CAMP Questions and Answers - Part 3
From the Project Management View from Rail Transit Programs and Projects Blog
by Henry Hattenrath
A collection of articles sharing project processes, design and construction experience, best practices, and lessons learned along with operational knowledge related to executing programs and projects in the rail transit industry.
Recent Posts
Transitioning Constructed Products from Projects to Owner's Operations
Lessons to be Learned. What Happens When the Buyer is Not the Owner, Operator and Maintainer of the Company?
Managing Warranty After Achieving Contract Milestones
What Happens After the Buyer and Seller Agree on a Punchlist?
What is a Punchlist?
Categories
Acceptance,
Analytics,
ANSI,
Asset Management,
Best Value,
Best Value Contractor Selection,
Best Value Selection Criteria,
Buyer,
Certifications,
Commissioning,
Communications Management,
Construction,
Construction Completion,
Construction Deliverables,
construction manager,
Construction Monitoring,
Construction Submittals,
Consultant,
Consultant Contract,
Contract Acquisition,
Contract Completion,
Contract Deliverables,
Contract Delivery,
Contract Development,
Contract Integration,
Contract Management,
Contract Milestones,
Contract Quality,
Contract Requirements,
Contract Submittals,
Contracts,
Decision Making,
Definitions,
Design,
Design Bid Build,
Design Build,
Design Build Delivery,
Design Deliverables,
Design Services,
Design Submittals,
Design-Bid-Build,
Division 1 Specifications,
Document Control,
Earned Value Management,
Engineering,
Estimating,
Estimator,
Ethics,
Factory Acceptance Test,
Final Acceptance,
Final Completion,
General Conditions,
General Provisions,
General Terms and Conditions,
Good Practices,
Government,
Hard Risks,
Hazards,
Human Resources,
Information For Bidders,
Inspection,
Inspection and Testing,
Inspection Test Plan,
Integration,
Integration Management,
Invitation For Bid,
Key Performance Indicators,
Knowledge Management,
Maintenance,
Management Integration,
Managerial Time,
Managing Change,
Managing Changes,
Master Project Schedule,
Meeting Minutes,
Mega Projects,
NCR Process,
Negotiations,
Non Conformance Report,
O&M Manuals,
Oversight Reports,
PM Fundamentals,
PMBOK,
PMI,
PMO,
Procurement Management,
Professional Obligations,
Program Management,
program manager,
Progress Reports,
Project Charter,
Project Controls,
Project Engineer,
Project Engineering,
Project Integration,
Project Interfacing,
Project Management,
Project Management Institute,
project management office,
Project Management Plan,
Project Manager,
Project Managerr,
Project Planning,
Project Records,
Project Schedules,
Project Team,
Project Teams,
ProjectManagement,
Public Relations,
punchlist,
Quality,
Quality,
Rail Car Purchase,
Rail Transit,
Rail Transit Organization,
Rail Transit Project,
Rail Transit Projects,
Railroad,
Reliability,
Resource Management,
RFI Logs,
risk,
Risk Allocation,
risk allocation,
Risk Allocations,
Risk Management,
Risk Management,
Safety,
Schedule Interfaces,
Schedule Management,
Schedule Milestones,
Scheduler,
Scheduling,
Scope of Work,
Security,
Seller,
Site Acceptance Test,
Soft Risks,
Special Inspections,
Specifications,
Submittal Logs,
Submittal Process,
Substantial Completion,
System Integration,
System Integration Test,
Systems,
Systems Purchase,
Testing/Test Management,
Threats,
Transformation,
Transformational Projects,
Transportation,
Vulnerability,
Work Area,
Work Areas
Date
This article complements the previous articles “What are good practices for Commissioning Acceptance and Maintenance Plan (CAMP)?” and Questions and Answers to CAMP – Parts 1 and 2. Here are Questions and Answers to CAMP – Part 3.
Are the CAMP requirements different for design bid build (DBB) and design build (DB) project delivery?
No. Since the CAMP process spans the design and construction phases of a project, the requirements are the same. However, the execution of the CAMP process is different. In DBB, there are separate contracts for Designer/Engineering of Record to create the construction contract, and for a Contractor to furnish/construct the product. In DB, there is a single contract where the EOR and Contractor are part of the same team with the design and construction phases proceeding in parallel.
If there is no CAMP in Div 1, where are the requirements found?
Commissioning, Acceptance and Maintenance Plan requirements may be spread throughout the general provisions and the technical specifications in the contract. As a result, the Buyer and Seller will need to work together to extract and consolidate the activities and documentation into a cohesive set of deliverables. In some cases, Buyers may label CAMP differently such as Integrated System Test Plan (ISTP) or System Test Plan, which may include Factory Acceptance Testing and Site Acceptance Testing.
On a project, is CAMP one package at the end of the project?
There can be one CAMP Package if the project consists of a single construction contract and there is no incremental acceptance of construction by the Buyer for operational use ahead of the substantial completion or construction completion as defined in the performance. Larger projects may include multiple contracts/subcontracts with scope that can be constructed and put into use independent of other contracts/subcontracts on the project. As a result, multiple CAMP packages will be required for each contract or subcontract. This may require the Project Management Plan incorporate a CAMP [Management] Plan to management the processes and deliverables.
What happens when the Buyer accepts the Sellers CAMP Package?
Based on typical contract requirements, the Buyer’s acceptance of the CAMP Package constitutes construction completion and the start of the Warranty period management by the Seller. During this period, the Buyer is responsible for periodic inspection and maintenance of the product, including consumable items. However failures and breakdowns of the constructed product is covered by the Sellers management of the established Warranty Plan. This normally includes Sellers labor and materials to repair the product to operational use.
What actions can the Buyer take to focus the Seller on completing punchlist work?
Creating an agreed upon punchlist is a co-predecessor to the contract milestone for Substantial Completion (SC ) and for issuance of certificates for occupancy. Finishing punchlist work is a predecessor to achieving the contract milestone for Construction Completion (CC). In order to focus the Seller on completing all work, the Buyer must carefully evaluate the Seller’s payment applications and assure the value of the remaining work is estimated and used by the Buyer to reduce the total earned value of verified work completed by the Seller. Under the General Provisions of the standard contract form, the Buyer can withhold the estimated value of remaining work from the invoice amount presented in the Seller’s payment application. In some contracts, the Buyer can reduce the Seller’s payment application amount by 2 times the estimated cost of remaining work.
Do you have any added Questions?
Posted on: April 15, 2020 05:36 PM |
Permalink
Comments (2)
Please login or join to subscribe to this item
Henry Hattenrath
Project Consultant| Tectonic Engineering MSA LLC
New York, Ny, United States
What actions can the Buyer take to focus the Seller on completing punchlist work?
Creating an agreed upon punchlist is a co-predecessor to the contract milestone for Substantial Completion (SC ) and for issuance of certificates for occupancy. Finishing punchlist work is a predecessor to achieving the contract milestone for Construction Completion (CC). In order to focus the Seller on completing all work, the Buyer must carefully evaluate the Seller’s payment applications and assure the value of the remaining work is estimated and used by the Buyer to reduce the total earned value of verified work completed by the Seller. Under the General Provisions of the standard contract form, the Buyer can withhold the estimated value of remaining work from the invoice amount presented in the Seller’s payment application. In some contracts, the Buyer can reduce the Seller’s payment application amount by 2 times the estimated cost of remaining work.