Project Management

Part 6 of 10-The Book that Most Impacted My Career-Excellence in Engineering

From the Project Management View from Rail Transit Programs and Projects Blog
by
A collection of articles sharing project processes, design and construction experience, best practices, and lessons learned along with operational knowledge related to executing programs and projects in the rail transit industry.

About this Blog

RSS

Recent Posts

Transitioning Constructed Products from Projects to Owner's Operations

Lessons to be Learned.  What Happens When the Buyer is Not the Owner, Operator and Maintainer of the Company?  

Managing Warranty After Achieving Contract Milestones

What Happens After the Buyer and Seller Agree on a Punchlist?

What is a Punchlist?

Categories

Acceptance, Analytics, ANSI, Asset Management, Best Value, Best Value Contractor Selection, Best Value Selection Criteria, Buyer, Certifications, Commissioning, Communications Management, Construction, Construction Completion, Construction Deliverables, construction manager, Construction Monitoring, Construction Submittals, Consultant, Consultant Contract, Contract Acquisition, Contract Completion, Contract Deliverables, Contract Delivery, Contract Development, Contract Integration, Contract Management, Contract Milestones, Contract Quality, Contract Requirements, Contract Submittals, Contracts, Decision Making, Definitions, Design, Design Bid Build, Design Build, Design Build Delivery, Design Deliverables, Design Services, Design Submittals, Design-Bid-Build, Division 1 Specifications, Document Control, Earned Value Management, Engineering, Estimating, Estimator, Ethics, Factory Acceptance Test, Final Acceptance, Final Completion, General Conditions, General Provisions, General Terms and Conditions, Good Practices, Government, Hard Risks, Hazards, Human Resources, Information For Bidders, Inspection, Inspection and Testing, Inspection Test Plan, Integration, Integration Management, Invitation For Bid, Key Performance Indicators, Knowledge Management, Maintenance, Management Integration, Managerial Time, Managing Change, Managing Changes, Master Project Schedule, Meeting Minutes, Mega Projects, NCR Process, Negotiations, Non Conformance Report, O&M Manuals, Oversight Reports, PM Fundamentals, PMBOK, PMI, PMO, Procurement Management, Professional Obligations, Program Management, program manager, Progress Reports, Project Charter, Project Controls, Project Engineer, Project Engineering, Project Integration, Project Interfacing, Project Management, Project Management Institute, project management office, Project Management Plan, Project Manager, Project Managerr, Project Planning, Project Records, Project Schedules, Project Team, Project Teams, ProjectManagement, Public Relations, punchlist, Quality, Quality, Rail Car Purchase, Rail Transit, Rail Transit Organization, Rail Transit Project, Rail Transit Projects, Railroad, Reliability, Resource Management, RFI Logs, risk, Risk Allocation, risk allocation, Risk Allocations, Risk Management, Risk Management, Safety, Schedule Interfaces, Schedule Management, Schedule Milestones, Scheduler, Scheduling, Scope of Work, Security, Seller, Site Acceptance Test, Soft Risks, Special Inspections, Specifications, Submittal Logs, Submittal Process, Substantial Completion, System Integration, System Integration Test, Systems, Systems Purchase, Testing/Test Management, Threats, Transformation, Transformational Projects, Transportation, Vulnerability, Work Area, Work Areas

Date

linkedin twitter facebook Request to reuse this  


This blog will cover sections of Excellence In Engineering by W.H. Roadstrum, 1967, and relate them to Project Management Institute’s Project Management Book of Knowledge (PMBOK).

In Chapter 4 of Excellence In Engineering, Roadstrum identifies Project Controls as three elements – Scheduling, Monitoring and Controlling.   As discussed in Part 5, the first of three elements of Project Controls was presented – Scheduling.   In this Part, the Monitoring practices will be highlighted.   

As I have learned through a career in project management, keeping the team focused on the project vision, mission, objective, and benefits, which are identified and committed to through the Project Charter, is an essential function of the project leader.   But an equally important part of the business of project management is to advise the team on performance to project metrics. 

 Roadstrum builds on the work flow and scheduling practices to define the practices for monitoring the baseline schedule within established milestones, dates and goals.

Good Engineering Practices for Monitoring

  1. Follow and monitor performance (time, cost, technical progress) on a regular basis.

  2. Include all contributors in the monitoring process so they are also “self-monitoring”.

  3. Plan at least general alternatives for each principal contingency.

  4. Keep the goal and its broad alternatives clearly in mind.

Poor Engineering Practices for Monitoring

  1. Because of preoccupation with novel and challenging areas of the project, allow unmonitored tasks to run far off schedule.

  2. Because of failure to identify critical items, do not follow these or provide alternatives.

  3. Wait for other people or the turn of events.Raise no questions on schedule progress until critical deadlines have been missed.

  4. Mistake proper rate of expenditures for adherence to technical schedule.

  5. Allow an old schedule to become so outdated as to be useless.

PMBOK – Fifth Edition Chapter 6, regarding Project Time Management, covers scheduling and schedule control tools and techniques common for monitoring of the project schedule, and the respective performance indicator (s), which are shared across schedules and estimates under the project controls function.

Section 6.6.2 identifies tools and techniques for monitoring and updating project schedules using subject matter expertise and software.    The project team can make improvements in achieving scheduled dates, planned progress goals, and in creating recovery plans for projects with poor performance indicators.    The actions may be created by several means:

  • Network Analysis – This involves showing where various activities converge or diverge with dependent activities.

  • Critical Path Method - This involves using the predecessor and successor connections with activities where the estimated duration has fixed start and end dates and contingency in scheduled duration with other activities.  

  • Critical Chain Method - This involves using buffers in activity durations to account for limited resources.

  • Resource Optimization – This involves using resource leveling and resource smoothing to adjust the duration of activities and align with available resources.

  • Modeling  - This involves  conducting trial and error changes to the baseline to detect potential schedule risks and to improve schedule efficiency and production effectiveness.

  • Leads and Lags - This involves adjusting the activity relations, such as start-to-start, finish-to- start, and finish-to-finish, to establish modified connections in the predecessor/successor relationship, such as start Task B 60 days prior to finish of Task A.

  • Schedule Compression - This involves  Crashing - shortening activity duration with corresponding increases in resources, and Fast Tracking - re-sequencing work activities to increase overall progress rate and to shorten the project duration.


Posted on: April 17, 2018 06:18 PM | Permalink

Comments (4)

Please login or join to subscribe to this item
avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
Thanks for another addition to the series Henry.

avatar
Eduin Fernando Valdes Alvarado Project Manager| F y F Fabricamos Futuro Villavicencio, Meta, Colombia
Thanks for sharing, thanks

avatar
Riyadh Salih Saskatchewan, Canada
Looks like I missed the first two episodes of the series

avatar
Drew Craig Sr. Agile & Product Coach| Vanguard Philadelphia, Pa, United States
Good correlation. Thanks, Henry.

Please Login/Register to leave a comment.

ADVERTISEMENTS

"Life does not cease to be funny when people die any more than it ceases to be serious when people laugh."

- George Bernard Shaw

ADVERTISEMENT

Sponsors