Good Practices for Project/Progress Meetings

From the Project Management View from Rail Transit Programs and Projects Blog
by
A collection of articles sharing project processes, design and construction experience, best practices, and lessons learned along with operational knowledge related to executing programs and projects in the rail transit industry.

About this Blog

RSS

Recent Posts

Transitioning Constructed Products from Projects to Owner's Operations

Lessons to be Learned.  What Happens When the Buyer is Not the Owner, Operator and Maintainer of the Company?  

Managing Warranty After Achieving Contract Milestones

What Happens After the Buyer and Seller Agree on a Punchlist?

What is a Punchlist?

Categories

Acceptance, Analytics, ANSI, Asset Management, Best Value, Best Value Contractor Selection, Best Value Selection Criteria, Buyer, Certifications, Commissioning, Communications Management, Construction, Construction Completion, Construction Deliverables, construction manager, Construction Monitoring, Construction Submittals, Consultant, Consultant Contract, Contract Acquisition, Contract Completion, Contract Deliverables, Contract Delivery, Contract Development, Contract Integration, Contract Management, Contract Milestones, Contract Quality, Contract Requirements, Contract Submittals, Contracts, Decision Making, Definitions, Design, Design Bid Build, Design Build, Design Build Delivery, Design Deliverables, Design Services, Design Submittals, Design-Bid-Build, Division 1 Specifications, Document Control, Earned Value Management, Engineering, Estimating, Estimator, Ethics, Factory Acceptance Test, Final Acceptance, Final Completion, General Conditions, General Provisions, General Terms and Conditions, Good Practices, Government, Hard Risks, Hazards, Human Resources, Information For Bidders, Inspection, Inspection and Testing, Inspection Test Plan, Integration, Integration Management, Invitation For Bid, Key Performance Indicators, Knowledge Management, Maintenance, Management Integration, Managerial Time, Managing Change, Managing Changes, Master Project Schedule, Meeting Minutes, Mega Projects, NCR Process, Negotiations, Non Conformance Report, O&M Manuals, Oversight Reports, PM Fundamentals, PMBOK, PMI, PMO, Procurement Management, Professional Obligations, Program Management, program manager, Progress Reports, Project Charter, Project Controls, Project Engineer, Project Engineering, Project Integration, Project Interfacing, Project Management, Project Management Institute, project management office, Project Management Plan, Project Manager, Project Managerr, Project Planning, Project Records, Project Schedules, Project Team, Project Teams, ProjectManagement, Public Relations, punchlist, Quality, Quality, Rail Car Purchase, Rail Transit, Rail Transit Organization, Rail Transit Project, Rail Transit Projects, Railroad, Reliability, Resource Management, RFI Logs, risk, Risk Allocation, risk allocation, Risk Allocations, Risk Management, Risk Management, Safety, Schedule Interfaces, Schedule Management, Schedule Milestones, Scheduler, Scheduling, Scope of Work, Security, Seller, Site Acceptance Test, Soft Risks, Special Inspections, Specifications, Submittal Logs, Submittal Process, Substantial Completion, System Integration, System Integration Test, Systems, Systems Purchase, Testing/Test Management, Threats, Transformation, Transformational Projects, Transportation, Vulnerability, Work Area, Work Areas

Date

linkedin twitter facebook Request to reuse this  

Categories: Construction, Quality


The most critical skills and activities by project managers is communications with the team, stakeholders, contractors, consultants, technical contributors, projects sponsors and funding partners.

In order to maintain project progress, many direct and indirect activities need to be performed and completed effectively and efficiently. Just as important as direct activities on construction projects such as excavation, concrete installation, steel erection, and systems installation, management meetings need to be held and attended in parallel with the more tangible activities.

Most capital projects contain interdependent phases for design and construction. As work progresses there are many types of recurring meetings that will be conducted such as oversight meetings with Owner/funding partners, project schedule meetings, contractor progress meetings, and design phase meetings with consultants, construction phase meetings with contractors.

Meetings are an essential part of management and supervision roles and responsibilities such as monitoring activities, reporting progress, assessing performance, and measuring quality of work. At the meetings, Agenda topics will be discussed, action items will be closed and new actions items will be assigned to project team members. As needed, the Project Manager will escalate and expedite resolution of issues or to obtain management decisions on topics outside the project team authority.

Effective and efficient meetings allow management personnel to spend more time on action items and on direct activities to assure continued progress. Conversely, an imbalance in the frequency of meetings and the time to complete assigned actions will make management less effective on direct and indirect activities. Project managers and the PMO need to find a balanced of process that avoid non-value added activities that detracts staff and takes manhours away from managing the essential deliverables.

Equally important, is properly documenting the discussions at the meetings and indicating the actions required for maintaining progress on direct and indirect activities. Meeting minutes should be concise, identify action items, due dates and assigned party. Critical decisions and approaches for work execution should be agreed upon and recorded for traceability along with appropriate documents that are part of the meeting handouts.

Good Practices for Project/Progress Meetings
• Schedule meetings in advance with a written purpose and Agenda
• Establish meeting times, dates and locations that are recurring on a calendar and that are aligned with PMO reporting periods and oversight meetings
• Provide copies of Agenda and handouts at the meeting and assure invited participants are consistent with the Project Management Plan
• Allow Subject Matter Experts to present deliverables, such as updated project schedules, financial reports, quality documentation, contract administration, and risk management
• Routinely engage participants in discussions and disposition of topics and action items
• Present progress based on specific data dates and consistent with other project reports and metrics
• Introduce new personnel or first time attendees prior to the start of the meeting
• Promptly generate and distribute Meeting Minutes so that action can be undertaken to report progress at the next meeting.

TIP: If the meeting Agenda includes obtaining comments on review of specific documents or making project decisions, the meeting Announcement should conspicuously indicate the expectation and the appropriate documents should be distributed with the Announcement.

Good Practices for Meeting Minutes
• Establish a consistent format for content, numbering and labeling
• Paraphrase discussions and assure actions are specific with due dates and assigned party
• Content should accurately reflect the meetings discussions
• Distribute Meeting Minutes and Handouts to all attendees and all non-attending invited team members
• Transmittal should highlight a summary of participants and assigned action items
• Record any progress made on action items since the meeting and up to issuance of the Minutes
• Rather than names use participant titles, departments or company names for contractors and consultants

TIP: Before distributing Meeting Minutes, check to see if there is any progress on action items since the meeting. As needed, update and distribute the Minutes with a note indicating the content reflects progress since the meeting.
      


Posted on: December 31, 2017 04:40 PM | Permalink

Comments (11)

Please login or join to subscribe to this item
avatar
Henry Hattenrath Project Consultant| Tectonic Engineering MSA LLC New York, Ny, United States
The content was originally published in November 2016 under DISCUSSIONS. With encouragement from my PM.com peers, it is now part of a BLOG. Check out the feedback on leadership skills and distribution of documents for review in advance of the meetings.

avatar
Vincent Guerard Coach - Trainer - Speaker - Advisor| Freelance Mont-Royal, Quebec, Canada
Glad You have it on a blog

avatar
Najam Mumtaz Retired Lahore, Punjab, Pakistan
Thank you Henry for sharing good practices of holding effective project meetings and it's follow up in the form of minutes of meetings.

avatar
Drake Settsu Project Manager / Blogger Hi, United States
Good tips.

avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
Some good advice here. Thanks Henry.

avatar
Br. Ts. PUI CHEE KHIAN PMP®, PMI-RMP®, PMI-SP, CCPM (CIDB), MBA, MPM® CPE, FAAPM, FCILG, MPMI, | CPE, FAAPM, FCILG, MPMI, MMSSA, MMIM, AMIVMM, CM(ACPM) Kuching, Sarawak, Malaysia
Standard construction practice that peers in construction industry may follow. Good sharing. Thanks.

avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Good Points Henry.

avatar
Eduin Fernando Valdes Alvarado Project Manager| F y F Fabricamos Futuro Villavicencio, Meta, Colombia
Thanks for sharing

avatar
Md. Masudur Rahman Project Manager| Pride Group Dhaka, Bangladesh
Good advice for me.

avatar
Md. Masudur Rahman Project Manager| Pride Group Dhaka, Bangladesh
Good advice for me.

avatar
Luis Branco CEO| Business Insight, Consultores de Gestão, Ldª Carcavelos, Lisboa, Portugal
Dear Henry
Interesting is your perspective on the topic: "Good Practices for Project / Progress Meetings"

Thanks for sharing

I liked the good practices and the tips suggested for the meetings within the projects