Project Management

Contract Integration on Rail Transit Projects

From the Project Management View from Rail Transit Programs and Projects Blog
by
A collection of articles sharing project processes, design and construction experience, best practices, and lessons learned along with operational knowledge related to executing programs and projects in the rail transit industry.

About this Blog

RSS

Recent Posts

Transitioning Constructed Products from Projects to Owner's Operations

Lessons to be Learned.  What Happens When the Buyer is Not the Owner, Operator and Maintainer of the Company?  

Managing Warranty After Achieving Contract Milestones

What Happens After the Buyer and Seller Agree on a Punchlist?

What is a Punchlist?

Categories

Acceptance, Analytics, ANSI, Asset Management, Best Value, Best Value Contractor Selection, Best Value Selection Criteria, Buyer, Certifications, Commissioning, Communications Management, Construction, Construction Completion, Construction Deliverables, construction manager, Construction Monitoring, Construction Submittals, Consultant, Consultant Contract, Contract Acquisition, Contract Completion, Contract Deliverables, Contract Delivery, Contract Development, Contract Integration, Contract Management, Contract Milestones, Contract Quality, Contract Requirements, Contract Submittals, Contracts, Decision Making, Definitions, Design, Design Bid Build, Design Build, Design Build Delivery, Design Deliverables, Design Services, Design Submittals, Design-Bid-Build, Division 1 Specifications, Document Control, Earned Value Management, Engineering, Estimating, Estimator, Ethics, Factory Acceptance Test, Final Acceptance, Final Completion, General Conditions, General Provisions, General Terms and Conditions, Good Practices, Government, Hard Risks, Hazards, Human Resources, Information For Bidders, Inspection, Inspection and Testing, Inspection Test Plan, Integration, Integration Management, Invitation For Bid, Key Performance Indicators, Knowledge Management, Maintenance, Management Integration, Managerial Time, Managing Change, Managing Changes, Master Project Schedule, Meeting Minutes, Mega Projects, NCR Process, Negotiations, Non Conformance Report, O&M Manuals, Oversight Reports, PM Fundamentals, PMBOK, PMI, PMO, Procurement Management, Professional Obligations, Program Management, program manager, Progress Reports, Project Charter, Project Controls, Project Engineer, Project Engineering, Project Integration, Project Interfacing, Project Management, Project Management Institute, project management office, Project Management Plan, Project Manager, Project Managerr, Project Planning, Project Records, Project Schedules, Project Team, Project Teams, ProjectManagement, Public Relations, punchlist, Quality, Quality, Rail Car Purchase, Rail Transit, Rail Transit Organization, Rail Transit Project, Rail Transit Projects, Railroad, Reliability, Resource Management, RFI Logs, risk, Risk Allocation, risk allocation, Risk Allocations, Risk Management, Risk Management, Safety, Schedule Interfaces, Schedule Management, Schedule Milestones, Scheduler, Scheduling, Scope of Work, Security, Seller, Site Acceptance Test, Soft Risks, Special Inspections, Specifications, Submittal Logs, Submittal Process, Substantial Completion, System Integration, System Integration Test, Systems, Systems Purchase, Testing/Test Management, Threats, Transformation, Transformational Projects, Transportation, Vulnerability, Work Area, Work Areas

Date

linkedin twitter facebook Request to reuse this  


On rail transit projects with multiple design and construction contracts, a key project management function is Contract Integration.  

Typically, a contract has specific performance milestones for delivering services and furnishing systems, products and tangible assets to complete the work.  The work activities, durations and sequencing of predecessor and successor work are defined in the detailed contract schedule, which is used to report progress and determine payments to the contractor.    

When multiple contracts are executed under a single project with a fixed budget and end date, the interfaces between contracts is critical to organizing and monitoring the work to ensure it is executed in the same manner as-designed.   A Project Manager (PM) or designated Integration Manager will define the specific interfaces between the contracts, identify the activities that are linked to the interfaces, and create a Contract Integration Plan (CIP).   The CIP, which is a supplement to the Project Management Plan (PMP), is used by the PM to monitor and maintain the sequence of contract progress and manage risks that impact the overall project schedule. 

Contract integration is a cross-functional management activity that connects knowledge of processes, input/outputs, and tools and techniques from several areas of PMI’s Construction Extension to Project Management Body of Knowledge, such as Scope Management, Time Management and Risk Management.  

In rail transit construction, contract integration can be performed by any one of several members of the project team, including PM and staff, Contract Officer/Manager, Scheduler and Risk Manager.  However, contract integration requires the team acquire a thorough understanding of:

  • Procurement methods and durations
  • Scope and contents of the contract documents
  • Timing of work progress relative to other contracts
  • Likely means and methods by contractors to meet the performance requirements of the contracts
  • Interfaces created by the scheduled sequence of the contracts.  

While the PM will assign the responsibility to a single team member, the entire project team should be aware of the function and the key markers that will be established to monitor the interfaces between contracts. 

The scopes of contract packages are developed for execution in a certain sequence to achieve project scope realization by the time the last contract is completed.   The planned sequence of construction contracts is heavily dictated by the physical reality of the project environment, available means and methods, and the space within the project envelope.   Those physical considerations will determine the key interfaces between each contract as well as a confidence level that the project plan and schedule can be properly executed.    

A simple method to implement contract integration on a project is to:

A)        Identify and describe the interfaces between contracts.    PM will manage the development of the contract documents.  Based on the contract scope and performance requirements, PM will prepare a simple statement such as Contract A for the system must complete submittals before Contract B for the equipment foundation is awarded so the weight and loading of the system equipment and the footprint can be finalized for constructing the foundation.   The Interfaces may include contracts under other projects that are adjacent to the Project envelope. 

If part of a Program, the interfaces may include connections to predecessor and successor projects.  An example interface is -  Contract E for the Control Center can not be completed until Contract D for the fiber Optic Network under another project is completed and available to connect into the Control Center.  

B)        Create a Master Project Schedule (MPS) with milestones or constraints linking the contracts to specific activities and dates.    PM will create an Integration Management Plan (IMP) that describes the interface and the connected contracts.   PM will assure the interfaces are shown in the MPS and that they are properly link in the approved detailed contracts schedules for each contract.   The interfaces will create specific connections to activities in each project contract and as needed, interfaces to specific milestones in contracts on other project adjacent to the Project envelope.   As the MPS is updated for progress, changes in activities dates may show variances between milestone dates and forecast milestone dates.   

C)        Establish the monitoring methods, schedule variance metrics and triggers, and the frequency for assessing any impacts to the dates based on progress updates or changes to the contract schedules.   PM will define the integration management responsibility in the PMP and incorporate the MPS milestones interfaces into the Risk Management Plan (RMP).   This may be discussed at monthly progress meetings, quarterly updates for the risk management plan, and at PMO Quality Management System Meetings.      

D)        Describe the mitigation for impacts to milestones or constraints created by contractors’ progress that varies from the planned schedule.   PM will create a CIP that describes the interface and the connected contracts and the actions required to address schedule variance for interface dates.  As the CIP identifies interfaces, the RMP will be updated for the risk that contract interfaces are changed along with qualitative judgment on probability and impact.   As theses risks are triggered, PM will lead the development of solutions, analyze the solutions and alternatives, assess threats and opportunities to other contracts and projects, and select/present to PMO the best value decision.  Due to critical nature of construction schedules, the solution development process should be completed within the PM’s progress reporting period.     

E)        Prepare a response action for solutions that require changes to contract milestones.  PM will develop the response action for the RMP, which will detail the cost, schedule and scope impacts from the triggered risk.    Interfaces with contract schedule variances that can not be mitigated will require changes in project end-date.   Under the RMP, the PM will execute the response plan, which will implement changes to cost, schedule and scope on the affected contracts, and as needed, to the Project and to any other projects with interfaces.

TIP:  Before developing the CIP, ensure that the project has developed the prerequisite project documents such as Project Charter, PMP, and a Procurement Plan/Contract Packaging Plan 

TIP:   Contracts can include labor agreements for work conducted by the Owner’s in-house labor forces, which are governed by Owner’s collective bargaining agreements with the unions with jurisdiction for the work.  

TIP:   Before validating the project schedule and milestones and finalizing the CIP, obtain the Owner’s organizational process and forms to support the proposed procurement acquisition and delivery methods for authorizing work by contractors and in-house forces.  

TIP:    The responsibility for contract integration maybe best handled by the PM with support from a Scheduler or Project Coordinator providing monthly updates on key marker activities in the Master Schedule.

TIP:   Best value decisions should not seek to reduce the project scope or create dramatic changes in a Program.  However if it does, a thorough review of interfaces should produce a Lessons Learned that may include updating the planning and executing of projects and the packaging and sequencing of contracts. 


Posted on: March 30, 2020 06:47 PM | Permalink

Comments (1)

Please login or join to subscribe to this item
avatar
Henry Hattenrath Project Consultant| Tectonic Engineering MSA LLC New York, Ny, United States
TIP: The quality of contract integration includes understanding and aligning the interfaces threaded through the individual contracts. Before a contract is published the PM, Contract Administrator and Legal groups perform iterative checks. These checks include assuring interfaces between various sections are properly aligned with standard contractual work flows. An example is provisions for schedule, payments and definitions. Schedule milestones need to be defined and be connected to processing payments on voice requests as well as knowing how liquidated damages or value of remaining work/punchlist may affect the amount of approved payments.

Please Login/Register to leave a comment.

ADVERTISEMENTS

"Whatever does not destroy me makes me stronger."

- Friedrich Wilhelm Nietzsche

ADVERTISEMENT

Sponsors