Good Practices for Design Document Development Process

From the Project Management View from Rail Transit Programs and Projects Blog
by
A collection of articles sharing project processes, design and construction experience, best practices, and lessons learned along with operational knowledge related to executing programs and projects in the rail transit industry.

About this Blog

RSS

Recent Posts

Transitioning Constructed Products from Projects to Owner's Operations

Lessons to be Learned.  What Happens When the Buyer is Not the Owner, Operator and Maintainer of the Company?  

Managing Warranty After Achieving Contract Milestones

What Happens After the Buyer and Seller Agree on a Punchlist?

What is a Punchlist?

Categories

Acceptance, Analytics, ANSI, Asset Management, Best Value, Best Value Contractor Selection, Best Value Selection Criteria, Buyer, Certifications, Commissioning, Communications Management, Construction, Construction Completion, Construction Deliverables, construction manager, Construction Monitoring, Construction Submittals, Consultant, Consultant Contract, Contract Acquisition, Contract Completion, Contract Deliverables, Contract Delivery, Contract Development, Contract Integration, Contract Management, Contract Milestones, Contract Quality, Contract Requirements, Contract Submittals, Contracts, Decision Making, Definitions, Design, Design Bid Build, Design Build, Design Build Delivery, Design Deliverables, Design Services, Design Submittals, Design-Bid-Build, Division 1 Specifications, Document Control, Earned Value Management, Engineering, Estimating, Estimator, Ethics, Factory Acceptance Test, Final Acceptance, Final Completion, General Conditions, General Provisions, General Terms and Conditions, Good Practices, Government, Hard Risks, Hazards, Human Resources, Information For Bidders, Inspection, Inspection and Testing, Inspection Test Plan, Integration, Integration Management, Invitation For Bid, Key Performance Indicators, Knowledge Management, Maintenance, Management Integration, Managerial Time, Managing Change, Managing Changes, Master Project Schedule, Meeting Minutes, Mega Projects, NCR Process, Negotiations, Non Conformance Report, O&M Manuals, Oversight Reports, PM Fundamentals, PMBOK, PMI, PMO, Procurement Management, Professional Obligations, Program Management, program manager, Progress Reports, Project Charter, Project Controls, Project Engineer, Project Engineering, Project Integration, Project Interfacing, Project Management, Project Management Institute, project management office, Project Management Plan, Project Manager, Project Managerr, Project Planning, Project Records, Project Schedules, Project Team, Project Teams, ProjectManagement, Public Relations, punchlist, Quality, Quality, Rail Car Purchase, Rail Transit, Rail Transit Organization, Rail Transit Project, Rail Transit Projects, Railroad, Reliability, Resource Management, RFI Logs, risk, Risk Allocation, risk allocation, Risk Allocations, Risk Management, Risk Management, Safety, Schedule Interfaces, Schedule Management, Schedule Milestones, Scheduler, Scheduling, Scope of Work, Security, Seller, Site Acceptance Test, Soft Risks, Special Inspections, Specifications, Submittal Logs, Submittal Process, Substantial Completion, System Integration, System Integration Test, Systems, Systems Purchase, Testing/Test Management, Threats, Transformation, Transformational Projects, Transportation, Vulnerability, Work Area, Work Areas

Date

linkedin twitter facebook Request to reuse this  

Categories: Construction, PMO


Based on my experience in project management on rail transit projects, critical skills and activities by project managers are communications with the team, stakeholders, contractors, consultants, technical contributors, projects sponsors and funding partners. On rail transit there is added consideration to the system users/pre-paid customers, system operating personnel, agency oversight, public officials, and communities that are served and impacted by the system.

The effective review of design documents can impact the quality of construction contracts, including specifications and drawings. Coupled with a presentation and review meetings, the input from diverse reviewers can be vetted and focused on the scheduled completion of design deliverables that meet the project plan, project purpose and objective, and the expectations of various project participants and stakeholders.

Unless an Owner has designated staff, the development of technical requirements for construction contracts is usually performed by a design consultant. The Owner identifies the consultant’s scope, deliverables and performance schedule, and establishes the process for Owner representatives to participate with the consultant in developing and reviewing the design deliverables. In order to manage the work, the Owner typically assigns a Project Manager (PM) to monitor the consultant and to ensure project participants complete activities to support a defined project plan, schedule and budget.

Design deliverables typically consist of iterative packages, such as 30%, 60%, 90% and 100% design, that are reviewed and revised before becoming the technical requirements in a construction contract. The content, format and level of detail in the deliverables are defined in the design scope, which is supplemented by the Owner’s design input such as design criteria, standard terms and conditions, model Division I specifications, industry standard specification formats and contract forms, operating standards and rules, and government code and regulations.

During the design process, the consultants will submit the deliverables to the Owner, and the PM will promptly distribute deliverables to a pre-established list of reviewers along with initial assessment/comments. As needed, the PM will provide guidance to the participants in reviewing and returning comments on the deliverables regarding technical compliance, quality and completeness of content, and consistency of format and requirements for integration with other contract components.

In order to facilitate and maintain progress on the design schedule, the PM will compile comments and conduct meeting s to assure the consultant addresses the Owner’s comments in subsequent deliverables through acceptance of the final contract-ready deliverable.

Good Practices for Design Comments
• Use a pre-defined matrix for recording comments and documenting their disposition – with fields for item numbers, reviewer, comment, specification section/page, drawing number.
• Submit comments that are presented in context for action – prefaced by change, delete, replace, verify, confirm
• Complete and provide the comments by the designated due date
• Resolve duplicate or conflicting comments before submitting the comment matrix
• Avoid comments on typos, punctuation and format that can be addressed through word processing or CAD software and administrative processes
• Avoid open-end questions that can be answered through review of design scope or design criteria
• Avoid multiple line item comments for global comments/changes – change “vendor” to “contractor”

TIP: Comments should be measured for appropriateness with the design Scope of Work (SOW) in the contract issued to the consultant for the design work. Comments outside the SOW should be presented to the Owner for disposition, and as needed, the Owner will formally modified the contract, SOW and design criteria.

Good Practices for Design Review Meetings
• Schedule meetings for a date that allows time for attendees to prepare initial comments
• Identify meeting objectives, specify input needed or decisions that are required
• Outline the expected change in content for the next iteration of deliverable
• Clarify design questions and refine the feedback into actionable comments
• Record the meetings, establish action items, and identify comments in the matrix
• Review Lessons Learned on similar contract types with comparable scope

TIP: If the meeting Agenda includes finalizing comments on specific documents or making design decisions, the meeting Announcement should conspicuously indicate the expectation and the appropriate documents distributed with the Announcement.
      


Posted on: December 31, 2017 03:56 PM | Permalink

Comments (6)

Please login or join to subscribe to this item
avatar
Henry Hattenrath Project Consultant| Tectonic Engineering MSA LLC New York, Ny, United States
The content was originally published in October 2016 under DISCUSSIONS. With encouragement from my PM.com peers, it is now part of a BLOG.

avatar
Vincent Guerard Coach - Trainer - Speaker - Advisor| Freelance Mont-Royal, Quebec, Canada
Henry, good that you previous discussion post are in a blog

avatar
Najam Mumtaz Retired Lahore, Punjab, Pakistan
Thank you Henry for sharing your experience of projects in rail transit industry and best practices of design comments and review meetings.

avatar
Anish Abraham Privacy Program Manager| University of Washington Auburn, Wa, United States
Thanks for posting this, very informative.

avatar
Eduin Fernando Valdes Alvarado Project Manager| F y F Fabricamos Futuro Villavicencio, Meta, Colombia
Thanks

avatar
Jose Luis Gonzalez Rugel Presidente Grupo Gonzalez - Program Manager - Docente- Consultor - ATP Trainner| Dipromacom Guayaquil, Guayas, Ecuador
Always in important to do the documentation of the meeting. Thanks for the information

Please Login/Register to leave a comment.