Project Management

Commissioning & Its Importance on Rail Transit Projects

From the Project Management View from Rail Transit Programs and Projects Blog
by
A collection of articles sharing project processes, design and construction experience, best practices, and lessons learned along with operational knowledge related to executing programs and projects in the rail transit industry.

About this Blog

RSS

Recent Posts

Transitioning Constructed Products from Projects to Owner's Operations

Lessons to be Learned.  What Happens When the Buyer is Not the Owner, Operator and Maintainer of the Company?  

Managing Warranty After Achieving Contract Milestones

What Happens After the Buyer and Seller Agree on a Punchlist?

What is a Punchlist?

Categories

Acceptance, Analytics, ANSI, Asset Management, Best Value, Best Value Contractor Selection, Best Value Selection Criteria, Buyer, Certifications, Commissioning, Communications Management, Construction, Construction Completion, Construction Deliverables, construction manager, Construction Monitoring, Construction Submittals, Consultant, Consultant Contract, Contract Acquisition, Contract Completion, Contract Deliverables, Contract Delivery, Contract Development, Contract Integration, Contract Management, Contract Milestones, Contract Quality, Contract Requirements, Contract Submittals, Contracts, Decision Making, Definitions, Design, Design Bid Build, Design Build, Design Build Delivery, Design Deliverables, Design Services, Design Submittals, Design-Bid-Build, Division 1 Specifications, Document Control, Earned Value Management, Engineering, Estimating, Estimator, Ethics, Factory Acceptance Test, Final Acceptance, Final Completion, General Conditions, General Provisions, General Terms and Conditions, Good Practices, Government, Hard Risks, Hazards, Human Resources, Information For Bidders, Inspection, Inspection and Testing, Inspection Test Plan, Integration, Integration Management, Invitation For Bid, Key Performance Indicators, Knowledge Management, Maintenance, Management Integration, Managerial Time, Managing Change, Managing Changes, Master Project Schedule, Meeting Minutes, Mega Projects, NCR Process, Negotiations, Non Conformance Report, O&M Manuals, Oversight Reports, PM Fundamentals, PMBOK, PMI, PMO, Procurement Management, Professional Obligations, Program Management, program manager, Progress Reports, Project Charter, Project Controls, Project Engineer, Project Engineering, Project Integration, Project Interfacing, Project Management, Project Management Institute, project management office, Project Management Plan, Project Manager, Project Managerr, Project Planning, Project Records, Project Schedules, Project Team, Project Teams, ProjectManagement, Public Relations, punchlist, Quality, Quality, Rail Car Purchase, Rail Transit, Rail Transit Organization, Rail Transit Project, Rail Transit Projects, Railroad, Reliability, Resource Management, RFI Logs, risk, Risk Allocation, risk allocation, Risk Allocations, Risk Management, Risk Management, Safety, Schedule Interfaces, Schedule Management, Schedule Milestones, Scheduler, Scheduling, Scope of Work, Security, Seller, Site Acceptance Test, Soft Risks, Special Inspections, Specifications, Submittal Logs, Submittal Process, Substantial Completion, System Integration, System Integration Test, Systems, Systems Purchase, Testing/Test Management, Threats, Transformation, Transformational Projects, Transportation, Vulnerability, Work Area, Work Areas

Date

linkedin twitter facebook Request to reuse this  


Recently a colleague in a leadership position on a rail transit project said, they do not understand the importance of testing.    This came after a project meeting, where incorporating more activities for Commissioning Acceptance and Maintenance Plan (CAMP) into the Detailed Contract Schedule (DCS) was discussed.   At the meeting, the feedback from the contractor’s Project Controls leader indicated that activities for inspection, testing and CAMP deliverables should not be in the DCS.   

In a previously posted article regarding Best Practices for Commissioning Acceptance and Maintenance Plan (CAMP), the Commissioning component was described as:  

Commissioning:   This is the pre-requisite activities and deliverables for starting the CAMP package and deliverables for Acceptance, and it is the Buyer’s (Owner) process for verification of project/contract scope and the Seller’s (Contractor) compliance with requirements.    The activities typically include Factory Acceptance Testing (FAT), On-Site Acceptance Testing (SAT), In-progress Inspections, Start-Up and Burn-In.   Commissioning activities should be integrated into Project Control schedules and Quality Plans, which contain quality control inspection and test plans.

This article expands on the Commissioning element of the CAMP process and deliverables and it describes the importance on rail transit projects.   The project assets typically include track switches and machines, signal systems, traction power systems, signal power systems, communication systems and security systems.      

Commissioning-Inspection and Testing

Inspections and testing of the contract product and deliverables is essential for demonstrating the work meets the contract and is ready for final acceptance.   The inspection and testing requirements are defined by the Owner or its designated Designer of Record (DOR) in the contract documents and in project plans.

  • Factory Acceptance Testing (FAT):   FAT is applied to high value, long lead, and critical assets that require extreme confidence that the asset will work when installed and interconnected to other products in the project to create an integrated system.    These type assets are usually supplied by specialty contractors to prime contractors for interconnecting all conduits and cables at the project site for operation.   The FAT is performed by the specialty contractors and it is usually witnessed by the prime contractor and other technical experts on the project.  FAT tests can range from several days to nearly a week or more depending on the complexity of test procedures and an action to correct problems.   FATs that require additional time may impact scheduled progress and require adjustments to interdependent activities in the DCS.
  • On-Site Acceptance Testing (SAT):  SAT is the successor to FAT.  SAT replicates much of the FAT and focuses on added testing for verifying operation with interconnected conducts, cable and supervisory systems.   The SAT is performed by the prime contractor and it is usually witnessed by the specialty contractor and other technical experts on the project.   Specialty contractors often provide on-site technical assistance to the prime contractor.   Due to the amount of preparatory pre-testing, SAT tests are usually several days and may require an Owner to make operational changes to accommodate testing.   SATs that require additional time may impact scheduled progress and require adjustments to interdependent activities in the DCS.
  • System Integration Testing (SIT):  SIT  is testing of several critical assets after the pre-requisite predecessor testing, including FAT and SAT.  SIT encompasses verifying asset operation within the overall rail transit system under conditions required to support its service plan, including train movement, passenger movement, customer information and announcements, safety and security monitoring, and central operating centers.   SITs that require additional time may impact scheduled progress and require adjustments to interdependent activities in the DCS.
  • First Article Inspections (FAIs):   FAIs involve testing to prove out design and functionality of components before mass production.   FAIs are usually applied to projects with retrofit scope involving the installation of equipment fleet-wide or system-wide to meet legal, statutory or regulatory requirements.    FAIs are performed at the specialty contractors’ facilities and may be followed by prototype installations on Owner property.   FAIs will create schedule hold points in DCS before specialty contractors will be released for production and delivery of the component.
  • Special Inspections (SIs):   SIs (and testing by independent testing agencies) are applied to project elements of construction such as steel, concrete, masonry, wood, soil, fire resistant materials, mastics, and smoke control, which bridges and buildings.   The SIs scope includes soil conditions, concrete rebar and formwork, concrete condition and strength, welding of structural members, bolting of structural members and fire proof insulation and coatings.   SIs will create schedule hold points in DCS for verifying test results meet requirements before work can proceed. 
  • Inspection and Testing Plans (ITP):   The ITP complements the SIs and covers the full scope of the project as described in the contract drawings and specifications.      ITP consists of the more routine inspections and tests that are part of the project Quality Management Program, which includes the Construction Quality Plan for overseeing the contractor’s workmanship, quality of materials, and compliance with contract drawings and specifications.   ITPs may create hold points in DCS for substantial completion and construction completion milestones, and to CAMP processes and deliverables until non-conformances are repaired, corrected or accepted under conditions by Owner or DOR.

With exception of ITPs, all of the inspections and tests require integration with interdependent construction activities to determine baseline dates.  As construction progress is updated in the DCS, changes in dates for inspections and testing may occur.

Best Practices - Commissioning

  • Projects must have a Project Management Plan covering construction monitoring and quality management with descriptions of scope, personnel, processes, and deliverables (sample Forms).
  • Contractor must have written procedures and deliverables for inspection and testing activities, and a process for monitoring performance and periodically updating plans to reflect scope changes and adjustments due to DCS.  
  • Owner must have a written plan to support contractor inspection and testing plans and with processes for monitoring Commissioning performance and implementing project and contract improvements.  
  • Owner’s project manager, with appropriate support staff, must focus on oversight of the contractor/subcontractors and provide direction to reinforce effective and integrated Quality processes across managerial silos.
  • Owner’s project representatives, or designated consultants, must be very familiar with the Organization and the responsible parties for obtaining and documenting technical feedback on the various inspections and testing for project elements.
  • Owner’s processes for travel arrangements must be flexible and responsive to changes in FAT and SAT dates.  This may be accomplished by implementing advance approvals for baseline dates that contain provisions to change dates without resubmitting arrangements. 

TIP:   Requirements for Project Management Plans can be found at several resources including www.transit.dot.gov [Federal Transit Administration] and www.PMI.org [Project Management Institute.]

TIP:    On large projects, FATs, SATs and FAIs need to be coordinated to avoid conflicts and to assure personnel and travel arrangements can be available for inspection and testing dates.

TIP:   FATs and SATs require advance review and approvals of the scope and procedures.  At least 60 days notice/submittal reviews prior to the anticipated dates should be shown on the DCS.

TIP:    For project work on system expansions, most of the SIT can be done while maintaining operations on other parts of the system. 

TIP:   For project work that is performed on an operating system, the SIT will need detailed staging and require an Owner to make operational changes to accommodate testing.     


Posted on: June 07, 2020 12:39 PM | Permalink

Comments (1)

Please login or join to subscribe to this item
avatar
Eduin Fernando Valdes Alvarado Project Manager| F y F Fabricamos Futuro Villavicencio, Meta, Colombia
Very interesting article., thanks for sharing

Please Login/Register to leave a comment.

ADVERTISEMENTS

"What is wanted is not the will to believe, but the wish to find out, which is the exact opposite."

- Bertrand Russell

ADVERTISEMENT

Sponsors