Project Management

Project Management View from Rail Transit Programs and Projects

by
A collection of articles sharing project processes, design and construction experience, best practices, and lessons learned along with operational knowledge related to executing programs and projects in the rail transit industry.

About this Blog

RSS

Recent Posts

Transitioning Constructed Products from Projects to Owner's Operations

Lessons to be Learned.  What Happens When the Buyer is Not the Owner, Operator and Maintainer of the Company?  

Managing Warranty After Achieving Contract Milestones

What Happens After the Buyer and Seller Agree on a Punchlist?

What is a Punchlist?

Categories

Acceptance, Analytics, ANSI, Asset Management, Best Value, Best Value Contractor Selection, Best Value Selection Criteria, Buyer, Certifications, Commissioning, Communications Management, Construction, Construction Completion, Construction Deliverables, construction manager, Construction Monitoring, Construction Submittals, Consultant, Consultant Contract, Contract Acquisition, Contract Completion, Contract Deliverables, Contract Delivery, Contract Development, Contract Integration, Contract Management, Contract Milestones, Contract Quality, Contract Requirements, Contract Submittals, Contracts, Decision Making, Definitions, Design, Design Bid Build, Design Build, Design Build Delivery, Design Deliverables, Design Services, Design Submittals, Design-Bid-Build, Division 1 Specifications, Document Control, Earned Value Management, Engineering, Estimating, Estimator, Ethics, Factory Acceptance Test, Final Acceptance, Final Completion, General Conditions, General Provisions, General Terms and Conditions, Good Practices, Government, Hard Risks, Hazards, Human Resources, Information For Bidders, Inspection, Inspection and Testing, Inspection Test Plan, Integration, Integration Management, Invitation For Bid, Key Performance Indicators, Knowledge Management, Maintenance, Management Integration, Managerial Time, Managing Change, Managing Changes, Master Project Schedule, Meeting Minutes, Mega Projects, NCR Process, Negotiations, Non Conformance Report, O&M Manuals, Oversight Reports, PM Fundamentals, PMBOK, PMI, PMO, Procurement Management, Professional Obligations, Program Management, program manager, Progress Reports, Project Charter, Project Controls, Project Engineer, Project Engineering, Project Integration, Project Interfacing, Project Management, Project Management Institute, project management office, Project Management Plan, Project Manager, Project Managerr, Project Planning, Project Records, Project Schedules, Project Team, Project Teams, ProjectManagement, Public Relations, punchlist, Quality, Quality, Rail Car Purchase, Rail Transit, Rail Transit Organization, Rail Transit Project, Rail Transit Projects, Railroad, Reliability, Resource Management, RFI Logs, risk, Risk Allocation, risk allocation, Risk Allocations, Risk Management, Risk Management, Safety, Schedule Interfaces, Schedule Management, Schedule Milestones, Scheduler, Scheduling, Scope of Work, Security, Seller, Site Acceptance Test, Soft Risks, Special Inspections, Specifications, Submittal Logs, Submittal Process, Substantial Completion, System Integration, System Integration Test, Systems, Systems Purchase, Testing/Test Management, Threats, Transformation, Transformational Projects, Transportation, Vulnerability, Work Area, Work Areas

Date

CAMP Questions and Answers - Part 1

linkedin twitter facebook Request to reuse this  

This article complements the previous article “What are good practices for Commissioning Acceptance and Maintenance Plan (CAMP)?”  Tailored to rail transit projects, this article follows with  Q&A on CAMP definitions, description of CAMP deliverables, integrated managerial functions supporting CAMP, and the general activities and sequence for CAMP.    Here are Questions and Answers to CAMP – Part 1.

When Does the CAMP Process Start?

CAMP starts with the design of the project and the creation of construction documents, and it continues through the closeout of the contract/project.   The process will consist of iterative development of a content a Matrix that lists the components that will form the constructed product as described in the project scope and objective.   The Matrix also lists the expected CAMP deliverables, such as Operation and Maintenance Manuals, Warranty, Training, As-Built Drawings, Spare Parts, Software, and GIS/Asset Management data.   Starting the work in the design will assure that at the time of the construction contract award, the Seller and Buyer have the same expectations for the CAMP deliverables.

What are the definitions for CAMP?

Commissioning:   This is the pre-requisite activities and deliverables for starting the CAMP package and deliverables for Acceptance, and it is the Buyer’s (Owner) process for verification of project/contract scope and the Seller’s (Contractor) compliance with requirements.    The activities typically include Factory Acceptance Testing (FAT), On-Site Acceptance Testing (SAT), In-progress Inspections, Start-Up and Burn-In.   Commissioning activities should be integrated into Project Control schedules and Quality Plans, which contain quality control test and inspection plans.

Acceptance:  This is a predecessor activity for contract closeout, and it refers to the Final Acceptance by the Buyer/Owner, which follows completion of Commissioning activities and  A) Final formal inspection of the Seller’s work.   B) Seller’s completion of punchlist work.   C) Buyer’s  confirming resolution of Submittals and Non-Conformance Reports (NCR).   D) Buyer’s receipt of Seller’s training, As-Built drawings, Spare parts, Warranty, Operation and Maintenance Manuals (Inspection and Maintenance).   E) BIM/GIS and Asset Management Data.   Contractually, Acceptance equates to Construction Completion, which its tied directly to commercial provisions, Final Payment and Warranty, and is a milestone for the Project Control schedule.  

Maintenance:   This is a post-contract closeout activity and it refers to Buyer’s readiness to conduct periodic inspections and maintain the Seller’s accepted work.  The Buyer’s readiness includes A) Allocating operating budget and assign management responsibility.  B) Purchase and inventory of special tools, consumable items and spare parts.  C) Assign new or reallocate operation/maintenance staff and resources.  D) Update company asset inventory and insurance. 

What are CAMP requirements?

The requirements for the items cited in the definitions above are typically embedded in the contract document.    Typical contract sections or project plans for CAMP technical requirements or inputs in rail transit are:

  • FAT/SAT:   This is found in the Division 2-16 Technical Specifications of the contract/purchase order.    It is most applicable to major systems and equipment, including signal systems, HVAC, substations, signal power motor generators, communications and supervisory control systems and control centers.   The Seller is required to submit detailed test procedures, and the test results for review and approval by the Buyer. 
  • Inspections:   This is implemented under the General Provisions and detailed in Technical Specifications of the contract/purchase order.   It is most applicable to work covered by government permitting and code compliance, and it is described in the Buyer’s construction  manager’s  (CM) monitoring plan and in the CM’s inspection and testing plan  for overseeing the Seller’s work.
  • Start-Up/Burn-In:   This is found in the Division 2-16 Technical Specifications of the contract/purchase order.   It is most applicable to power systems such as substations and signal power motor generators.   The Burn-in periods can range from 30 – 90 days after initial start-up under full load.   For replacement projects, the completion of the Burn-In for the new infrastructure is a predecessor activity in the Seller’s Detailed Contract Schedule for demolition of the old systems.  
  • Final Inspection:    This is found in the General Provisions of the contract/purchase order, usually under the Payment and Time/Contract Schedule Milestones.   Final inspection is typically an end-of-contract item.  However, Buyer and Seller may agree to incremental inspection, use and occupancy of portions of the work.   The Seller’s detailed contract schedule and the Inspection and Test  Plan will delineate the proposed sequence for completing portions of the work.  
  • Punchlist:   This requirement follows Final Inspection and it is a predecessor for achieving Time/Contract Schedule Milestone for Substantial Completion (SC) in the General Provisions of the contract/purchase order.   SC means the work is useful to the Buyer ahead of the completion of work and milestones such as Construction Completion and Contract Completion.
  • Resolution of Submittals and Non-Conformance Reports (NCRs):   This is part of the Buyer’s contract monitoring plan and the project quality plan.  These Plans assure that delivered and installed products reflect the current contract including all negotiated changes and contract modifications, and the completion of corrective actions on NCRs under the Seller’s Quality Management Plan.
Posted on: February 23, 2020 02:53 PM | Permalink | Comments (2)

Value of Knowledge Management and Contract Deliverables

linkedin twitter facebook Request to reuse this  

Recently I was asked to estimate the cost of the various deliverables that are contractually required from Sellers to Buyers.   The estimate included the Seller’s material cost, software cost, labor and administrative effort to prepare, publish and deliver multiple copies of knowledge deliverables, labor for knowledge transfer services, and administrative costs for post contract liabilities.   The knowledge deliverables consisted of As-Built drawings and Operation and Maintenance Manuals.   The knowledge transfer services consisted of training and organized handover of project records.   The post-contract liabilities consisted of Warranty services. 

From previous contract experience in the rail transit domain, the contract deliverables are usually covered in the Buyer/Seller agreement and the value is covered by the retainage withheld by the Buyer from the Seller’s approved progress payments.   The retainage is typically 5% and it’s released from the Buyer to the Seller at the completion of Final Payment, which is dependent on the Seller meeting the contract requirements.  

What the preliminary estimate showed was the cost to produce the end-of-contract deliverables expected by the Buyer from the Seller was within the 5% retainage amount.   As a result, the historical use of 5% retainage in contract payment transactions provided high confidence that the Seller would fulfill the requirements or in theory, risk the Buyer using the retainage to fund another professional service contract for completing the deliverables.   

After further review, the estimate did not though, account for the value of the knowledge and services to the Buyer’s operation.  Most of the end-of-contract deliverables will outlast the initial Buyer’s use and continue to provide knowledge for the operation and maintenance of the contract product.    For contract producing sophisticated systems or cutting edge technology and services, the value to the operations may be far more that the 5% retainage.   

Long after the Seller’s contract is closed out, the knowledge created will help the Buyer in training new employees on operating the system, conducting preventive, predictive and routine maintenance and in coordinating as-built conditions for future projects.  As a result, the Buyer will need to secure the knowledge for safe storage and quick retrieval and provide all resources needed for an operational asset. 

In order to assure the continued value of the end-of-contract deliverables, the Buyer will need to protect these legacy documents and establish knowledge management processes and resources.   Deliverables such as As-Built drawings, O&M Manuals and training lesson plans and materials will continue to provide the Buyer with critical knowledge to share with employees for years to come while the product continues through its use-life cycle.

What was once a paper exchange is now being replaced by paperless alternatives that are environmentally conscientious and take up less space and cost less.  Digital libraries on off-properties are replacing storage and retrieval of paper documents.  However, this transition is not yet complete and many companies still require a combination of paper and digital copies of project and contract documents.  

Like the intangible value of a Warranty, the value of the knowledge from the end-of-contract is hard to quantify.   And its true value will only be appreciated when needed and usually at an inconvenient time.    But the qualitative value to a typical railroad organization includes:

  • Engineering design for as-built conditions of the parent project that are essential to support future child projects
  • Engineering construction for instructions on preventive and routine maintenance and life cycle overhauls on the project products
  • Engineering construction for Warranty plans for monitoring and executing repairs on project products
  • Engineering design and construction for troubleshooting PLC and microprocessor  operating and application hardware and software
  • Procurement for ordering information of consumable and maintenance materials for the project products
  • Stores for storing and maintaining inventory of spare parts to support maintenance and repair of project products
  • Asset management for comprehensive data and information on constructed products from the project to support maintenance and future modifications
  • Human Resources for  lesson plans and documentation for training personnel on operation and maintenance of the project products

  

TIP:   Most projects funded by the US government are required to retain project records for a defined period, and thereafter can determine the disposition of the records, including disposal.   Buyer’s should have a plan for selecting the records and the medium for longer term storage and retrieval of project knowledge.

TIP:   Buyer’s should review contract requirements to assess if the paper focused deliverables are more cost effective than a digital approach for the scope of the project.  For smaller, lower budget projects, paper may still be the best medium for contract deliverables.  For larger, high budget projects, digital software and licenses may be a more effective solution, which can be accessed and searched by the Buyer from any computer location 24 X 7. 

Feedback to Comments 

A.  On estimated cost:  The evaluation of estimated cost for deliverables was favorable because it was a Design-Build contract, where the value of the design allowed for a buffer.     The estimate relative to a fixed bid/lump sum may require the Buyer consider a large retainage percentage to cover expectations on a contract with systems.  The estimated value does not include the spare parts, which would be itemized separately in the bid price of the contract. 

B.  The closest rail transit projects consider knowledge management is as-built deliverables and O&M Manuals. Historically, rail transit projects deal with paper and hammers. As system projects increase the volume of paper, Buyer’s in the rail transit domain will need to consider management and sharing knowledge via electronic/digital medium. 

C.  On IT initiatives for KM:  Historically commuter railroads with budgets that are funded by the government, which off-set actual operating expenses to fare revenue ratio, tend to lag with leading edge IT practices in other industries. However, as the volume of paper increases with the size and complexity of mega projects, it will be inevitable for railroads to consider paperless approaches. While limiting paper, the are still projects that will require paper copies and software hard drives on-site for immediate use in recovery and restoring operations. 

Posted on: February 05, 2020 05:32 PM | Permalink | Comments (10)