Project Management

Part 3  -  Challenges, the Laws of Physics, Project/Construction Management and Reality

From the Project Management View from Rail Transit Programs and Projects Blog
by
A collection of articles sharing project processes, design and construction experience, best practices, and lessons learned along with operational knowledge related to executing programs and projects in the rail transit industry.

About this Blog

RSS

Recent Posts

Transitioning Constructed Products from Projects to Owner's Operations

Lessons to be Learned.  What Happens When the Buyer is Not the Owner, Operator and Maintainer of the Company?  

Managing Warranty After Achieving Contract Milestones

What Happens After the Buyer and Seller Agree on a Punchlist?

What is a Punchlist?

Categories

Acceptance, Analytics, ANSI, Asset Management, Best Value, Best Value Contractor Selection, Best Value Selection Criteria, Buyer, Certifications, Commissioning, Communications Management, Construction, Construction Completion, Construction Deliverables, construction manager, Construction Monitoring, Construction Submittals, Consultant, Consultant Contract, Contract Acquisition, Contract Completion, Contract Deliverables, Contract Delivery, Contract Development, Contract Integration, Contract Management, Contract Milestones, Contract Quality, Contract Requirements, Contract Submittals, Contracts, Decision Making, Definitions, Design, Design Bid Build, Design Build, Design Build Delivery, Design Deliverables, Design Services, Design Submittals, Design-Bid-Build, Division 1 Specifications, Document Control, Earned Value Management, Engineering, Estimating, Estimator, Ethics, Factory Acceptance Test, Final Acceptance, Final Completion, General Conditions, General Provisions, General Terms and Conditions, Good Practices, Government, Hard Risks, Hazards, Human Resources, Information For Bidders, Inspection, Inspection and Testing, Inspection Test Plan, Integration, Integration Management, Invitation For Bid, Key Performance Indicators, Knowledge Management, Maintenance, Management Integration, Managerial Time, Managing Change, Managing Changes, Master Project Schedule, Meeting Minutes, Mega Projects, NCR Process, Negotiations, Non Conformance Report, O&M Manuals, Oversight Reports, PM Fundamentals, PMBOK, PMI, PMO, Procurement Management, Professional Obligations, Program Management, program manager, Progress Reports, Project Charter, Project Controls, Project Engineer, Project Engineering, Project Integration, Project Interfacing, Project Management, Project Management Institute, project management office, Project Management Plan, Project Manager, Project Managerr, Project Planning, Project Records, Project Schedules, Project Team, Project Teams, ProjectManagement, Public Relations, punchlist, Quality, Quality, Rail Car Purchase, Rail Transit, Rail Transit Organization, Rail Transit Project, Rail Transit Projects, Railroad, Reliability, Resource Management, RFI Logs, risk, Risk Allocation, risk allocation, Risk Allocations, Risk Management, Risk Management, Safety, Schedule Interfaces, Schedule Management, Schedule Milestones, Scheduler, Scheduling, Scope of Work, Security, Seller, Site Acceptance Test, Soft Risks, Special Inspections, Specifications, Submittal Logs, Submittal Process, Substantial Completion, System Integration, System Integration Test, Systems, Systems Purchase, Testing/Test Management, Threats, Transformation, Transformational Projects, Transportation, Vulnerability, Work Area, Work Areas

Date

linkedin twitter facebook Request to reuse this  


Contract Submittal Process

You see it more and more, corporate leaders flex their authority and demand the work force do it faster, do it cheaper, do it better and do it right.   Despite the obvious opposing forces to achieve these goals, program and project managers are expected to execute and overcome obstacles to progress and project realization.   

Demanding construction contract submittals be processed in a 7 day review cycle can only achieve success if the contractor’s submittal quality, size and complexity are aligned with the Construction Manager’s (CM)  process work flow and the assigned reviewer resources.

For typical construction projects, the contract specifications follow Construction Specifications Institute (CSI).    The submittal general description, specific product requirements and the execution requirements are typically contained in the CSI-Division 1 specifications.   The product requirements include descriptions of items such as shop drawings, product data, as-built drawings, calculations, inspection and test reports, and material samples.  The execution requirements include the disposition of reviews, the review duration and timing with construction schedule, resubmittal requirements, and the overall process work flow.   The disposition of submittal reviews are normally A) Proceed.  B)  Proceed As Noted.   C)  Proceed As Noted – Revise and Resubmit.  D)  Do Not Proceed – Revise and Resubmit.

In many rail transit projects, contractors are typically requested to plan the submittal register and schedule for a 30 day period from receipt of submittals to return of comments to the contractor.   This period includes CM administration, review comments by Engineer of Record (EOR), and review and reconciliation of Owner comments.   The construction contract submittal process is managed with simple software tools, such as MSExcel, or more targeted contract management tools, such as SharePoint and UNIFER, that track submittals by specification, date to CM, date returned to contractor, and the disposition.  

To shorten the review cycle period, program and project executives as well as scheduling experts would insist that additional EOR staff be increased and that reviews be conducted by multiple reviewers. 

Assigning multiple reviewers to submittals to shorten the review period may work on paper. If multiple reviewers are assigned, then the process work follow will need to conduct an integration review and comment reconciliation before the submittal can be returned to the contractor.   But typically, it is more effective to assign a single person familiar with the requirements and the contract development.   A single reviewer will assure a systematic and integrated review of a submittal from start to finish. 

The Division 1 specification for submittals allows the CM and contractor much latitude and flexibility to create a process work flow to maximize the use of the contractor’s internal processes and documentation standards.   However, the processes and documentation standards can be vastly different between contracts and vary widely depending on the contract scope.   Additionally, system contracts, tunneling contracts, vehicle procurement contracts, vehicle storage yard contracts and substation contracts all are unique to their individual industries. 

The content and complexity of submittals and Requests for Information are also a function of contractor processes, new technology, specialized means and methods, and direction received at project meetings.   In order to improve the performance, a more prescriptive description of submittal packages tailored to shop drawings, product data, test procedures, and installation instructions will need to be developed to effectuate a 7 day review cycle:  

  • Submittals:   Based on the approved Submittal Register/Schedule, documents submitted to the CM shall contain no more than 20 drawings or 50 sheets for product data, manuals, and calculations.   For composite submittal content, the total sheets shall not exceed 30 sheets. (For large submittals, the contractor/CM will need to establish multiple Submittals that allows a longer review period of consecutive 7 day periods.)
  • Requests For Information:   Using the ESA standard form, an RFI shall be limited to one primary question and no more than 5 sheets of attachments. 

Managing a more prescriptive submittal process will require the CM and contractor to more intensely monitor staffing and CPS priorities to maintain aggressive progress.  Additionally, the CM and contractor will be needed to be nimble in making changes as the construction schedule is adjusted.   As a result, the standard submittal register/schedule may become more extensive as other attributes are added to the process work flow, including:

  • Assigned reviewers
  • Successor construction activity ID, description and start date
  • Interdependencies with other submittals

Reality

Unless process reviews are diligently managed and controlled by CM within the approved Submittal Register/Schedule, the return of submittals will deviate from the contract guide of 30 days.   The risks on the construction schedule will be monitored and mitigated by the CM, contractor and EOR working closely together to prioritize critical submittals for review.   


Posted on: July 28, 2018 06:00 PM | Permalink

Comments (8)

Please login or join to subscribe to this item
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Good points Henry

avatar
Nabeel Hamed PMO Manager| General Contracting Co. Dammam, Saudi Arabia
To resolve the issue of clogging with accumulated submittals, some clients instruct contractors to limit their early submittals to those required for pushing the site work for the first 3 months of the site construction activities.

avatar
Nabeel Hamed PMO Manager| General Contracting Co. Dammam, Saudi Arabia
Also, I have noticed that some clients prepare material data sheets filled with required parameters and ready for filling and stamping by the contractor and material vendor. This will make submittal review much easier and faster.

avatar
Henry Hattenrath Project Consultant| Tectonic Engineering MSA LLC New York, Ny, United States
Nabeel

Your suggestions will be helpful to the Owner, client and the CM representative. The selection of targeted reviewers is also an area that can help reduce waiting for feedback from reviewers who may not have a technical interest in the submittal and deliverable. In some cases, the client and Owner may decide they do not need to review many items and they defer responsibility to the CM and Engineer of Record..

avatar
Tamer Zeyad Sadiq Assistant Cost Manager| Turner & Townsend Riyadh, Ar Riyad, Saudi Arabia
Thanks for sharing!!

avatar
Eduin Fernando Valdes Alvarado Project Manager| F y F Fabricamos Futuro Villavicencio, Meta, Colombia
Thanks for sharing

avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
Always interesting Henry. Thanks.

avatar
Vincent Guerard Coach - Trainer - Speaker - Advisor| Freelance Mont-Royal, Quebec, Canada
Henry,
Very good
The notation you suggest is very interesting, and better than the one I have seen use here. A and B similar C - Revise and resubmit and D - Refuse

Please Login/Register to leave a comment.

ADVERTISEMENTS

A mind once stretched by a new idea never regains its original dimensions.

- Anonymous

ADVERTISEMENT

Sponsors