Part 8 - Do You Know the Entire Contract

From the Project Management View from Rail Transit Programs and Projects Blog
by
A collection of articles sharing project processes, design and construction experience, best practices, and lessons learned along with operational knowledge related to executing programs and projects in the rail transit industry.

About this Blog

RSS

Recent Posts

Transitioning Constructed Products from Projects to Owner's Operations

Lessons to be Learned.  What Happens When the Buyer is Not the Owner, Operator and Maintainer of the Company?  

Managing Warranty After Achieving Contract Milestones

What Happens After the Buyer and Seller Agree on a Punchlist?

What is a Punchlist?

Categories

Acceptance, Analytics, ANSI, Asset Management, Best Value, Best Value Contractor Selection, Best Value Selection Criteria, Buyer, Certifications, Commissioning, Communications Management, Construction, Construction Completion, Construction Deliverables, construction manager, Construction Monitoring, Construction Submittals, Consultant, Consultant Contract, Contract Acquisition, Contract Completion, Contract Deliverables, Contract Delivery, Contract Development, Contract Integration, Contract Management, Contract Milestones, Contract Quality, Contract Requirements, Contract Submittals, Contracts, Decision Making, Definitions, Design, Design Bid Build, Design Build, Design Build Delivery, Design Deliverables, Design Services, Design Submittals, Design-Bid-Build, Division 1 Specifications, Document Control, Earned Value Management, Engineering, Estimating, Estimator, Ethics, Factory Acceptance Test, Final Acceptance, Final Completion, General Conditions, General Provisions, General Terms and Conditions, Good Practices, Government, Hard Risks, Hazards, Human Resources, Information For Bidders, Inspection, Inspection and Testing, Inspection Test Plan, Integration, Integration Management, Invitation For Bid, Key Performance Indicators, Knowledge Management, Maintenance, Management Integration, Managerial Time, Managing Change, Managing Changes, Master Project Schedule, Meeting Minutes, Mega Projects, NCR Process, Negotiations, Non Conformance Report, O&M Manuals, Oversight Reports, PM Fundamentals, PMBOK, PMI, PMO, Procurement Management, Professional Obligations, Program Management, program manager, Progress Reports, Project Charter, Project Controls, Project Engineer, Project Engineering, Project Integration, Project Interfacing, Project Management, Project Management Institute, project management office, Project Management Plan, Project Manager, Project Managerr, Project Planning, Project Records, Project Schedules, Project Team, Project Teams, ProjectManagement, Public Relations, punchlist, Quality, Quality, Rail Car Purchase, Rail Transit, Rail Transit Organization, Rail Transit Project, Rail Transit Projects, Railroad, Reliability, Resource Management, RFI Logs, risk, Risk Allocation, risk allocation, Risk Allocations, Risk Management, Risk Management, Safety, Schedule Interfaces, Schedule Management, Schedule Milestones, Scheduler, Scheduling, Scope of Work, Security, Seller, Site Acceptance Test, Soft Risks, Special Inspections, Specifications, Submittal Logs, Submittal Process, Substantial Completion, System Integration, System Integration Test, Systems, Systems Purchase, Testing/Test Management, Threats, Transformation, Transformational Projects, Transportation, Vulnerability, Work Area, Work Areas

Date

linkedin twitter facebook Request to reuse this  


Critical Components in General Conditions   -  Liquidated Damages

This is the 8th in a series of discussions that is intended to prompt Project Teams to be aware of the entire contract document, including Information For Bidders (IFB), General Conditions/Terms and Conditions (GCs) and the Technical Requirements [Specifications and Drawings.] 

It is important the Buyer’s Project Manager, Contracting Officer, and PM support services (estimator) verify content or provide input that ensures the contract is complete and executable within the Buyer’s organizational assets and business processes.   

GC – Liquidated Damages (LDs):   LSs is an estimated amount of costs incurred by the Buyer for the Seller’s delay in meeting milestones in contract Performance Schedule requirements.     The amount is expressed in a unit measure for the delay.  For each hour, day or week delay, the amount is accrued for  deduction from the Seller’s future payment requests/invoices.     The deduction is at the discretion of the Buyer and it follows the contract requirements for payments, which includes reduction for cause.   It does not constitute a change in the contract. 

The use of LDs is determined by the Buyer during the contract development process, and they are a function of critical interdependencies with other contract activities, other project work or other projects in a program or portfolio.   LDs can also be the result of statutory dates in government regulations and mandates that were used to identify Performance Schedule milestones and completion dates.     However, the Buyer’s decisions on LD requirements comes with the potential of higher bid amounts as bidders seek to cover the risks with allocations to mitigate potential delays and respond to events to minimize impacts from delays to milestones, and thereby to avoid erosion of profits.   

The LD amount is based on an estimate created from a description of impacts on the Buyer due to the Seller’s delay.   This may include expenses  for dedicated staff to support the Seller’s work ,including stand-by crews and equipment for schedule activities.   The estimate must be a reasonable representation of expenses and be based on the cost metrics and conditions known at the time of the bid.   

LDs can apply to one or more specific milestones in the Performance Schedule.   The most common milestone is Substantial Completion, which allows the Buyer to use the Seller’s product with the condition that punchlist work is defined and a completion date agreed upon before the contract completion milestone.    However at the Buyer’s discretion, other milestones and LD amount can be identifying and added during the contract development.

 LDs can not be waived.   The only action/remedy to reduce the Seller’s liability for Buyer’s estimate of incurred cost is for the Buyer to change the contract date in Performance Schedule for the milestone associated with the LD.    The process for changing the Performance Schedule can be initiated by the Buyer as a contract changes due to an Owner delay or by the Seller as a request for time extension.    The implementation of a schedule change requires the same level of diligence and justification as to grant an excusable delay or scope change, and to the documentation to substantiate and process the change in the contract.        

Usually, the contract does not include a “capped” amount for the accrued amount of LDs.  There may be organizational Lessons Learned that necessitate the Buyer adjusting the LD requirements.    This may be needed based on questions during the bid period from numerous bidders.    In order to ensure bid responses, the Buyer may adjust the LD amount and/or add requirements to specify a maximum accrued amount. 

For contracts in the rail transit domain, LDs are commonly used for contracts involving locomotive and passenger car purchases, specialized work equipment vehicle/shop equipment procurement, and for infrastructure systems for signals, supervisory controls, train movement controls, power substations, and signal power that are interdependent with other contracts within the project or program. 

TIP:   LDs estimate should be vetted thoroughly to ensure the document can be defended by the Buyer in response to a claim from the Seller or subsequent litigation action by the Seller. 

TIP:   LDs should be monitored and as potential accruals near, the Buyer and Seller should address the topics at progress meetings and describe actions in the monthly progress reports.

TIP:   LDs on multiple milestones should be carefully balanced with the administrative effort to monitor, manage, document and enforce.   


Posted on: October 27, 2018 12:45 PM | Permalink

Comments (3)

Please login or join to subscribe to this item
avatar
RAJESH K L Project Manager, PMP| Bharat Electronics, Bengaluru, India Bengaluru, Karnataka, India
Thanks for sharing

avatar
Eduin Fernando Valdes Alvarado Project Manager| F y F Fabricamos Futuro Villavicencio, Meta, Colombia
Very interesting, thanks for sharing

avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia