMP documents accepted to the Owner on previous contracts. TIP: CAMP deliverables should utilize as many of the documents reviewed during construction contract Submittals, which typically include detailed instructions for start-up, operation and maintenance as well as a list of recommended consumable parts, replacement spare parts, inspections, warranty and trouble shooting information. TIP: Owner/Buyer should compile a set of SAMPLE documents – proven acceptable to Owner POCs, that can be used by Buyer/Seller PMs to create and distribute CAMP deliverables. TIP: Buyer’s CAMP Manager should have access to information across various functional silos of the project management organization and data management system software, including design (CAMP development), construction (CAMP implementation and training records), quality (Product/system tests, inspections and various reports) and commercial (Contract changes, requests for acceptance, payment for spare parts, and requests for release of retainage). TIP: Since final acceptance of products initiates the start of the Seller’s warranty period, Seller’s PM, Buyer PM’s and Owner should create a post contract completion team to monitor the warranty lifecycle, which may occur while construction is on-going and extend after contract completion is achieved. TIP: Since receipt of spare parts is in the CAMP scope, Buyer’s and Seller’s PMs need to establish a formal process and documentation to manage the transfer of spare parts to support the incremental final acceptance of contract products. TIP: Typical projects start with a Kick-Off Meeting, the completion of CAMP including the warranty period one-year after contract final completion, should be finalized by a Closeout Meeting between the Owner, Buyer’s PM and Seller’s PM. As may be required, Owner’s final evaluation of Seller’s performance should record and assessment for CAMP and Warranty. TIP: Mega projects always start with a ground breaking ceremony where top officials from the Owner, Buyer’s PM team, Seller, Funding Partners, politicians and other influencers are smiling and holding shovels. The CAMP deliverables and the completion of warranty – one year after full contract completion should be equally ceremonial, such as a press conference with similes, hand-shakes and words of satisfaction between the Owner, Buyer’s PM and Seller’s PM. As may be required, Owner’s final evaluation of Seller’s performance should record and assessment for CAMP and Warranty. |