Part 7 of 10-The Book that Most Impacted My Career-Excellence in Engineering
From the Project Management View from Rail Transit Programs and Projects Blog
by Henry Hattenrath
A collection of articles sharing project processes, design and construction experience, best practices, and lessons learned along with operational knowledge related to executing programs and projects in the rail transit industry.
Recent Posts
Transitioning Constructed Products from Projects to Owner's Operations
Lessons to be Learned. What Happens When the Buyer is Not the Owner, Operator and Maintainer of the Company?
Managing Warranty After Achieving Contract Milestones
What Happens After the Buyer and Seller Agree on a Punchlist?
What is a Punchlist?
Categories
Acceptance,
Analytics,
ANSI,
Asset Management,
Best Value,
Best Value Contractor Selection,
Best Value Selection Criteria,
Buyer,
Certifications,
Commissioning,
Communications Management,
Construction,
Construction Completion,
Construction Deliverables,
construction manager,
Construction Monitoring,
Construction Submittals,
Consultant,
Consultant Contract,
Contract Acquisition,
Contract Completion,
Contract Deliverables,
Contract Delivery,
Contract Development,
Contract Integration,
Contract Management,
Contract Milestones,
Contract Quality,
Contract Requirements,
Contract Submittals,
Contracts,
Decision Making,
Definitions,
Design,
Design Bid Build,
Design Build,
Design Build Delivery,
Design Deliverables,
Design Services,
Design Submittals,
Design-Bid-Build,
Division 1 Specifications,
Document Control,
Earned Value Management,
Engineering,
Estimating,
Estimator,
Ethics,
Factory Acceptance Test,
Final Acceptance,
Final Completion,
General Conditions,
General Provisions,
General Terms and Conditions,
Good Practices,
Government,
Hard Risks,
Hazards,
Human Resources,
Information For Bidders,
Inspection,
Inspection and Testing,
Inspection Test Plan,
Integration,
Integration Management,
Invitation For Bid,
Key Performance Indicators,
Knowledge Management,
Maintenance,
Management Integration,
Managerial Time,
Managing Change,
Managing Changes,
Master Project Schedule,
Meeting Minutes,
Mega Projects,
NCR Process,
Negotiations,
Non Conformance Report,
O&M Manuals,
Oversight Reports,
PM Fundamentals,
PMBOK,
PMI,
PMO,
Procurement Management,
Professional Obligations,
Program Management,
program manager,
Progress Reports,
Project Charter,
Project Controls,
Project Engineer,
Project Engineering,
Project Integration,
Project Interfacing,
Project Management,
Project Management Institute,
project management office,
Project Management Plan,
Project Manager,
Project Managerr,
Project Planning,
Project Records,
Project Schedules,
Project Team,
Project Teams,
ProjectManagement,
Public Relations,
punchlist,
Quality,
Quality,
Rail Car Purchase,
Rail Transit,
Rail Transit Organization,
Rail Transit Project,
Rail Transit Projects,
Railroad,
Reliability,
Resource Management,
RFI Logs,
risk,
Risk Allocation,
risk allocation,
Risk Allocations,
Risk Management,
Risk Management,
Safety,
Schedule Interfaces,
Schedule Management,
Schedule Milestones,
Scheduler,
Scheduling,
Scope of Work,
Security,
Seller,
Site Acceptance Test,
Soft Risks,
Special Inspections,
Specifications,
Submittal Logs,
Submittal Process,
Substantial Completion,
System Integration,
System Integration Test,
Systems,
Systems Purchase,
Testing/Test Management,
Threats,
Transformation,
Transformational Projects,
Transportation,
Vulnerability,
Work Area,
Work Areas
Date
This blog will cover sections of Excellence In Engineering by W.H. Roadstrum, 1967, and relate them to Project Management Institute’s Project Management Book of Knowledge (PMBOK).
In Chapter 4 of Excellence In Engineering, Roadstrum covers Scheduling, Monitoring and Controlling processes and practices project work. While Part 5 and Part 6 of this blog series presented Scheduling and Monitoring, this blog will cover the Controlling element.
From a project perspective, the controlling process is initiated after the baseline schedule is prepared and the processes and practices for monitoring project activities and progress to the baseline are implemented by the project team. Similar to controlling contract change orders, changes to the schedule need to be identified, confirmed, evaluated for effectiveness and then implemented to create a new baseline for monitoring work.
Near the end of the Chapter, Roadstrum summarizes:
Good Engineering Practices for Controlling
1.Take early corrective action where needed.
2.Balance project effort on all needed phases.
3.Watch continually for places where the effort can be reduced.
4.Make changes early rather than late.
Poor Engineering Practices for Controlling
1.Mistake “scheduling” for “control.” Fail to monitor or to take needed action.
2.Overemphasize certain areas to the detriment of overall cost and schedule.
3.Failing to make controlling changes in time.
The development and use of scheduling software has enabled project teams to more effectively and efficiently monitor project work by providing automated analysis of critical schedule metrics to produce numerous reports for earned value, changes in critical activities, and production and performance indexes.
PMBOK Chapter 6-Section 6.7.2 identifies tools and techniques for Control Schedule, including:
- Trend Analysis – This examines metrics comparing actual progress and expenses against past performance and available unit cost/production rates for the project estimate.
- Critical Path Method – This examines activities on the critical path to assess early or late completion of work and to identify threats or opportunities for schedule adjustments.
- Critical Chain Method – This examines resources allocations planned and actual to assess production rates, to forecast for activity completions and to identify adjustments in resources that may improve the schedule.
- Earned Value Management – Based on the earned value, this compares schedule and cost of planned work with the budget value of work completed. The ratios for cost and schedule produce performance indexes (CPI=EV/Actual Cost; and SPI=EV/Planned Value. )
The controlling process encompasses documenting the rationale for the schedule action, and provides feedback to produce and share Lessons Learned on other projects. The schedule software output can be used to explain variances, produce a record to initiate a schedule change, and to document the expected results from implementing the changes in the baseline schedule.
Posted on: April 24, 2018 07:14 PM |
Permalink
Comments (6)
Please login or join to subscribe to this item
Thanks Henry for this installment of the series.
Thanks Henry for your efforts and especially the good practices.
Adeel Khan Leghari
Director, Technology & Transformation| Deloitte & Touche
Riyadh, Riyadh, Saudi Arabia
Drew Craig
Sr. Agile & Product Coach| Vanguard
Philadelphia, Pa, United States
Thanks, Henry, for this chapter of your series. Nice correlation b/t the two.
Please Login/Register to leave a comment.
|
"There is nothing more difficult than talking about music."
- Camille Saint-Saens
|