Good Practices for Field Monitoring Construction

From the Project Management View from Rail Transit Programs and Projects Blog
by
A collection of articles sharing project processes, design and construction experience, best practices, and lessons learned along with operational knowledge related to executing programs and projects in the rail transit industry.

About this Blog

RSS

Recent Posts

Transitioning Constructed Products from Projects to Owner's Operations

Lessons to be Learned.  What Happens When the Buyer is Not the Owner, Operator and Maintainer of the Company?  

Managing Warranty After Achieving Contract Milestones

What Happens After the Buyer and Seller Agree on a Punchlist?

What is a Punchlist?

Categories

Acceptance, Analytics, ANSI, Asset Management, Best Value, Best Value Contractor Selection, Best Value Selection Criteria, Buyer, Certifications, Commissioning, Communications Management, Construction, Construction Completion, Construction Deliverables, construction manager, Construction Monitoring, Construction Submittals, Consultant, Consultant Contract, Contract Acquisition, Contract Completion, Contract Deliverables, Contract Delivery, Contract Development, Contract Integration, Contract Management, Contract Milestones, Contract Quality, Contract Requirements, Contract Submittals, Contracts, Decision Making, Definitions, Design, Design Bid Build, Design Build, Design Build Delivery, Design Deliverables, Design Services, Design Submittals, Design-Bid-Build, Division 1 Specifications, Document Control, Earned Value Management, Engineering, Estimating, Estimator, Ethics, Factory Acceptance Test, Final Acceptance, Final Completion, General Conditions, General Provisions, General Terms and Conditions, Good Practices, Government, Hard Risks, Hazards, Human Resources, Information For Bidders, Inspection, Inspection and Testing, Inspection Test Plan, Integration, Integration Management, Invitation For Bid, Key Performance Indicators, Knowledge Management, Maintenance, Management Integration, Managerial Time, Managing Change, Managing Changes, Master Project Schedule, Meeting Minutes, Mega Projects, NCR Process, Negotiations, Non Conformance Report, O&M Manuals, Oversight Reports, PM Fundamentals, PMBOK, PMI, PMO, Procurement Management, Professional Obligations, Program Management, program manager, Progress Reports, Project Charter, Project Controls, Project Engineer, Project Engineering, Project Integration, Project Interfacing, Project Management, Project Management Institute, project management office, Project Management Plan, Project Manager, Project Managerr, Project Planning, Project Records, Project Schedules, Project Team, Project Teams, ProjectManagement, Public Relations, punchlist, Quality, Quality, Rail Car Purchase, Rail Transit, Rail Transit Organization, Rail Transit Project, Rail Transit Projects, Railroad, Reliability, Resource Management, RFI Logs, risk, Risk Allocation, risk allocation, Risk Allocations, Risk Management, Risk Management, Safety, Schedule Interfaces, Schedule Management, Schedule Milestones, Scheduler, Scheduling, Scope of Work, Security, Seller, Site Acceptance Test, Soft Risks, Special Inspections, Specifications, Submittal Logs, Submittal Process, Substantial Completion, System Integration, System Integration Test, Systems, Systems Purchase, Testing/Test Management, Threats, Transformation, Transformational Projects, Transportation, Vulnerability, Work Area, Work Areas

Date

linkedin twitter facebook Request to reuse this  


Based on my experience in project management on rail transit projects, here are my best practices on field monitoring construction, which were compiled from work on capital projects for railroad infrastructure.

More often than not, most rail transit projects include multiple construction contracts and the use of railroad construction trades (referred to as Force Account - FA) to perform work over a vast project site. The work locations will change as work progresses and there not always barricades or work zone fences to protect the work site nor is there an on-site project office. All work is performed on the Right-Of-Way (ROW) with train service maintained for customers. Each active work location will be controlled by the individual FA work crews or by Contractors with appropriate railroad construction managers, protective services for track outages and power outages, safety escorts and/or flag protection services where sites have moving trains or on-track vehicles.

Contractors and FA will provide full supervision on site to create and safe and secure environment and to assure work performance meets schedule, work quality and safe work practices. Additionally, Contractor’s will submit a Safe Work Plan and detailed site specific work plans for each work location, and as specified by contract or purchase order, will assign Safety and Quality Managers to supplement supervision and project management. FA will establish a dedicated Safety Manager, and assign FA Managers accountable for monitoring of quality and safe work practices of in-house forces. FA will also assign personnel for inspection and acceptance of work performed by Contractors.

While contracts include Monthly Progress Reports and Meeting Minutes, these documents alone do not provide a continuous daily record of project work. Although there may be no fixed office, contractors maintain on-site logs and records of construction activities. However, these documents are not always available or accessible to project managers and other team members, who may be located at a project office miles from the work location. As a result, the daily construction oversight by project management (PM) personnel (or designated staff and GEC consultants) is critical to filling communications gaps and providing the project management staff with daily reports on activities in the field. The field activities will consist of:
• Reviewing Daily Field Reports from contractors and FA
• Visiting active work sites to observe safe work practices, signage and safety equipment, and to assess work means and methods
• Inspecting and recording contractor or FA compliance with construction documents
• Submitting field reports and coordinating observations with project controls and quality personnel
• Assuring controls for the entry and exit of personnel, equipment and materials at each work location
• Supervising activities of all visitors to site, including Independent Testing Agencies (ITA), mark-out contractors, safety officers/inspectors, code compliance officers, and FA/owner inspectors

Plan for Field Conditions
Field work on railroad construction project can vary greatly as will conditions regarding field offices and access to equipment and facilities for monitoring activities. For work on train stations, shops and yards and electrical substations, the site can usually be a fixed area where a fence can be erected to secure and control the work zone. The area will also allow for project offices, employee facilities, parking, and storage for materials, tools, and equipment.

However, for infrastructure systems such as track, power, signal and communications, the work area can cover miles of ROW. With the work zone and access changing daily with progress, there is no fenced work zone or offices available for meetings, administrative work and employee lockers. As a result, contractors, ITAs, construction managers and project oversight need to adapt. This typically means carrying the essential contents of the project office with them in vehicles, such as contract documents, safety equipment, telephones, test equipment, and outreach information. All other project offices activities will be performed at home office locations or designated headquarters.

Good Practices for Field Activities
• Conduct site walkthroughs at the start and end of the workday
• Observe and assess safe work practices and site housekeeping
• Verify work activity comply with the contract requirements
• Participate in job briefing and safe work meetings
• Assure work activities respect and minimize inconvenience for the day to day interaction with parties outside the work area
• Take and transmit photographs to main offices throughout the workday showing progress, field conditions, safe work practices and quality checks
• Submit Daily Field Reports to main offices by close of business or before next day start-up
• Notify the PMO and as needed, local authorities of any vandalism or stolen property

TIP: Always have access to the contract documents, approved work plans, and utility mark-outs, and use them while observing work. As needed, cite them in verifying compliance or providing field direction.

TIP: To aid in reporting of vandalism and stolen property, contractors should maintain descriptions and serial numbers of equipment and tools stored at the site.

TIP: Conduct telephone status meetings with main office at the start and end of workday.

Good Practices for Field Reports
• Document Timeline of progress throughout the work period
• Identify all subcontractor and visitors to the work site
• Record verbal reports from conducting special inspections by ITAs or Owner/FA representatives
• Correlate observations to specific contract requirements
• Indicate results from pre-construction field surveys and mark-outs

TIP: Record field direction to contractor from differing field conditions, including underground utilities not shown on mark-outs by in-house asset management or by outside “One Call” contractors hired on behalf of outside utilities/companies with assets in the construction work zone.
      


Posted on: January 13, 2018 06:17 PM | Permalink

Comments (8)

Please login or join to subscribe to this item
avatar
Henry Hattenrath Project Consultant| Tectonic Engineering MSA LLC New York, Ny, United States
The content was originally published in November 2016 under DISCUSSIONS. With encouragement from my PM.com peers, it is now part of a BLOG.

avatar
Najam Mumtaz Retired Lahore, Punjab, Pakistan
Rail road construction is project which has a unique feature that it can not have everything on-site as with the progress of project the site changes quite often which presents unique set of challenges. PM has to ensure being on site to get the information required to keep the project running smoothly.
Thank you Henry for sharing your experience, good practices and tips for handling rail road projects or other projects which can not have a proper infrastructure on site.

avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
Thanks Henry for this article.

avatar
Eduin Fernando Valdes Alvarado Project Manager| F y F Fabricamos Futuro Villavicencio, Meta, Colombia
Thanks for sharing

avatar
Anish Abraham Privacy Program Manager| University of Washington Auburn, Wa, United States
Informative article and thanks for sharing

avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Great Point Henry - Cheers

avatar
Md. Masudur Rahman Project Manager| Pride Group Dhaka, Bangladesh
True for almost all the constructions. Thanks for sharing.

avatar
Nikolaos Mavris Senior Project Manager| Rail Road Infra
Thanks for your article Henry.
A daily site report from an independent party is very useful for PM and PMO when many subcontractors are deployed and especially when there are interfaces between them or delays that affect handover.