Part 2 - Do You Know the Entire Contract
From the Project Management View from Rail Transit Programs and Projects Blog
by Henry Hattenrath
A collection of articles sharing project processes, design and construction experience, best practices, and lessons learned along with operational knowledge related to executing programs and projects in the rail transit industry.
Recent Posts
Transitioning Constructed Products from Projects to Owner's Operations
Lessons to be Learned. What Happens When the Buyer is Not the Owner, Operator and Maintainer of the Company?
Managing Warranty After Achieving Contract Milestones
What Happens After the Buyer and Seller Agree on a Punchlist?
What is a Punchlist?
Categories
Acceptance,
Analytics,
ANSI,
Asset Management,
Best Value,
Best Value Contractor Selection,
Best Value Selection Criteria,
Buyer,
Certifications,
Commissioning,
Communications Management,
Construction,
Construction Completion,
Construction Deliverables,
construction manager,
Construction Monitoring,
Construction Submittals,
Consultant,
Consultant Contract,
Contract Acquisition,
Contract Completion,
Contract Deliverables,
Contract Delivery,
Contract Development,
Contract Integration,
Contract Management,
Contract Milestones,
Contract Quality,
Contract Requirements,
Contract Submittals,
Contracts,
Decision Making,
Definitions,
Design,
Design Bid Build,
Design Build,
Design Build Delivery,
Design Deliverables,
Design Services,
Design Submittals,
Design-Bid-Build,
Division 1 Specifications,
Document Control,
Earned Value Management,
Engineering,
Estimating,
Estimator,
Ethics,
Factory Acceptance Test,
Final Acceptance,
Final Completion,
General Conditions,
General Provisions,
General Terms and Conditions,
Good Practices,
Government,
Hard Risks,
Hazards,
Human Resources,
Information For Bidders,
Inspection,
Inspection and Testing,
Inspection Test Plan,
Integration,
Integration Management,
Invitation For Bid,
Key Performance Indicators,
Knowledge Management,
Maintenance,
Management Integration,
Managerial Time,
Managing Change,
Managing Changes,
Master Project Schedule,
Meeting Minutes,
Mega Projects,
NCR Process,
Negotiations,
Non Conformance Report,
O&M Manuals,
Oversight Reports,
PM Fundamentals,
PMBOK,
PMI,
PMO,
Procurement Management,
Professional Obligations,
Program Management,
program manager,
Progress Reports,
Project Charter,
Project Controls,
Project Engineer,
Project Engineering,
Project Integration,
Project Interfacing,
Project Management,
Project Management Institute,
project management office,
Project Management Plan,
Project Manager,
Project Managerr,
Project Planning,
Project Records,
Project Schedules,
Project Team,
Project Teams,
ProjectManagement,
Public Relations,
punchlist,
Quality,
Quality,
Rail Car Purchase,
Rail Transit,
Rail Transit Organization,
Rail Transit Project,
Rail Transit Projects,
Railroad,
Reliability,
Resource Management,
RFI Logs,
risk,
Risk Allocation,
risk allocation,
Risk Allocations,
Risk Management,
Risk Management,
Safety,
Schedule Interfaces,
Schedule Management,
Schedule Milestones,
Scheduler,
Scheduling,
Scope of Work,
Security,
Seller,
Site Acceptance Test,
Soft Risks,
Special Inspections,
Specifications,
Submittal Logs,
Submittal Process,
Substantial Completion,
System Integration,
System Integration Test,
Systems,
Systems Purchase,
Testing/Test Management,
Threats,
Transformation,
Transformational Projects,
Transportation,
Vulnerability,
Work Area,
Work Areas
Date
Critical Components in Information For Bidders - Company Qualifications
This is the 2nd in a series of discussions that is intended to prompt Project Teams to be aware of the entire contract document, including Information For Bidders (IFB), General Conditions/Terms and Conditions (GCs) and the Technical Requirements [Specifications and Drawings.]
It is important the Buyer’s Project Manager, Contracting Officer, and technical representatives verify content and ensure the contract is complete and executable within the Buyer’s organizational assets and business processes.
Typically public and government contracts are advertised with legal notices in local and regional newspapers to attract a large pool of Seller’s to participate in the bid process. The larger the pool of potential Sellers, the better the opportunity for competitive bid pricing, and thereby increasing the potential best value for the Buyer and it funding partners, which many times include government funding.
Once the contract is advertised for bid, any business entity can obtain the contract documents and submit a bid for the work. In order to equally serve the time and financial investment by the Buyer and the bidders in the procurement process, the contract should identify company qualifications.
IFB Company Qualifications: Company qualifications are typically included in the Information for Bidders section of the standard form contract document. This section identifies the corporate requirements for the Seller. The requirements can include years experience; experience with project’s similar in scope, complexity and amount; licenses/certifications; and the technical capabilities of the Seller’s organization. The requirements should be correlated with the technical specifications regarding Cited Standards, Quality and Deliverables, and be consistent with the Engineer-Of-Record’s list of potential qualified Sellers for the contract work.
For construction in the rail transit domain, key project experience may include individual and combined scope for track and switches, DC substations, overhead AC catenary systems, third rail-traction power, ASC/cab signal systems, radio communications and fiber optic networks, supervisory centers and supervisory systems, train stations and platforms, rolling stock (passenger cars, locomotives and work trains), rolling stock and work train shops, and employee facilities.
TIP: The qualitative and quantitative requirements should be balanced with the qualified pool of Sellers but not be overly restrictive so as to reduce the submission of responsive bids.
TIP: Once the metrics are established in the contract, they can not be waived. In order to avoid any type of protest during the bid evaluation, provide some flexibility in requirements that allows for Buyer discretion using an equivalent combination of years experience, project experience, management expertise, and technical capabilities.
TIP: Requirements for installation specialists, system integrators and equipment suppliers can also be stated in the technical specifications, which are prepared by the EOR. During the final review of the completed contract documents, company qualifications in the IFB and specification sections should be aligned. As needed, the IFB can identify other unique company qualifications by reference to the specification section for requirements.
Posted on: September 10, 2018 09:15 PM |
Permalink
Comments (8)
Please login or join to subscribe to this item
Thanks for the look-in Henry.
Pench Batta
Enterprise Lean Agile DevOps Coach /SAFe Program Consultant (SPC6)| Capgemini, Inc.
Bentonville, Ar, United States
Henry, quite interesting article on Contracts!
Henry - Thanks for sharing insight.
Henry Hattenrath
Project Consultant| Tectonic Engineering MSA LLC
New York, Ny, United States
TIP: Requirements for installation specialists, system integrators and equipment suppliers can also be stated in the technical specifications, which are prepared by the EOR. During the final review of the completed contract documents, company qualifications in the IFB and specification sections should be aligned. As needed, the IFB can identify other unique company qualifications by reference to the specification section for requirements.
Vincent Guerard
Coach - Trainer - Speaker - Advisor| Freelance
Mont-Royal, Quebec, Canada
In another construction sector qualification also include health and safety information.
Stelian ROMAN
Project Manager| MicroSafety
Carlingford, New South Wales, Australia
Interesting, thanks for sharing
Henry, thanks for sharing this valuable information.
Please Login/Register to leave a comment.
|
"New York is my Lourdes, where I go for spiritual refreshment; a place where you're least likely to be bitten by a wild goat."
- Brendan Behan
|