What is a Punchlist?
| A punchlist is most common in the construction industry. But it may be an overused term on prime contracts between Buyers and Sellers - when a simple To-Do-List might be more appropriate description for a tool construction managers (CM) use to monitor contractor progress toward achieving contract milestones. Punchlist is not normally part of the definitions in the construction contract Form. As a result, Punchlist means different things to Sellers and Buyers. Definition From various sources of expertise, punchlist is described as:
Punchlist is interdependent with the progress of work by the Seller and the milestones specified by the Buyer in the Contract. The milestones are typically contained in the General Conditions/Provisions (GCs) of a contract document. Punchlist creation is associated with substantial completion and punchlist completion is associated with construction completion. Work Flow Punchlist work flow:
Most US standard contract Forms, cite the requirements for substantial completion and construction completion in the General Conditions/Provisions regarding section related to Performance Schedule and Payments. Punchlist Content The content of a punchlist should contain only minor touch-ups and repairs to installed/constructed work that is described by specific in-scope observations and the locations to be corrected for completion. A punchlist that contains base scope items not yet installed or tested and operational is not acceptable and not suitable for meeting the completion milestone. Items observed that are not in-scope will be deleted from the punchlist and be addressed by the Buyer through other project processes for changes to work. In addition to contract milestones and payments, an acceptable punchlist that the Buyer determines meets the substantial completion requirements is often tied to incentives and liquidated damages. Meeting substantial completion is also related to other contract requirements. Punchlist Interfaces Interfaces with other contract requirements in the work flow include: Item 4-After substantial completion, Seller and Buyer can initiate reconciliation of incentives and liquidated damages. Buyer can suspend consideration of all potential changes, instruct Seller to demobilize and to perform site restoration by the final completion/contract completion milestone, request Seller to submit deliverables such as O&M Manuals, As-Built Drawings Package and Warranties, and if applicable, release performance bonds. Item 5-After construction completion, Seller and Buyer can initiate the contract closeout. Item 7-After demobilization, Seller can reduce insurance coverage. TIP: A punchlist should only be submitted once by Seller and reviewed by Buyer for completeness an accuracy. Thereafter, it is locked down. No items can be addressed. Items can only be verified as completed and closed. TIP: All items on the punchlist should be addressed and closed by the Sellers within a period that avoids the risk of further damage or new conditions that requires corrective action. TIP: For Buyer’s, including their construction managers, that require in-progress punchlists to assess the contractor’s physical work relative to the construction substantial completion milestone, a more granular definition of punchlist may be needed. Here are some proposed definitions that can provide guidance to Buyer and Seller as the punchlist changes with the progress of construction.
TIP: An observation listed on the punchlist should identify the inspecting agency/inspector name and date, cite the specific location (s) and the drawing/specification/code, and describe the needed correction to meet with the contract requirements, approved shop drawings or other industry standards for the type of work. TIP: The punchlist observations should be actionable and the description begin with words such as repair, replace, adjust, touch-up, polish, remove, rebalance and clean. Items with words such as install, test, paint, fill, energize, backfill and connect may indicate that base scope is not yet completed. |
Know the Contract - Part 14, Contract Completion/Closeout
| This is the 14th in a series of discussions that is intended to prompt Project Teams to be aware of the entire contract document, including Information For Bidders (IFB), General Provisions/General Conditions/Terms and Conditions (GCs) and the Technical Requirements [Specifications and Drawings.] Part 14 of Know the Contract is Contract Completion/Closeout. Closeout is the successor to all other work performed under the Contract and it is final set of activities between the Buyer and Seller. While the requirements for Closeout may be scattered throughout the Contract document, the most important are described in the GC’s sections related to Schedule and Payments. At this phase of the Contract, the Buyer’s Contracting Officer is the primary arbiter for determining that all requirements are met by the Seller and confirmed by the Buyer’s Project Manager. Part 6-Schedule Performance and Part 7-Progress & Milestone Payments of this series describe the content in the typical contract Form. Satisfying these requirements precede completing the Closeout process and documentation, and includes substantiating completion of testing and start-up; training; delivering spare parts; submitting operation & maintenance manuals, software, as-built drawings, asset management data and warranty; and closure of all quality management processes and deliverables. Regardless of the contracting method, such as Design-Bid-Build, Design Build and CM At Risk, the Closeout of the contract is governed by the GCs as well as any Special Conditions and terms negotiated for contract award. The typical activities and topics include:
During the Closeout phase, the Buyer may develop Lessons Learned from the Seller’s performance on the Contract. The Lessons Learned will be utilized by the Buyer to consider changes in requirements as well as management processes and documentation on future Contracts. Some of the topics from Lessons Learned may include:
TIP: The responsible parties for Closeout are the Buyer’s Project Manager with support from the Buyer’s Contracting Officer and the Seller’s Project Manager with support from the Seller’s prime contracting/procurement official. TIP: While risking duplication of requirements, create a separate Division 1 specification covering the requirements and deliverables checklist for contract closeout. TIP: Most US contract Forms were written based on paper transactions throughout the Contract cycle. Due to awareness of threats outside normal contract and project processes, security of products, deliverables and documentation is now part of controlling access to sensitive contract records. As a result, EDMS has replaced paper documents and is used more effectively to segregate, store and restrict distribution of documents that contain sensitive information. TIP: The use of electronic document control system (EDMS) has become a critical part of managing and executing the work at a project and contract level. As a result, there may be a need to create requirements for content, format, compatibility and the transfer method of the Seller’s EDMS with the Buyer’s hardware, software and the organizational management of records. TIP: Ensure Closeout requirements and terminology are well defined and are consistent with the process and requirements in the GCs. Clarity of terms is essential for both the Buyer and Seller. TIP: Buyer’s Contracting Officer should provide clear guidance to the Buyer’s Project Manager on the process, timeline and documentation required to satisfy the contract closeout. |
CAMP Questions and Answers - Part 2
| This article complements the previous articles “What are good practices for Commissioning Acceptance and Maintenance Plan (CAMP)?” and Questions and Answers to CAMP – Part 1. Here are Questions and Answers to CAMP – Part 2. What are the CAMP deliverables? Typical contract sections or project plans for CAMP deliverables are:
Who is responsible for CAMP? CAMP is a cross-functional process and it is correlated with various activities and the creation of various project records. As established by the project in the Schedule Work Breakdown Structure, the CAMP process monitors work across several managerial silos. In some Electronic Document Management Systems, the managerial silos or project phases include: Design: The development and refinement of project product requirements, and the creation of contract documents and performance metrics for the product meeting the Buyer’s criteria and business case results. Construction: The physical fabrication/manufacture of systems, brick & mortar assembly of a structure for the systems, and the integrated start-up and testing the entire product for Buyers acceptance. Quality: The control and assurance on the product, processes and documentation meet the Buyer’s requirements for the project product, including design and construction submittals and deliverables and the content for CAMP. Commercial: The management of project finances, contract payments and closeout, contract changes and of contractor performance to schedule milestones, which includes monitoring incentives for beating milestones and liquidated damages for missing milestones. What typical CAMP activities should be in the Detailed Contract Schedule? A sample of the critical cross functional activities with responsibilities by Buyer/Seller are:
|
CAMP Questions and Answers - Part 1
| This article complements the previous article “What are good practices for Commissioning Acceptance and Maintenance Plan (CAMP)?” Tailored to rail transit projects, this article follows with Q&A on CAMP definitions, description of CAMP deliverables, integrated managerial functions supporting CAMP, and the general activities and sequence for CAMP. Here are Questions and Answers to CAMP – Part 1. When Does the CAMP Process Start? CAMP starts with the design of the project and the creation of construction documents, and it continues through the closeout of the contract/project. The process will consist of iterative development of a content a Matrix that lists the components that will form the constructed product as described in the project scope and objective. The Matrix also lists the expected CAMP deliverables, such as Operation and Maintenance Manuals, Warranty, Training, As-Built Drawings, Spare Parts, Software, and GIS/Asset Management data. Starting the work in the design will assure that at the time of the construction contract award, the Seller and Buyer have the same expectations for the CAMP deliverables. What are the definitions for CAMP? Commissioning: This is the pre-requisite activities and deliverables for starting the CAMP package and deliverables for Acceptance, and it is the Buyer’s (Owner) process for verification of project/contract scope and the Seller’s (Contractor) compliance with requirements. The activities typically include Factory Acceptance Testing (FAT), On-Site Acceptance Testing (SAT), In-progress Inspections, Start-Up and Burn-In. Commissioning activities should be integrated into Project Control schedules and Quality Plans, which contain quality control test and inspection plans. Acceptance: This is a predecessor activity for contract closeout, and it refers to the Final Acceptance by the Buyer/Owner, which follows completion of Commissioning activities and A) Final formal inspection of the Seller’s work. B) Seller’s completion of punchlist work. C) Buyer’s confirming resolution of Submittals and Non-Conformance Reports (NCR). D) Buyer’s receipt of Seller’s training, As-Built drawings, Spare parts, Warranty, Operation and Maintenance Manuals (Inspection and Maintenance). E) BIM/GIS and Asset Management Data. Contractually, Acceptance equates to Construction Completion, which its tied directly to commercial provisions, Final Payment and Warranty, and is a milestone for the Project Control schedule. Maintenance: This is a post-contract closeout activity and it refers to Buyer’s readiness to conduct periodic inspections and maintain the Seller’s accepted work. The Buyer’s readiness includes A) Allocating operating budget and assign management responsibility. B) Purchase and inventory of special tools, consumable items and spare parts. C) Assign new or reallocate operation/maintenance staff and resources. D) Update company asset inventory and insurance. What are CAMP requirements? The requirements for the items cited in the definitions above are typically embedded in the contract document. Typical contract sections or project plans for CAMP technical requirements or inputs in rail transit are:
|
Good practices for Commissioning Acceptance and Maintenance Plans (CAMP)?
| Until recently, Commissioning, Acceptance and Maintenance Plan (CAMP) deliverables on major projects were delegated to the contractor for determining format, content, level of detail and the submittal date. Typically, the compilation of the associated deliverables was part of final acceptance of contract products by the Buyer and achieving the performance milestone by Seller for contract completion. At contract completion, the withheld retainage by the Buyer, which can be 5% deducted from all Seller’s progress payments through 100% earned contract value, becomes part of the contract closeout. As a result, contractors typically leave the CAMP deliverables until the end of the contract. Contract closeout means the Buyer’s Project Manager (PM) can close the remaining administrative office, package the files for storage, and be reassigned to other projects on a full-time basis. For the Seller’s PM, it means all financial reimbursement obligations are complete and they can close files and financial bookings, and reassign any remaining staff to other contracts. However, there are numerous Lessons on contracts from closeout experiences that reflect poor quality and incomplete CAMP deliverables. The situation is compounded by the urgency of the Buyer’s PM to closeout the contract and of the Seller’s PM to collect all retainage due from the already approved payments. At this time on the contract lifecycle, CAMP deliverables can easily become secondary, as both PM’s are usually focused on closeout and moving on to new projects or contracts. In order to mitigate the risk of poor quality and incomplete CAMP deliverables on rail transit projects, a major United States (USA) commuter railroad updated its requirements for consultant design contracts and contractor construction contracts. The scope of work for design contracts specify that a CAMP Matrix be developed and submitted with each level of deliverables. The Division 1 Specifications for the construction contracts specify the CAMP as a deliverable with scope, product and execution requirements that include the CAMP Matrix – developed by the design consultant. The CAMP Matrix includes the major systems constructed, and for deliverables, such as Training, Operation and Maintenance Manuals, Spare Parts, Software, Software Licenses, Warranty, and As-built drawings, which are itemized in the Divisions 2-16 Specifications of the construction contract. Some Mega projects also include deliverables for BIM/GIS, Asset Management and service contract agreements. As the Matrix progresses from the design contract and into the construction contract, more detailed descriptions of the components /systems of the constructed product are incorporated. This creates better understanding of the CAMP deliverables. Since implementing in the late 2000’s, the USA commuter railroad has collected Lessons Learned on CAMP requirements, which are used during the development of new projects and contracts. Enhancing the contracts was proven to enable Buyer’s PMs to better manage the Seller’s PMs and realize higher quality and comprehensive CAMP deliverables that met the real expectations of the Owner’s operating departments. The CAMP Matrix makes it clearer to both PM’s on the scope of deliverables and it provides the foundation for expanding the use into alternate delivery contracts such as Design Build (DB). Thanks to designing CAMP into the deliverables, the Seller for DBB contract has well defined requirements and deliverables scope for CAMP. In DB contract, the Seller will develop the CAMP scope during the design phase and compile the source documents from construction contract submittals from the DB prime and all its subcontractors and vendors/suppliers. Due to the size of scope and contract values on mega projects, the planned intermediate use of contract products for operational use ahead of the contract completion/final acceptance milestone is a practical necessity. In the current rail transit environment in USA, the project leadership commitments to funding partners, stakeholders, politicians and influencers create urgency to place products in-service for Ribbon Cutting ceremonies and press conferences. As a result, Owner’s assume responsibility for maintenance well ahead on the scheduled contract or project completion. This requires that the usual end-of-contract CAMP activities become incremental and intermediate, and the project team needs to adjust project management staffing by Buyers and Sellers to expedite CAMP deliverables. Good Practices for CAMP
Topics for Further Consideration at Closeout:
TIP: CAMP deliverables should be tailored to the Owner’s expectations and to SAMPLES of CAMP documents accepted to the Owner on previous contracts. TIP: CAMP deliverables should utilize as many of the documents reviewed during construction contract Submittals, which typically include detailed instructions for start-up, operation and maintenance as well as a list of recommended consumable parts, replacement spare parts, inspections, warranty and trouble shooting information. TIP: Owner/Buyer should compile a set of SAMPLE documents – proven acceptable to Owner POCs, that can be used by Buyer/Seller PMs to create and distribute CAMP deliverables. TIP: Buyer’s CAMP Manager should have access to information across various functional silos of the project management organization and data management system software, including design (CAMP development), construction (CAMP implementation and training records), quality (Product/system tests, inspections and various reports) and commercial (Contract changes, requests for acceptance, payment for spare parts, and requests for release of retainage). TIP: Since final acceptance of products initiates the start of the Seller’s warranty period, Seller’s PM, Buyer PM’s and Owner should create a post contract completion team to monitor the warranty lifecycle, which may occur while construction is on-going and extend after contract completion is achieved. TIP: Since receipt of spare parts is in the CAMP scope, Buyer’s and Seller’s PMs need to establish a formal process and documentation to manage the transfer of spare parts to support the incremental final acceptance of contract products. TIP: Typical projects start with a Kick-Off Meeting, the completion of CAMP including the warranty period one-year after contract final completion, should be finalized by a Closeout Meeting between the Owner, Buyer’s PM and Seller’s PM. As may be required, Owner’s final evaluation of Seller’s performance should record and assessment for CAMP and Warranty. TIP: Mega projects always start with a ground breaking ceremony where top officials from the Owner, Buyer’s PM team, Seller, Funding Partners, politicians and other influencers are smiling and holding shovels. The CAMP deliverables and the completion of warranty – one year after full contract completion should be equally ceremonial, such as a press conference with similes, hand-shakes and words of satisfaction between the Owner, Buyer’s PM and Seller’s PM. As may be required, Owner’s final evaluation of Seller’s performance should record and assessment for CAMP and Warranty. |