A punchlist is most common in the construction industry. But it may be an overused term on prime contracts between Buyers and Sellers - when a simple To-Do-List might be more appropriate description for a tool construction managers (CM) use to monitor contractor progress toward achieving contract milestones.
Punchlist is not normally part of the definitions in the construction contract Form. As a result, Punchlist means different things to Sellers and Buyers.
Definition
From various sources of expertise, punchlist is described as:
- American Institute of Architects (A201-2017): @ Substantial Completion – a comprehensive list of items to be completed prior to final payment.
- Design Build Institute of America (535): @ Substantial Completion - (ii) the remaining items of work that have to be completed before final payment.
- PMI PMBOK Construction: the work items that are identified during a final inspection that need to be completed.
- Construction Coverage (website): is a document created in the final stages of a construction project to provide a list of items that must be addressed before construction is considered complete and payment is issued.
- Merriam-Webster (dictionary): a list of usually minor tasks to be completed at the end of a project.
Punchlist is interdependent with the progress of work by the Seller and the milestones specified by the Buyer in the Contract. The milestones are typically contained in the General Conditions/Provisions (GCs) of a contract document. Punchlist creation is associated with substantial completion and punchlist completion is associated with construction completion.
Work Flow
Punchlist work flow:
- Seller and Buyer's CM confirm to Buyer Project Manager work is substantially completed
- Buyer's CM/Project Manager coordinates inspections by the Buyer's project team members and other stakeholders and creates a punchlist
- Buyer's CM submits the punchlist for review and final edits by the project team and stakeholders
- Buyer's Contracting Officer acknowledges substantial completion to Seller, submits the punchlist for Seller's corrective action by the construction completion date
- Seller and Buyer's CM confirm to Buyer's Project Manager all work is completed and achieved construction completion
- Buyer's CM/Project Manager coordinates final inspections by the Buyer's project team members and other stakeholders to verify all items on the punchlist are completed
- Buyer's Contracting Officer acknowledges construction completion and instructs Seller to demobilize and perform site restoration by the final completion/contract completion milestone.
Most US standard contract Forms, cite the requirements for substantial completion and construction completion in the General Conditions/Provisions regarding section related to Performance Schedule and Payments.
Punchlist Content
The content of a punchlist should contain only minor touch-ups and repairs to installed/constructed work that is described by specific in-scope observations and the locations to be corrected for completion. A punchlist that contains base scope items not yet installed or tested and operational is not acceptable and not suitable for meeting the completion milestone. Items observed that are not in-scope will be deleted from the punchlist and be addressed by the Buyer through other project processes for changes to work.
In addition to contract milestones and payments, an acceptable punchlist that the Buyer determines meets the substantial completion requirements is often tied to incentives and liquidated damages. Meeting substantial completion is also related to other contract requirements.
Punchlist Interfaces
Interfaces with other contract requirements in the work flow include: Item 4-After substantial completion, Seller and Buyer can initiate reconciliation of incentives and liquidated damages. Buyer can suspend consideration of all potential changes, instruct Seller to demobilize and to perform site restoration by the final completion/contract completion milestone, request Seller to submit deliverables such as O&M Manuals, As-Built Drawings Package and Warranties, and if applicable, release performance bonds. Item 5-After construction completion, Seller and Buyer can initiate the contract closeout. Item 7-After demobilization, Seller can reduce insurance coverage.
TIP: A punchlist should only be submitted once by Seller and reviewed by Buyer for completeness an accuracy. Thereafter, it is locked down. No items can be addressed. Items can only be verified as completed and closed.
TIP: All items on the punchlist should be addressed and closed by the Sellers within a period that avoids the risk of further damage or new conditions that requires corrective action.
TIP: For Buyer’s, including their construction managers, that require in-progress punchlists to assess the contractor’s physical work relative to the construction substantial completion milestone, a more granular definition of punchlist may be needed. Here are some proposed definitions that can provide guidance to Buyer and Seller as the punchlist changes with the progress of construction.
- In-Progress/Preliminary Punchlist: List of remaining work and corrections prepared and submitted prior to the milestone for substantial completion, and it may contain items that are part of the base scope but not yet installed and tested. This Punchlist is submitted as information, and it represents Buyer and Seller in-progress inspection observations from multiple parties. This Llist is monitored until substantial completion is achieved by the Seller.
- Formal Punchlist: List of remaining work and corrections is mutually prepared by the Buyer, Buyer’s construction manager, and Seller after substantial completion, which represents the work is ready for it intended use, all tests are completed and all work is operational. This Punchlist is submitted for review and comments by Buyer. Concurrently, Buyer will schedule a walkthrough inspection by the Buyer and all end user representatives to compile a complete punchlist. This List with comments resolved will be the official list of remaining work.
- Final Punchlist: List of items confirmed completed by the Seller and confirmed completed by Buyer or Buyer’s construction manager. This Punchlist is submitted for Buyer Sign-Off along with a request by Seller for final walkthrough. The Buyer arranges for all parties to attend for sign-off that all items on the punchlist. Sign-off of this Punchlist is the predecessor to Buyer’s acceptance of the Seller’s work, which is an interdependency of criteria for completing the contract closeout.
TIP: An observation listed on the punchlist should identify the inspecting agency/inspector name and date, cite the specific location (s) and the drawing/specification/code, and describe the needed correction to meet with the contract requirements, approved shop drawings or other industry standards for the type of work.
TIP: The punchlist observations should be actionable and the description begin with words such as repair, replace, adjust, touch-up, polish, remove, rebalance and clean. Items with words such as install, test, paint, fill, energize, backfill and connect may indicate that base scope is not yet completed.