Project Management

Project Management View from Rail Transit Programs and Projects

by
A collection of articles sharing project processes, design and construction experience, best practices, and lessons learned along with operational knowledge related to executing programs and projects in the rail transit industry.

About this Blog

RSS

Recent Posts

Transitioning Constructed Products from Projects to Owner's Operations

Lessons to be Learned.  What Happens When the Buyer is Not the Owner, Operator and Maintainer of the Company?  

Managing Warranty After Achieving Contract Milestones

What Happens After the Buyer and Seller Agree on a Punchlist?

What is a Punchlist?

Categories

Acceptance, Analytics, ANSI, Asset Management, Best Value, Best Value Contractor Selection, Best Value Selection Criteria, Buyer, Certifications, Commissioning, Communications Management, Construction, Construction Completion, Construction Deliverables, construction manager, Construction Monitoring, Construction Submittals, Consultant, Consultant Contract, Contract Acquisition, Contract Completion, Contract Deliverables, Contract Delivery, Contract Development, Contract Integration, Contract Management, Contract Milestones, Contract Quality, Contract Requirements, Contract Submittals, Contracts, Decision Making, Definitions, Design, Design Bid Build, Design Build, Design Build Delivery, Design Deliverables, Design Services, Design Submittals, Design-Bid-Build, Division 1 Specifications, Document Control, Earned Value Management, Engineering, Estimating, Estimator, Ethics, Factory Acceptance Test, Final Acceptance, Final Completion, General Conditions, General Provisions, General Terms and Conditions, Good Practices, Government, Hard Risks, Hazards, Human Resources, Information For Bidders, Inspection, Inspection and Testing, Inspection Test Plan, Integration, Integration Management, Invitation For Bid, Key Performance Indicators, Knowledge Management, Maintenance, Management Integration, Managerial Time, Managing Change, Managing Changes, Master Project Schedule, Meeting Minutes, Mega Projects, NCR Process, Negotiations, Non Conformance Report, O&M Manuals, Oversight Reports, PM Fundamentals, PMBOK, PMI, PMO, Procurement Management, Professional Obligations, Program Management, program manager, Progress Reports, Project Charter, Project Controls, Project Engineer, Project Engineering, Project Integration, Project Interfacing, Project Management, Project Management Institute, project management office, Project Management Plan, Project Manager, Project Managerr, Project Planning, Project Records, Project Schedules, Project Team, Project Teams, ProjectManagement, Public Relations, punchlist, Quality, Quality, Rail Car Purchase, Rail Transit, Rail Transit Organization, Rail Transit Project, Rail Transit Projects, Railroad, Reliability, Resource Management, RFI Logs, risk, Risk Allocation, risk allocation, Risk Allocations, Risk Management, Risk Management, Safety, Schedule Interfaces, Schedule Management, Schedule Milestones, Scheduler, Scheduling, Scope of Work, Security, Seller, Site Acceptance Test, Soft Risks, Special Inspections, Specifications, Submittal Logs, Submittal Process, Substantial Completion, System Integration, System Integration Test, Systems, Systems Purchase, Testing/Test Management, Threats, Transformation, Transformational Projects, Transportation, Vulnerability, Work Area, Work Areas

Date

What is a Punchlist?

linkedin twitter facebook Request to reuse this  

A punchlist is most common in the construction industry.  But it may be an overused term on prime contracts between Buyers and Sellers - when a simple To-Do-List might be more appropriate description for a tool construction managers (CM) use to monitor contractor progress toward achieving contract milestones.  

Punchlist is not normally part of the definitions in the construction contract Form.   As a result, Punchlist means different things to Sellers and Buyers.

Definition

From various sources of expertise, punchlist is described as:

  • American Institute of Architects (A201-2017):  @ Substantial Completion – a comprehensive list of items to be completed prior to final payment.
  • Design Build Institute of America (535): @ Substantial Completion - (ii) the remaining items of work that have to be completed before final payment.  
  • PMI PMBOK Construction: the work items that are identified during a final inspection that need to be completed.
  • Construction Coverage (website):  is a document created in the final stages of a construction project to provide a list of items that must be addressed before construction is considered complete and payment is issued.
  • Merriam-Webster (dictionary):  a list of usually minor tasks to be completed at the end of a project.

Punchlist is interdependent with the progress of work by the Seller and the milestones specified by the Buyer in the Contract.  The milestones are typically contained in the General Conditions/Provisions (GCs) of a contract document.  Punchlist creation is associated with substantial completion and punchlist completion is associated with construction completion.   

Work Flow

Punchlist work flow:

  1. Seller and Buyer's CM confirm to Buyer Project Manager work is substantially completed
  2. Buyer's CM/Project Manager coordinates inspections by the Buyer's project team members and other stakeholders and creates a punchlist
  3. Buyer's CM submits the punchlist for review and final edits by the project team and stakeholders
  4. Buyer's Contracting Officer acknowledges substantial completion to Seller, submits the punchlist for Seller's corrective action by the construction completion date 
  5. Seller and Buyer's CM confirm to Buyer's Project Manager all work is completed and achieved construction completion
  6. Buyer's CM/Project Manager coordinates final inspections by the Buyer's project team members and other stakeholders to verify all items on the punchlist are completed
  7. Buyer's Contracting Officer acknowledges construction completion and instructs Seller to demobilize and perform site restoration by the final completion/contract completion milestone.

Most US standard contract Forms, cite the requirements for substantial completion and construction completion in the General Conditions/Provisions regarding section related to Performance Schedule and Payments.   

Punchlist Content

The content of a punchlist should contain only minor touch-ups and repairs to installed/constructed work that is described by specific in-scope observations and the locations to be corrected for completion.   A punchlist that contains base scope items not yet installed or tested and operational is not acceptable and not suitable for meeting the completion milestone.   Items observed that are not in-scope will be deleted from the punchlist and be addressed by the Buyer through other project processes for changes to work. 

In addition to contract milestones and payments, an acceptable punchlist that the Buyer determines meets the substantial completion requirements is often tied to incentives and liquidated damages.   Meeting substantial completion is also related to other contract requirements. 

Punchlist Interfaces

Interfaces with other contract requirements in the work flow include:  Item 4-After substantial completion, Seller and Buyer can initiate reconciliation of incentives and liquidated damages.  Buyer can suspend consideration of all potential changes, instruct Seller to demobilize and to perform site restoration by the final completion/contract completion milestone, request Seller to submit deliverables such as O&M Manuals, As-Built Drawings Package and Warranties, and if applicable, release performance bonds.   Item 5-After construction completion, Seller and Buyer can initiate the contract closeout.  Item 7-After demobilization, Seller can reduce insurance coverage.

TIP:   A punchlist should only be submitted once by Seller and reviewed by Buyer for completeness an accuracy.  Thereafter, it is locked down.  No items can be addressed.  Items can only be verified as completed and closed.  

TIP:  All items on the punchlist should be addressed and closed by the Sellers within a period that avoids the risk of further damage or new conditions that requires corrective action. 

TIP:    For Buyer’s, including their construction managers, that require in-progress punchlists to assess the contractor’s physical work relative to the construction substantial completion milestone, a more granular definition of punchlist may be neededHere are some proposed definitions that can provide guidance to Buyer and Seller as the punchlist changes with the progress of construction.

  • In-Progress/Preliminary Punchlist:   List of remaining work and corrections prepared and submitted prior to the milestone for substantial completion, and it may contain items that are part of the base scope but not yet installed and tested.  This Punchlist is submitted as information, and it represents Buyer and Seller  in-progress inspection observations from multiple parties.   This Llist is monitored until substantial completion is achieved by the Seller.   
  • Formal Punchlist:  List of remaining work and corrections is mutually prepared by the Buyer, Buyer’s construction manager, and Seller after substantial completion, which represents the work is ready for it intended use, all tests are completed and all work is operational.   This Punchlist is submitted for review and comments by Buyer.   Concurrently, Buyer will schedule a walkthrough inspection by the Buyer and all end user representatives to compile a complete punchlist.  This List with comments resolved will be the official list of remaining work.
  • Final Punchlist:  List of items confirmed completed by the Seller and confirmed completed by Buyer or Buyer’s construction manager.  This Punchlist is submitted for Buyer Sign-Off along with a request by Seller  for final walkthrough.   The Buyer arranges for all parties to attend for sign-off that all items on the punchlist.    Sign-off of this Punchlist is the predecessor to Buyer’s acceptance of the Seller’s work, which is an interdependency of criteria for completing the contract closeout.   

TIP:   An observation listed on the punchlist should identify the inspecting agency/inspector name and date, cite the specific location (s) and the drawing/specification/code, and describe the needed correction to meet with the contract requirements, approved shop drawings or other industry standards for the type of work.

TIP:  The punchlist observations should be actionable and the description begin with words such as repair, replace, adjust, touch-up, polish, remove, rebalance and clean.  Items with words such as install, test, paint, fill, energize, backfill and connect may indicate that base scope is not yet completed. 

Posted on: September 05, 2022 01:40 PM | Permalink | Comments (4)

What is a Punchlist?

linkedin twitter facebook Request to reuse this  

A punchlist is most common in the construction industry.  But it may be an overused term on prime contracts between Buyers and Sellers - when a simple To-Do-List might be more appropriate description for a tool construction managers (CM) use to monitor contractor progress toward achieving contract milestones.  

Punchlist is not normally part of the definitions in the construction contract Form.   As a result, Punchlist means different things to Sellers and Buyers.

Definition

From various sources of expertise, punchlist is described as:

  • American Institute of Architects (A201-2017):  @ Substantial Completion – a comprehensive list of items to be completed prior to final payment.
  • Design Build Institute of America (535): @ Substantial Completion - (ii) the remaining items of work that have to be completed before final payment.  
  • PMI PMBOK Construction: the work items that are identified during a final inspection that need to be completed.
  • Construction Coverage (website):  is a document created in the final stages of a construction project to provide a list of items that must be addressed before construction is considered complete and payment is issued.
  • Merriam-Webster (dictionary):  a list of usually minor tasks to be completed at the end of a project.

Punchlist is interdependent with the progress of work by the Seller and the milestones specified by the Buyer in the Contract.  The milestones are typically contained in the General Conditions/Provisions (GCs) of a contract document.  Punchlist creation is associated with substantial completion and punchlist completion is associated with construction completion.   

Work Flow

Punchlist work flow:

  1. Seller and Buyer's CM confirm to Buyer Project Manager work is substantially completed
  2. Buyer's CM/Project Manager coordinates inspections by the Buyer's project team members and other stakeholders and creates a punchlist
  3. Buyer's CM submits the punchlist for review and final edits by the project team and stakeholders
  4. Buyer's Contracting Officer acknowledges substantial completion to Seller, submits the punchlist for Seller's corrective action by the construction completion date 
  5. Seller and Buyer's CM confirm to Buyer's Project Manager all work is completed and achieved construction completion
  6. Buyer's CM/Project Manager coordinates final inspections by the Buyer's project team members and other stakeholders to verify all items on the punchlist are completed
  7. Buyer's Contracting Officer acknowledges construction completion and instructs Seller to demobilize and perform site restoration by the final completion/contract completion milestone.

Most US standard contract Forms, cite the requirements for substantial completion and construction completion in the General Conditions/Provisions regarding section related to Performance Schedule and Payments.   

Punchlist Content

The content of a punchlist should contain only minor touch-ups and repairs to installed/constructed work that is described by specific in-scope observations and the locations to be corrected for completion.   A punchlist that contains base scope items not yet installed or tested and operational is not acceptable and not suitable for meeting the completion milestone.   Items observed that are not in-scope will be deleted from the punchlist and be addressed by the Buyer through other project processes for changes to work. 

In addition to contract milestones and payments, an acceptable punchlist that the Buyer determines meets the substantial completion requirements is often tied to incentives and liquidated damages.   Meeting substantial completion is also related to other contract requirements. 

Punchlist Interfaces

Interfaces with other contract requirements in the work flow include:  Item 4-After substantial completion, Seller and Buyer can initiate reconciliation of incentives and liquidated damages.  Buyer can suspend consideration of all potential changes, instruct Seller to demobilize and to perform site restoration by the final completion/contract completion milestone, request Seller to submit deliverables such as O&M Manuals, As-Built Drawings Package and Warranties, and if applicable, release performance bonds.   Item 5-After construction completion, Seller and Buyer can initiate the contract closeout.  Item 7-After demobilization, Seller can reduce insurance coverage.

TIP:   A punchlist should only be submitted once by Seller and reviewed by Buyer for completeness an accuracy.  Thereafter, it is locked down.  No items can be addressed.  Items can only be verified as completed and closed.  

TIP:  All items on the punchlist should be addressed and closed by the Sellers within a period that avoids the risk of further damage or new conditions that requires corrective action. 

TIP:    For Buyer’s, including their construction managers, that require in-progress punchlists to assess the contractor’s physical work relative to the construction substantial completion milestone, a more granular definition of punchlist may be neededHere are some proposed definitions that can provide guidance to Buyer and Seller as the punchlist changes with the progress of construction.

  • In-Progress/Preliminary Punchlist:   List of remaining work and corrections prepared and submitted prior to the milestone for substantial completion, and it may contain items that are part of the base scope but not yet installed and tested.  This Punchlist is submitted as information, and it represents Buyer and Seller  in-progress inspection observations from multiple parties.   This Llist is monitored until substantial completion is achieved by the Seller.   
  • Formal Punchlist:  List of remaining work and corrections is mutually prepared by the Buyer, Buyer’s construction manager, and Seller after substantial completion, which represents the work is ready for it intended use, all tests are completed and all work is operational.   This Punchlist is submitted for review and comments by Buyer.   Concurrently, Buyer will schedule a walkthrough inspection by the Buyer and all end user representatives to compile a complete punchlist.  This List with comments resolved will be the official list of remaining work.
  • Final Punchlist:  List of items confirmed completed by the Seller and confirmed completed by Buyer or Buyer’s construction manager.  This Punchlist is submitted for Buyer Sign-Off along with a request by Seller  for final walkthrough.   The Buyer arranges for all parties to attend for sign-off that all items on the punchlist.    Sign-off of this Punchlist is the predecessor to Buyer’s acceptance of the Seller’s work, which is an interdependency of criteria for completing the contract closeout.   

TIP:   An observation listed on the punchlist should identify the inspecting agency/inspector name and date, cite the specific location (s) and the drawing/specification/code, and describe the needed correction to meet with the contract requirements, approved shop drawings or other industry standards for the type of work.

TIP:  The punchlist observations should be actionable and the description begin with words such as repair, replace, adjust, touch-up, polish, remove, rebalance and clean.  Items with words such as install, test, paint, fill, energize, backfill and connect may indicate that base scope is not yet completed. 

Posted on: September 05, 2022 01:40 PM | Permalink | Comments (4)

What is a Punchlist?

linkedin twitter facebook Request to reuse this  

A punchlist is most common in the construction industry.  But it may be an overused term on prime contracts between Buyers and Sellers - when a simple To-Do-List might be more appropriate description for a tool construction managers (CM) use to monitor contractor progress toward achieving contract milestones.  

Punchlist is not normally part of the definitions in the construction contract Form.   As a result, Punchlist means different things to Sellers and Buyers.

Definition

From various sources of expertise, punchlist is described as:

  • American Institute of Architects (A201-2017):  @ Substantial Completion – a comprehensive list of items to be completed prior to final payment.
  • Design Build Institute of America (535): @ Substantial Completion - (ii) the remaining items of work that have to be completed before final payment.  
  • PMI PMBOK Construction: the work items that are identified during a final inspection that need to be completed.
  • Construction Coverage (website):  is a document created in the final stages of a construction project to provide a list of items that must be addressed before construction is considered complete and payment is issued.
  • Merriam-Webster (dictionary):  a list of usually minor tasks to be completed at the end of a project.

Punchlist is interdependent with the progress of work by the Seller and the milestones specified by the Buyer in the Contract.  The milestones are typically contained in the General Conditions/Provisions (GCs) of a contract document.  Punchlist creation is associated with substantial completion and punchlist completion is associated with construction completion.   

Work Flow

Punchlist work flow:

  1. Seller and Buyer's CM confirm to Buyer Project Manager work is substantially completed
  2. Buyer's CM/Project Manager coordinates inspections by the Buyer's project team members and other stakeholders and creates a punchlist
  3. Buyer's CM submits the punchlist for review and final edits by the project team and stakeholders
  4. Buyer's Contracting Officer acknowledges substantial completion to Seller, submits the punchlist for Seller's corrective action by the construction completion date 
  5. Seller and Buyer's CM confirm to Buyer's Project Manager all work is completed and achieved construction completion
  6. Buyer's CM/Project Manager coordinates final inspections by the Buyer's project team members and other stakeholders to verify all items on the punchlist are completed
  7. Buyer's Contracting Officer acknowledges construction completion and instructs Seller to demobilize and perform site restoration by the final completion/contract completion milestone.

Most US standard contract Forms, cite the requirements for substantial completion and construction completion in the General Conditions/Provisions regarding section related to Performance Schedule and Payments.   

Punchlist Content

The content of a punchlist should contain only minor touch-ups and repairs to installed/constructed work that is described by specific in-scope observations and the locations to be corrected for completion.   A punchlist that contains base scope items not yet installed or tested and operational is not acceptable and not suitable for meeting the completion milestone.   Items observed that are not in-scope will be deleted from the punchlist and be addressed by the Buyer through other project processes for changes to work. 

In addition to contract milestones and payments, an acceptable punchlist that the Buyer determines meets the substantial completion requirements is often tied to incentives and liquidated damages.   Meeting substantial completion is also related to other contract requirements. 

Punchlist Interfaces

Interfaces with other contract requirements in the work flow include:  Item 4-After substantial completion, Seller and Buyer can initiate reconciliation of incentives and liquidated damages.  Buyer can suspend consideration of all potential changes, instruct Seller to demobilize and to perform site restoration by the final completion/contract completion milestone, request Seller to submit deliverables such as O&M Manuals, As-Built Drawings Package and Warranties, and if applicable, release performance bonds.   Item 5-After construction completion, Seller and Buyer can initiate the contract closeout.  Item 7-After demobilization, Seller can reduce insurance coverage.

TIP:   A punchlist should only be submitted once by Seller and reviewed by Buyer for completeness an accuracy.  Thereafter, it is locked down.  No items can be addressed.  Items can only be verified as completed and closed.  

TIP:  All items on the punchlist should be addressed and closed by the Sellers within a period that avoids the risk of further damage or new conditions that requires corrective action. 

TIP:    For Buyer’s, including their construction managers, that require in-progress punchlists to assess the contractor’s physical work relative to the construction substantial completion milestone, a more granular definition of punchlist may be neededHere are some proposed definitions that can provide guidance to Buyer and Seller as the punchlist changes with the progress of construction.

  • In-Progress/Preliminary Punchlist:   List of remaining work and corrections prepared and submitted prior to the milestone for substantial completion, and it may contain items that are part of the base scope but not yet installed and tested.  This Punchlist is submitted as information, and it represents Buyer and Seller  in-progress inspection observations from multiple parties.   This Llist is monitored until substantial completion is achieved by the Seller.   
  • Formal Punchlist:  List of remaining work and corrections is mutually prepared by the Buyer, Buyer’s construction manager, and Seller after substantial completion, which represents the work is ready for it intended use, all tests are completed and all work is operational.   This Punchlist is submitted for review and comments by Buyer.   Concurrently, Buyer will schedule a walkthrough inspection by the Buyer and all end user representatives to compile a complete punchlist.  This List with comments resolved will be the official list of remaining work.
  • Final Punchlist:  List of items confirmed completed by the Seller and confirmed completed by Buyer or Buyer’s construction manager.  This Punchlist is submitted for Buyer Sign-Off along with a request by Seller  for final walkthrough.   The Buyer arranges for all parties to attend for sign-off that all items on the punchlist.    Sign-off of this Punchlist is the predecessor to Buyer’s acceptance of the Seller’s work, which is an interdependency of criteria for completing the contract closeout.   

TIP:   An observation listed on the punchlist should identify the inspecting agency/inspector name and date, cite the specific location (s) and the drawing/specification/code, and describe the needed correction to meet with the contract requirements, approved shop drawings or other industry standards for the type of work.

TIP:  The punchlist observations should be actionable and the description begin with words such as repair, replace, adjust, touch-up, polish, remove, rebalance and clean.  Items with words such as install, test, paint, fill, energize, backfill and connect may indicate that base scope is not yet completed. 

Posted on: September 05, 2022 01:40 PM | Permalink | Comments (4)

What is a Punchlist?

linkedin twitter facebook Request to reuse this  

A punchlist is most common in the construction industry.  But it may be an overused term on prime contracts between Buyers and Sellers - when a simple To-Do-List might be more appropriate description for a tool construction managers (CM) use to monitor contractor progress toward achieving contract milestones.  

Punchlist is not normally part of the definitions in the construction contract Form.   As a result, Punchlist means different things to Sellers and Buyers.

Definition

From various sources of expertise, punchlist is described as:

  • American Institute of Architects (A201-2017):  @ Substantial Completion – a comprehensive list of items to be completed prior to final payment.
  • Design Build Institute of America (535): @ Substantial Completion - (ii) the remaining items of work that have to be completed before final payment.  
  • PMI PMBOK Construction: the work items that are identified during a final inspection that need to be completed.
  • Construction Coverage (website):  is a document created in the final stages of a construction project to provide a list of items that must be addressed before construction is considered complete and payment is issued.
  • Merriam-Webster (dictionary):  a list of usually minor tasks to be completed at the end of a project.

Punchlist is interdependent with the progress of work by the Seller and the milestones specified by the Buyer in the Contract.  The milestones are typically contained in the General Conditions/Provisions (GCs) of a contract document.  Punchlist creation is associated with substantial completion and punchlist completion is associated with construction completion.   

Work Flow

Punchlist work flow:

  1. Seller and Buyer's CM confirm to Buyer Project Manager work is substantially completed
  2. Buyer's CM/Project Manager coordinates inspections by the Buyer's project team members and other stakeholders and creates a punchlist
  3. Buyer's CM submits the punchlist for review and final edits by the project team and stakeholders
  4. Buyer's Contracting Officer acknowledges substantial completion to Seller, submits the punchlist for Seller's corrective action by the construction completion date 
  5. Seller and Buyer's CM confirm to Buyer's Project Manager all work is completed and achieved construction completion
  6. Buyer's CM/Project Manager coordinates final inspections by the Buyer's project team members and other stakeholders to verify all items on the punchlist are completed
  7. Buyer's Contracting Officer acknowledges construction completion and instructs Seller to demobilize and perform site restoration by the final completion/contract completion milestone.

Most US standard contract Forms, cite the requirements for substantial completion and construction completion in the General Conditions/Provisions regarding section related to Performance Schedule and Payments.   

Punchlist Content

The content of a punchlist should contain only minor touch-ups and repairs to installed/constructed work that is described by specific in-scope observations and the locations to be corrected for completion.   A punchlist that contains base scope items not yet installed or tested and operational is not acceptable and not suitable for meeting the completion milestone.   Items observed that are not in-scope will be deleted from the punchlist and be addressed by the Buyer through other project processes for changes to work. 

In addition to contract milestones and payments, an acceptable punchlist that the Buyer determines meets the substantial completion requirements is often tied to incentives and liquidated damages.   Meeting substantial completion is also related to other contract requirements. 

Punchlist Interfaces

Interfaces with other contract requirements in the work flow include:  Item 4-After substantial completion, Seller and Buyer can initiate reconciliation of incentives and liquidated damages.  Buyer can suspend consideration of all potential changes, instruct Seller to demobilize and to perform site restoration by the final completion/contract completion milestone, request Seller to submit deliverables such as O&M Manuals, As-Built Drawings Package and Warranties, and if applicable, release performance bonds.   Item 5-After construction completion, Seller and Buyer can initiate the contract closeout.  Item 7-After demobilization, Seller can reduce insurance coverage.

TIP:   A punchlist should only be submitted once by Seller and reviewed by Buyer for completeness an accuracy.  Thereafter, it is locked down.  No items can be addressed.  Items can only be verified as completed and closed.  

TIP:  All items on the punchlist should be addressed and closed by the Sellers within a period that avoids the risk of further damage or new conditions that requires corrective action. 

TIP:    For Buyer’s, including their construction managers, that require in-progress punchlists to assess the contractor’s physical work relative to the construction substantial completion milestone, a more granular definition of punchlist may be neededHere are some proposed definitions that can provide guidance to Buyer and Seller as the punchlist changes with the progress of construction.

  • In-Progress/Preliminary Punchlist:   List of remaining work and corrections prepared and submitted prior to the milestone for substantial completion, and it may contain items that are part of the base scope but not yet installed and tested.  This Punchlist is submitted as information, and it represents Buyer and Seller  in-progress inspection observations from multiple parties.   This Llist is monitored until substantial completion is achieved by the Seller.   
  • Formal Punchlist:  List of remaining work and corrections is mutually prepared by the Buyer, Buyer’s construction manager, and Seller after substantial completion, which represents the work is ready for it intended use, all tests are completed and all work is operational.   This Punchlist is submitted for review and comments by Buyer.   Concurrently, Buyer will schedule a walkthrough inspection by the Buyer and all end user representatives to compile a complete punchlist.  This List with comments resolved will be the official list of remaining work.
  • Final Punchlist:  List of items confirmed completed by the Seller and confirmed completed by Buyer or Buyer’s construction manager.  This Punchlist is submitted for Buyer Sign-Off along with a request by Seller  for final walkthrough.   The Buyer arranges for all parties to attend for sign-off that all items on the punchlist.    Sign-off of this Punchlist is the predecessor to Buyer’s acceptance of the Seller’s work, which is an interdependency of criteria for completing the contract closeout.   

TIP:   An observation listed on the punchlist should identify the inspecting agency/inspector name and date, cite the specific location (s) and the drawing/specification/code, and describe the needed correction to meet with the contract requirements, approved shop drawings or other industry standards for the type of work.

TIP:  The punchlist observations should be actionable and the description begin with words such as repair, replace, adjust, touch-up, polish, remove, rebalance and clean.  Items with words such as install, test, paint, fill, energize, backfill and connect may indicate that base scope is not yet completed. 

Posted on: September 05, 2022 01:40 PM | Permalink | Comments (4)

Know the Contract  -  Part 14, Contract Completion/Closeout

linkedin twitter facebook Request to reuse this  

This is the 14th in a series of discussions that is intended to prompt Project Teams to be aware of the entire contract document, including Information For Bidders (IFB), General Provisions/General Conditions/Terms and Conditions (GCs) and the Technical Requirements [Specifications and Drawings.] 

Part 14 of Know the Contract is Contract Completion/Closeout.   Closeout is the successor to all other work performed under the Contract and it is final set of activities between the Buyer and Seller.    While the requirements for Closeout may be scattered throughout the Contract document, the most important are described in the GC’s sections related to Schedule and Payments.   At this phase of the Contract, the Buyer’s Contracting Officer is the primary arbiter for determining that all requirements are met by the Seller and confirmed by the Buyer’s Project Manager.   

Part 6-Schedule Performance and Part 7-Progress & Milestone Payments of this series describe the content in the typical contract Form.   Satisfying these requirements precede completing the Closeout process and documentation, and includes substantiating completion of testing and start-up; training; delivering spare parts; submitting operation & maintenance manuals, software, as-built drawings, asset management data and warranty; and closure of all quality management  processes and deliverables. 

Regardless of the contracting method, such as Design-Bid-Build, Design Build and CM At Risk, the Closeout of the contract is governed by the GCs as well as any Special Conditions and terms negotiated for contract award.   The typical activities and topics include:

  • Settling all change orders, requests for extension of time due to Buyer actions,  differing site conditions or claims for extra work and damages
  • Reconciling all incentives payments and damage accruals from exceeding or delaying established milestone dates for completion of work
  • Confirming receipt of all GC deliverables, including photographs, monthly progress reports and schedules, manpower utilization reports, certified payroll and prevailing wage records,  and prompt payment records.
  • Resolving all claims, disputes, legal actions, or pending attorney actions between Buyer and Seller, including all contract issues with Seller’s subcontractors, vendors and suppliers
  • Verifying all payments and release of retainage to prime contractor, subcontractors, vendors and suppliers 
  • Processing all contract modifications and final contract amount
  • Transferring all contract records in paper and digital format

During the Closeout phase, the Buyer may develop Lessons Learned from the Seller’s performance on the Contract.  The Lessons Learned will be utilized by the Buyer to consider changes in requirements as well as management processes and documentation on future Contracts.  Some of the topics from Lessons Learned may include:

  • Effectiveness of the contracting delivery method and the Buyer’s and Seller’s organizational structure to support the work
  • Realism in Buyer’s duration for contract milestones and effectiveness of incentives and liquidated damages
  • Evaluation of Seller’s prime contractors, vendors and suppliers to meet the Buyer’s schedule deadlines
  • Buyer’s and Seller’s risk threats and opportunities mitigated and realized during the Contract
  • Change orders and claims encountered by Buyer that may be avoided by editing requirements in future Seller’s contracts.

TIP:  The responsible parties for Closeout are the Buyer’s Project Manager with support from the Buyer’s Contracting Officer and the Seller’s Project Manager with support from the Seller’s prime contracting/procurement official.

TIP:  While risking duplication of requirements, create a separate Division 1 specification covering the requirements and deliverables checklist for contract closeout.

TIP:   Most US contract Forms were written based on paper transactions throughout the Contract cycle.  Due to awareness of threats outside normal contract and project processes, security of products, deliverables and documentation is now part of controlling access to sensitive contract records.    As a result, EDMS has replaced paper documents and is used more effectively to segregate, store and restrict distribution of documents that contain sensitive information.      

TIP:  The use of electronic document control system (EDMS) has become a critical part of managing and executing the work at a project and contract level.   As a result, there may be a need to create requirements for content, format, compatibility and the transfer method of the Seller’s EDMS with the Buyer’s hardware, software and the organizational management of records.  

TIP:  Ensure Closeout requirements and terminology are well defined and are consistent with the process and requirements in the GCs.  Clarity of terms is essential for both the Buyer and Seller. 

TIP:  Buyer’s Contracting Officer should provide clear guidance to the Buyer’s Project Manager on the process, timeline and documentation required to satisfy the contract closeout.

Posted on: March 13, 2022 07:36 PM | Permalink | Comments (4)
ADVERTISEMENTS

"If you want to please only the critics, don't play too loud, too soft, too fast or too slow."

- Arturo Toscanini

ADVERTISEMENT

Sponsors