Project Management

Part 5 of 10-The Book that Most Impacted My Career-Excellence in Engineering

From the Project Management View from Rail Transit Programs and Projects Blog
by
A collection of articles sharing project processes, design and construction experience, best practices, and lessons learned along with operational knowledge related to executing programs and projects in the rail transit industry.

About this Blog

RSS

Recent Posts

Transitioning Constructed Products from Projects to Owner's Operations

Lessons to be Learned.  What Happens When the Buyer is Not the Owner, Operator and Maintainer of the Company?  

Managing Warranty After Achieving Contract Milestones

What Happens After the Buyer and Seller Agree on a Punchlist?

What is a Punchlist?

Categories

Acceptance, Analytics, ANSI, Asset Management, Best Value, Best Value Contractor Selection, Best Value Selection Criteria, Buyer, Certifications, Commissioning, Communications Management, Construction, Construction Completion, Construction Deliverables, construction manager, Construction Monitoring, Construction Submittals, Consultant, Consultant Contract, Contract Acquisition, Contract Completion, Contract Deliverables, Contract Delivery, Contract Development, Contract Integration, Contract Management, Contract Milestones, Contract Quality, Contract Requirements, Contract Submittals, Contracts, Decision Making, Definitions, Design, Design Bid Build, Design Build, Design Build Delivery, Design Deliverables, Design Services, Design Submittals, Design-Bid-Build, Division 1 Specifications, Document Control, Earned Value Management, Engineering, Estimating, Estimator, Ethics, Factory Acceptance Test, Final Acceptance, Final Completion, General Conditions, General Provisions, General Terms and Conditions, Good Practices, Government, Hard Risks, Hazards, Human Resources, Information For Bidders, Inspection, Inspection and Testing, Inspection Test Plan, Integration, Integration Management, Invitation For Bid, Key Performance Indicators, Knowledge Management, Maintenance, Management Integration, Managerial Time, Managing Change, Managing Changes, Master Project Schedule, Meeting Minutes, Mega Projects, NCR Process, Negotiations, Non Conformance Report, O&M Manuals, Oversight Reports, PM Fundamentals, PMBOK, PMI, PMO, Procurement Management, Professional Obligations, Program Management, program manager, Progress Reports, Project Charter, Project Controls, Project Engineer, Project Engineering, Project Integration, Project Interfacing, Project Management, Project Management Institute, project management office, Project Management Plan, Project Manager, Project Managerr, Project Planning, Project Records, Project Schedules, Project Team, Project Teams, ProjectManagement, Public Relations, punchlist, Quality, Quality, Rail Car Purchase, Rail Transit, Rail Transit Organization, Rail Transit Project, Rail Transit Projects, Railroad, Reliability, Resource Management, RFI Logs, risk, Risk Allocation, risk allocation, Risk Allocations, Risk Management, Risk Management, Safety, Schedule Interfaces, Schedule Management, Schedule Milestones, Scheduler, Scheduling, Scope of Work, Security, Seller, Site Acceptance Test, Soft Risks, Special Inspections, Specifications, Submittal Logs, Submittal Process, Substantial Completion, System Integration, System Integration Test, Systems, Systems Purchase, Testing/Test Management, Threats, Transformation, Transformational Projects, Transportation, Vulnerability, Work Area, Work Areas

Date

linkedin twitter facebook Request to reuse this  


This is Part 5 of a blog about a book that most impacted my career - Excellence In Engineering by W.H. Roadstrum, 1967, and relates it to Project Management Institute’s Project Management Book of Knowledge (PMBOK).

My work experience includes varying roles in managing projects and integrating the deliverables from Project Controls such as estimates, schedules, progress reports, financial reports, and project performance reports.   In all cases, the project team was responsible for the quality and implementation of the deliverables from Project Controls.   These deliverables were essential tools for the team to manage project performance to scope, schedule, budget, project objective, safety and quality goals, and customer expectations.  

The effectiveness of the tools is a function of the organizational assets that are inputs to Project Controls, and from which the project management office establishes requirements, processes and procedures to create, generate, measure and assess realistic project metrics.

In Excellence In Engineering-Chapter 4, Roadstrum emphasizes several points on Project Controls:

  1. Good technical engineering work will be obscured (and can even be completely nullified) by poor administrative control.

  2. Good technical work will not by itself control a project.A project can not control itself.It must be deliberately controlled by the project team, especially the project engineer.

  3. Plan and schedule for almost every engineering project will change significantly during the work.

  4. It is a surprisingly common belief among some groups of engineers that technical work can not be effectively controlled.This attitude prevails at times even in high places.Such a conviction sometimes reflects the influences of a manger who feels the same way, or of previous ones who did.

  5. The idea that projects can not be effectively controlled is a self-fulfilling prophecy for the engineer who thinks this way.

  6. From a business standpoint, company management naturally expects that technical work will be administered effectively.

Work flow for initial schedule development consists of:

  1. Establish initial overall concept.

  2. Determine critical factors in each area.

  3. Specify all interface conditions and alternatives.

  4. Establish estimates {for each of the activities.

  5. Establish final configuration and make recommendations.

  6. Complete proposal document and costing.

Good Engineering Practices for Scheduling

  1. Schedule the whole project vat the outset.Recognize interdependence of parts.

  2. Identify the critical items early.Keep a current list of them.

  3. Seek out the best time and cost estimates available on critical items.

  4. Modify and update schedule as needed.

  5. Bring all contributors or contributing groups into the scheduling process.

Poor Engineering Practices for Scheduling

  1. Make no schedule or only a trivial one.Never go into the critical detail which will determine the success of the project.

  2. Fail to recognize the interdependencies in schedule.Schedule unrealistically.

  3. Make schedules in too much detail.Include non-critical detail.

  4. Select schedule milestones which are difficult to follow and assess.

Chapter 6, PMBOK-Fifth Edition provides some guidance on inputs and outputs for the schedule development and maintenance cycle.

In PMBOK Section  6.6.1, the inputs for an effective schedule include: 

  • Activity list

  • Activity attributes

  • Logic ties between activities

  • Interdependencies between work packages and other projects

  • Enterprise factors, such as manpower and equipment

  • Organizational assets and processes used by participants, including the contractor and client.

PMBOK Section 6.6.3.2 defines the product for Project Schedule, which is created using the input and expert knowledge of project staff and applying scheduling standards and tools defined in the Project Management and Scheduling Plans.    The section describes the project schedule as an output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources.  At a minimum, the project schedule includes planned start date and finish date for each activity.


Posted on: April 08, 2018 06:15 PM | Permalink

Comments (6)

Please login or join to subscribe to this item
avatar
Riyadh Salih Saskatchewan, Canada
Henry, very good topic reminded me with the steps we use in performing maintenance 1. I identify 2. Plan 3. Schedule 4. Assign 5. Execute 6. Learn / Archive but if there is an Emergency the step 2 & 3 will be bypassed and move directly to 4. Assign.

avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
Henry, I think this must be your all-time favorite book.

avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Great points Henry.

avatar
Najam Mumtaz Retired Lahore, Punjab, Pakistan
Thank you Henry for describing project controls, steps to schedule development and maintenance cycle.

avatar
Eduin Fernando Valdes Alvarado Project Manager| F y F Fabricamos Futuro Villavicencio, Meta, Colombia
Thanks for sharing, very interesting

avatar
Drew Craig Sr. Agile & Product Coach| Vanguard Philadelphia, Pa, United States
Excellent items to point out. Thanks, Henry.

Please Login/Register to leave a comment.

ADVERTISEMENTS

"No man who has once heartily and wholly laughed can be altogether irreclaimably bad."

- Thomas Carlyle

ADVERTISEMENT

Sponsors