Good Practices for Project Outreach

From the Project Management View from Rail Transit Programs and Projects Blog
by
A collection of articles sharing project processes, design and construction experience, best practices, and lessons learned along with operational knowledge related to executing programs and projects in the rail transit industry.

About this Blog

RSS

Recent Posts

Transitioning Constructed Products from Projects to Owner's Operations

Lessons to be Learned.  What Happens When the Buyer is Not the Owner, Operator and Maintainer of the Company?  

Managing Warranty After Achieving Contract Milestones

What Happens After the Buyer and Seller Agree on a Punchlist?

What is a Punchlist?

Categories

Acceptance, Analytics, ANSI, Asset Management, Best Value, Best Value Contractor Selection, Best Value Selection Criteria, Buyer, Certifications, Commissioning, Communications Management, Construction, Construction Completion, Construction Deliverables, construction manager, Construction Monitoring, Construction Submittals, Consultant, Consultant Contract, Contract Acquisition, Contract Completion, Contract Deliverables, Contract Delivery, Contract Development, Contract Integration, Contract Management, Contract Milestones, Contract Quality, Contract Requirements, Contract Submittals, Contracts, Decision Making, Definitions, Design, Design Bid Build, Design Build, Design Build Delivery, Design Deliverables, Design Services, Design Submittals, Design-Bid-Build, Division 1 Specifications, Document Control, Earned Value Management, Engineering, Estimating, Estimator, Ethics, Factory Acceptance Test, Final Acceptance, Final Completion, General Conditions, General Provisions, General Terms and Conditions, Good Practices, Government, Hard Risks, Hazards, Human Resources, Information For Bidders, Inspection, Inspection and Testing, Inspection Test Plan, Integration, Integration Management, Invitation For Bid, Key Performance Indicators, Knowledge Management, Maintenance, Management Integration, Managerial Time, Managing Change, Managing Changes, Master Project Schedule, Meeting Minutes, Mega Projects, NCR Process, Negotiations, Non Conformance Report, O&M Manuals, Oversight Reports, PM Fundamentals, PMBOK, PMI, PMO, Procurement Management, Professional Obligations, Program Management, program manager, Progress Reports, Project Charter, Project Controls, Project Engineer, Project Engineering, Project Integration, Project Interfacing, Project Management, Project Management Institute, project management office, Project Management Plan, Project Manager, Project Managerr, Project Planning, Project Records, Project Schedules, Project Team, Project Teams, ProjectManagement, Public Relations, punchlist, Quality, Quality, Rail Car Purchase, Rail Transit, Rail Transit Organization, Rail Transit Project, Rail Transit Projects, Railroad, Reliability, Resource Management, RFI Logs, risk, Risk Allocation, risk allocation, Risk Allocations, Risk Management, Risk Management, Safety, Schedule Interfaces, Schedule Management, Schedule Milestones, Scheduler, Scheduling, Scope of Work, Security, Seller, Site Acceptance Test, Soft Risks, Special Inspections, Specifications, Submittal Logs, Submittal Process, Substantial Completion, System Integration, System Integration Test, Systems, Systems Purchase, Testing/Test Management, Threats, Transformation, Transformational Projects, Transportation, Vulnerability, Work Area, Work Areas

Date

linkedin twitter facebook Request to reuse this  


By following an established plan, project managers routinely communicate with the team, stakeholders, contractors, consultants, technical contributors, projects sponsors and funding partners. In rail transit projects there is added consideration to the system users/pre-paid customers, system operating personnel, agency oversight, public officials, and communities that are served and impacted by the system.

Most rail transit agencies have a Community Affairs/Government Relations Department or assigned designee that is responsible for dealing with external entities. As part of the communications plan, project managers will be assisted by the in developing letters, press releases, newspaper ads, posters, brochures, and videos that will targeted to specific audiences and timed for issuance with critical milestones of the project. While these communications are normally tied to the project schedule, project managers will also need to respond to complaints or inquiries at any given time.

Public outreach plans and deliverables for project will likely follow the agencies standard format and contents, and include contact information for a designated representative – not necessarily the project manager. The content and purpose of each deliverable will be targeted to the audiences, such as Community, Public officials, Customers, and On –Site visitors. Each deliverable may have unique content. The core topics may consist of project description, overall schedule and milestones, benefits to the community and customers, impacts to customers and the community during work periods, and contact information for corporate spokespersons.

Good Practices for Outreach
• Create a strategic plan for creating and distributing deliverables that allows adequate time for development and issuance that is timed with project milestones
• Ensure project records are collected to support outreach content with photographs
• Collect quotations from project team members, stakeholders, contractors, consultants, technical contributors, projects sponsors, funding partners, Subject Matter Experts and oversight consultants
• Consider other topics such as innovation methods implemented by the project, such as a contracting process, goals/opportunities for minority or disadvantaged business, resiliency feature in the project design, and benefits to the local construction industry
• Coordinate content with other corporate plans and content for marketing and sales
• Assure project team members are trained in effective communications and situational techniques for speaking with the public.

TIP: While mega-projects are most likely to have an extensive outreach even small projects may need outreach.

TIP: Treat your project as a brand for the Client, consultant, contractor and individuals involved.

Good Practices for Deliverables
• Assure content is consistent with other project documents such as Project Charter, Project Management Plan and external project reports
• Ensure deliverables indicate a data date so the content is time scaled
• Cite statements from Subject Matter Experts and oversight consultants
• Have copies of deliverables at work locations for project team designee distribution to visitors.

TIP: Have a one-page sheet of Frequently Asked Questions and Answers available on-site so the project designee is prepared to discuss the project with visitors.

TIP: While mega-projects are most likely to have an extensive outreach even small projects may need a internal/external website to share information with internal customers and interested parties and with external public customers and interested parties, oversight and government officials, transportation advocates and politicians.

TIP: On a daily basis, ensure there is a project representative designated on-site to address visitor comments, questions or complaints.
      


Posted on: January 19, 2018 06:48 PM | Permalink

Comments (6)

Please login or join to subscribe to this item
avatar
Henry Hattenrath Project Consultant| Tectonic Engineering MSA LLC New York, Ny, United States
The content was originally published in December 2016 under DISCUSSIONS. With encouragement from my PM.com peers, it is now part of a BLOG.

avatar
Najam Mumtaz Retired Lahore, Punjab, Pakistan
Thank you Henry for sharing good practices and tips for project outreach. Mega projects do have someone designated to do this job with powerpoint presentations and data charts but we can always have representative with flyers or posters to address visitor comments and questions for smaller projects.

avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
Good insights.

avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Good Points.

avatar
Anish Abraham Privacy Program Manager| University of Washington Auburn, Wa, United States
Nice article and thanks for your insight on this.

avatar
Eduin Fernando Valdes Alvarado Project Manager| F y F Fabricamos Futuro Villavicencio, Meta, Colombia
Very interesting, thanks

Please Login/Register to leave a comment.

ADVERTISEMENTS

"The greatest deception men suffer is from their own opinions."

- Leonardo Da Vinci

ADVERTISEMENT

Sponsors