CAMP Questions and Answers - Part 2

From the Project Management View from Rail Transit Programs and Projects Blog
by
A collection of articles sharing project processes, design and construction experience, best practices, and lessons learned along with operational knowledge related to executing programs and projects in the rail transit industry.

About this Blog

RSS

Recent Posts

Transitioning Constructed Products from Projects to Owner's Operations

Lessons to be Learned.  What Happens When the Buyer is Not the Owner, Operator and Maintainer of the Company?  

Managing Warranty After Achieving Contract Milestones

What Happens After the Buyer and Seller Agree on a Punchlist?

What is a Punchlist?

Categories

Acceptance, Analytics, ANSI, Asset Management, Best Value, Best Value Contractor Selection, Best Value Selection Criteria, Buyer, Certifications, Commissioning, Communications Management, Construction, Construction Completion, Construction Deliverables, construction manager, Construction Monitoring, Construction Submittals, Consultant, Consultant Contract, Contract Acquisition, Contract Completion, Contract Deliverables, Contract Delivery, Contract Development, Contract Integration, Contract Management, Contract Milestones, Contract Quality, Contract Requirements, Contract Submittals, Contracts, Decision Making, Definitions, Design, Design Bid Build, Design Build, Design Build Delivery, Design Deliverables, Design Services, Design Submittals, Design-Bid-Build, Division 1 Specifications, Document Control, Earned Value Management, Engineering, Estimating, Estimator, Ethics, Factory Acceptance Test, Final Acceptance, Final Completion, General Conditions, General Provisions, General Terms and Conditions, Good Practices, Government, Hard Risks, Hazards, Human Resources, Information For Bidders, Inspection, Inspection and Testing, Inspection Test Plan, Integration, Integration Management, Invitation For Bid, Key Performance Indicators, Knowledge Management, Maintenance, Management Integration, Managerial Time, Managing Change, Managing Changes, Master Project Schedule, Meeting Minutes, Mega Projects, NCR Process, Negotiations, Non Conformance Report, O&M Manuals, Oversight Reports, PM Fundamentals, PMBOK, PMI, PMO, Procurement Management, Professional Obligations, Program Management, program manager, Progress Reports, Project Charter, Project Controls, Project Engineer, Project Engineering, Project Integration, Project Interfacing, Project Management, Project Management Institute, project management office, Project Management Plan, Project Manager, Project Managerr, Project Planning, Project Records, Project Schedules, Project Team, Project Teams, ProjectManagement, Public Relations, punchlist, Quality, Quality, Rail Car Purchase, Rail Transit, Rail Transit Organization, Rail Transit Project, Rail Transit Projects, Railroad, Reliability, Resource Management, RFI Logs, risk, Risk Allocation, risk allocation, Risk Allocations, Risk Management, Risk Management, Safety, Schedule Interfaces, Schedule Management, Schedule Milestones, Scheduler, Scheduling, Scope of Work, Security, Seller, Site Acceptance Test, Soft Risks, Special Inspections, Specifications, Submittal Logs, Submittal Process, Substantial Completion, System Integration, System Integration Test, Systems, Systems Purchase, Testing/Test Management, Threats, Transformation, Transformational Projects, Transportation, Vulnerability, Work Area, Work Areas

Date

linkedin twitter facebook Request to reuse this  


This article complements the previous articles “What are good practices for Commissioning Acceptance and Maintenance Plan (CAMP)?” and Questions and Answers to CAMP – Part 1.  Here are Questions and Answers to CAMP – Part 2.

What are the CAMP deliverables?

Typical contract sections or project plans for CAMP deliverables are:

  • Receipt of Final Testing and Acceptance Sign-Off Documentation:  This consists of a complementary series of project documents, which demonstrate quality and managerial oversight of the work.    Based on the scope, this may include factory acceptance test results, site acceptance test results, inspections at substantial completion, final inspection at completion of punchlist, record of special inspections, and closure of Permits by the issuing agency.   This documentation is produced by construction management consultants and Agencies with permitting jurisdiction.
  • Certificate of Construction Completion: This is certification that all punchlist work is complete; start-up, training and burn-in is complete; and the overall Project Element is constructed as shown on the RFC design packages, shops drawings and material/product submittals.  Unless indicated otherwise, this Certificate is produced by the primary Construction Manager. 
  • Certificate of Construction Compliance/Code Compliance:  This is certification that all work meets the contract technical and quality requirements, the Design Build Quality Program, and all stipulations in construction Permits.   This Certificate is produced the Engineer of Record. 
  • Spare Parts:   This is found in the Division 2-16 Technical Specifications of the contract/purchase order.   The spare parts description and quantities will typically be itemized in the Buyer’s contract award price breakdown and in the Seller’s Detailed Contract Schedule/payment schedule.  
  • Training, O&M Manuals:   This is found in the Division 1 Technical Specifications of the contract/purchase order.    While the Seller’s  system and equipment suppliers typically have standard services and deliverables for off-the-self components, the Buyer’s may have extraordinary requirements to meet the operation standards, procedures and processes of the company. 
  • As-Built drawings  This is found in the Division 1 Technical Specifications of the contract/purchase order.     This item may also be expressed and defined by the Buyer with other labels such as red-lined contract drawings and record drawings.   It is typically an updated version of the conformed contract drawings from the Seller, which includes all contract changes and modifications, and it indicates the actual installed locations of the constructed assets.
  • Warranty:    This is found in the General Provisions, and it may be amplified in Division 2-16 Technical Specifications for large, high value technology systems and equipment.    By Contract, the Warranty starts at Buyer’s use/acceptance of the work, and it follows Final Inspection, and Punchlist activities.    Seller’s obligation  for warranty  is typically one year and as supplemented by manufacturer’s and Original Equipment Suppliers’ warranties, which may extend post-contract closeout for several years as described in the product data/specification reviewed during the Contract Submittal process. 
  • Software and Software Licenses:    The requirements scope for computer supported products with hardware and software are usually found in the Technical Specifications in Division 10-16, including (10) Specialties, (11) Equipment, (13) Special Construction, (14) Conveying Systems, (15) Mechanical/Plumbing, and (16) Electrical.   However, depending on the contract format, requirements may also be separated into new Divisions including (21) Fire Suppression, (23) HVAC, (25) Integrated Automation, (26) Electrical, (27) Communications, and (28) Electronic/Safety/Security.  
  • BIM/GIS Data and Asset Management Data:    This is found in the Division 1 Technical Specifications of the contract/purchase order.   While the data can be generated using the contract drawings, it is more accurate to complete after the As-Built drawings are submitted and accepted.  

Who is responsible for CAMP?

CAMP is a cross-functional process and it is correlated with various activities and the creation of various project records.  As established by the project in the Schedule Work Breakdown Structure, the CAMP process monitors work across several managerial silos.   In some Electronic Document Management Systems, the managerial silos or project phases include:

Design:   The development and refinement of project product requirements, and the creation of contract documents and performance metrics for the product meeting the Buyer’s criteria and business case results.

Construction:   The physical fabrication/manufacture of systems, brick & mortar assembly of a structure for the systems, and the integrated start-up and testing the entire product for Buyers acceptance.  

Quality:   The control and assurance on the product, processes and documentation meet the Buyer’s requirements for the project product, including design and construction submittals and deliverables and the content for CAMP.  

Commercial:   The management of project finances, contract payments and closeout, contract changes and of contractor performance to schedule milestones, which includes monitoring incentives for beating milestones and liquidated damages for missing milestones. 

What typical CAMP activities should be in the Detailed Contract Schedule?

A sample of the critical cross functional activities with responsibilities by Buyer/Seller are:

  1. Seller initiates CAMP package and compiles project records
  2. Seller and Buyer confirm readiness for substantial completion/operational use
  3. Seller/Buyer conduct and document QC/QA inspection and testing, including Site  Acceptance Test (Predecessor = B)
  4. Seller/Buyer conduct and document substantial completion inspection and punchlist (Predecessor = C)
  5. Seller requests progress payment for 100% earned value and Buyer issues progress payment (Predecessor = D)
  6. Seller submits CAMP package and notifies Buyer on readiness for final inspection (Predecessor = A, E)
  7. Seller/Buyer conduct and document final inspection and completion of punchlist/work and burn-in (Predecessor = F)
  8. Seller submits contract closeout documents and requests release of retainage withheld from previously approved progress payments (Predecessor = G)
  9. Buyer confirms acceptance of CAMP package, including and all products and deliverables by contract requirements, and releases retainage to Seller  (Predecessor = F, G, H)

Posted on: March 16, 2020 05:22 PM | Permalink

Comments (0)

Please login or join to subscribe to this item


Please Login/Register to leave a comment.

ADVERTISEMENTS

"From the moment I picked your book up until I laid it down I was convulsed with laughter. Some day I intend to read it."

- Groucho Marx

ADVERTISEMENT

Sponsors