Project Management

Part 7 - Challenges, the Laws of Physics, Project/Construction Management and Reality

From the Project Management View from Rail Transit Programs and Projects Blog
by
A collection of articles sharing project processes, design and construction experience, best practices, and lessons learned along with operational knowledge related to executing programs and projects in the rail transit industry.

About this Blog

RSS

Recent Posts

Transitioning Constructed Products from Projects to Owner's Operations

Lessons to be Learned.  What Happens When the Buyer is Not the Owner, Operator and Maintainer of the Company?  

Managing Warranty After Achieving Contract Milestones

What Happens After the Buyer and Seller Agree on a Punchlist?

What is a Punchlist?

Categories

Acceptance, Analytics, ANSI, Asset Management, Best Value, Best Value Contractor Selection, Best Value Selection Criteria, Buyer, Certifications, Commissioning, Communications Management, Construction, Construction Completion, Construction Deliverables, construction manager, Construction Monitoring, Construction Submittals, Consultant, Consultant Contract, Contract Acquisition, Contract Completion, Contract Deliverables, Contract Delivery, Contract Development, Contract Integration, Contract Management, Contract Milestones, Contract Quality, Contract Requirements, Contract Submittals, Contracts, Decision Making, Definitions, Design, Design Bid Build, Design Build, Design Build Delivery, Design Deliverables, Design Services, Design Submittals, Design-Bid-Build, Division 1 Specifications, Document Control, Earned Value Management, Engineering, Estimating, Estimator, Ethics, Factory Acceptance Test, Final Acceptance, Final Completion, General Conditions, General Provisions, General Terms and Conditions, Good Practices, Government, Hard Risks, Hazards, Human Resources, Information For Bidders, Inspection, Inspection and Testing, Inspection Test Plan, Integration, Integration Management, Invitation For Bid, Key Performance Indicators, Knowledge Management, Maintenance, Management Integration, Managerial Time, Managing Change, Managing Changes, Master Project Schedule, Meeting Minutes, Mega Projects, NCR Process, Negotiations, Non Conformance Report, O&M Manuals, Oversight Reports, PM Fundamentals, PMBOK, PMI, PMO, Procurement Management, Professional Obligations, Program Management, program manager, Progress Reports, Project Charter, Project Controls, Project Engineer, Project Engineering, Project Integration, Project Interfacing, Project Management, Project Management Institute, project management office, Project Management Plan, Project Manager, Project Managerr, Project Planning, Project Records, Project Schedules, Project Team, Project Teams, ProjectManagement, Public Relations, punchlist, Quality, Quality, Rail Car Purchase, Rail Transit, Rail Transit Organization, Rail Transit Project, Rail Transit Projects, Railroad, Reliability, Resource Management, RFI Logs, risk, Risk Allocation, risk allocation, Risk Allocations, Risk Management, Risk Management, Safety, Schedule Interfaces, Schedule Management, Schedule Milestones, Scheduler, Scheduling, Scope of Work, Security, Seller, Site Acceptance Test, Soft Risks, Special Inspections, Specifications, Submittal Logs, Submittal Process, Substantial Completion, System Integration, System Integration Test, Systems, Systems Purchase, Testing/Test Management, Threats, Transformation, Transformational Projects, Transportation, Vulnerability, Work Area, Work Areas

Date

linkedin twitter facebook Request to reuse this  


Analytics at the Expenses of PM Overhead

Project Management Offices (PMO) establish and uniformly apply Key Performance Indicators (KPIs) for program and project managers to monitor performance on projects and programs of projects (Mega projects).   Typical KPIs on projects are Schedule Performance Index (SPI), Cost Performance Index (CPI) and Planned EVM verse Actual EVM.    Other KPIs for monitoring project cost and schedule goals can include forecasts of future efforts expressed in ratios including remaining duration, remaining EVM, Estimate To Complete, and pending project/contract changes.     

For projects that are not performing as expected, PMOs may need to conduct management reviews and implement additional monitoring measures to mitigate poor performance to cost and schedule.   As a result, more granular KPIs (Sub-KPIs) are created for work directly related to the performance of individual contributors with significant roles and responsibilities where the service quality was identified as a root cause affecting project performance. 

The purpose of the Sub-KPIs is to monitor, measure, assess and act on performance attributes and make decisions on critical activities in order to assure progress to meet project schedule milestones.  The goal is to improve processes and procedures, and to reduce schedule activity durations, which are identified as risk threats to critical project dates.   Each of the Sub-KPIs will capture historical data that will be used for identifying and resolving problems and for increasing confidence in future project decisions.  

This new level of monitoring will focus on analytics that PMO executives should establish through a defined breakdown structure of KPIs, which include metrics for activities that are driving durations of processes and procedures essential to quality performance to goals.    

Examples of Sub-KPIs include:

  • Days for processing Contract Change Orders (CO)
  • Days and manhours for reviewing Contractor Submittals
  • Days and manhours for responding to Contractor RFIs
  • Days for processing Project Changes (PC)
  • Percentage CO Change Amount from Original Contract Award Amount
  • Percentage PC Change Amount from the Original Project Budget.

In the example, the Sub-KPIs are all related to schedule progress as prioritized by the PMO.   A high percentage are outside the project teams control, and under the direct responsibility of the PMO’s management and the contracting office, which is usually an existing organizational asset within the Owner’s business structure.   As a result, monitoring of the related Sub-KPIs should have executive level buy-in and commitment that provides the PMO with the authority to improve processes and procedures.  

Creating new Sub-KPIs will require enhancement to existing reporting to incorporate color coded graphics such as dashboards, heat maps, histograms, and bar graphs, which provide conspicuous visual recognition of critical metrics for managing efforts across the project.   The color coding may indicate Red – Outside Tolerances - Action Required, Yellow – Near Tolerance Thresholds - Action Under Review, and Green – Within Tolerances - No Action  Required.   

Depending on the project domain, other Sub-KPIs may be created for monitoring and improving performance to intermediate milestones and EVM targets.    For rail-transit projects, there may be significant access restraints, production time limits, and promised on-site services by Owner to contractor.    In this case, Sub-KPIs might include ratios for:  1) Actual access days to site and planned access days.   2) Actual contact hours and planned production hours.   3) Actual crew days for work and planned crew days to support contractor.   4) Accrued liquidated damages and contract amount.   5) Accrued incentive payments verse contract budget.

Reality A

In theory, KPIs and Sub-KPIs increase management quality and improves project performance at the expense of added management overhead cost and staff levels.   However, each PMO needs to assess the benefits from the added managerial effort for implementing and monitoring the KPIs and Sub-KPIs.

Reality B

The number of KPIs will proportionally increase costs for Project Controls, management overhead and for added project analysts that are required for the collecting data, reporting data, explaining metric variances and implementing corrective actions.    

Reality C

At the expenses of other progress/performance report attributes and content, readers may overly focus on the red metrics while ignoring non-red items.  This may cause missed opportunities on schedule risk events that may actually be more significant to schedule performance and be more easily resolved to mitigate or avoid the events.

Reality D

Performance monitoring of Sub-KPIs without an improvement in schedule durations may indicate processes are not aligned with project expectations despite recognition of the impact to progress.    Executive management needs to ensure that the metrics identified as contributing to schedule risks can be mitigated.  Otherwise, the risks are just be accepted threats that need to be built into the schedule.     


Posted on: December 07, 2018 07:11 PM | Permalink

Comments (5)

Please login or join to subscribe to this item
avatar
Alok Priyadarshi Project Manager| Tata Consulting Engineers Limited Jamshedpur, Jharkhand, India
Nice post.
Thanks a lot!!

avatar
RAJESH K L Project Manager, PMP| Bharat Electronics, Bengaluru, India Bengaluru, Karnataka, India
Thanks for sharing. Good post.
Its nice to follow Part7 of the topic

avatar
Eduin Fernando Valdes Alvarado Project Manager| F y F Fabricamos Futuro Villavicencio, Meta, Colombia
Thanks for sharing

avatar
Vincent Guerard Coach - Trainer - Speaker - Advisor| Freelance Mont-Royal, Quebec, Canada
Interesting those KPIs, but I'm always surprised to see that both parties don't seem to take action on KPIs that are in the RED. Is that your experience?

avatar
Henry Hattenrath Project Consultant| Tectonic Engineering MSA LLC New York, Ny, United States
Vincent

My experience is that the KPIs need to be properly vetted and rigor tested by Project Controls with the PMs to determine if the results are correct and that the data is reliable, accurate and timely measuring performance to KPIs. Despite the limitations cited in PM texts regarding CPS and SPI, Project Controls and PMs simply worked the metrics. For CPS and SPI the range of metrics should be between 0.8 and 1.2. But PMO executives routinely accepted and trumpeted ratios that were outside this range. Ratios outside the range may be an indication that the data and the measured performance is not appropriate for the current environment.

Please Login/Register to leave a comment.

ADVERTISEMENTS

A cat is a lion in a jungle of small bushes.

- English proverbs

ADVERTISEMENT

Sponsors