Project Management

What is budget variance?

From the The Money Files Blog
by
A blog that looks at all aspects of project and program finances from budgets, estimating and accounting to getting a pay rise and managing contracts. Written by Elizabeth Harrin from GirlsGuideToPM.com.

About this Blog

RSS

Recent Posts

3 Tips for when your to do list is full of important things

Managing data maturity risks

What does commercial viability mean?

Building resilience into project delivery

Lessons about project metrics



If you’ve been working in project management for some time, you might be familiar with the idea of variance. However, new project managers, or those who haven’t had to prepare financial information about their projects before, might find the idea a bit harder to get their heads around. Keep reading – this is for you!

I was speaking to one such project manager recently. While she had a ton of experience, she hadn’t needed to provide financial information for her projects as it wasn’t part of her stakeholders’ expectations. When the costs are mainly internal resource, many companies don’t require project managers to work that out in money terms. We tend to just estimate in days or some other unit of time and that’s good enough.

However, there will come a point in your career where you will most likely be asked to start crunching budget numbers for your projects. As you move into environments with greater levels of project management maturity, for example, it becomes more important to track things across projects in a standard way.

Budgets for money are the same in principle as budgets for time: you still need to work out how much you need and how much you are using, just like you would for time tracking on a project where you are only estimating in person hours/days. There’s another ‘however’ coming though…

However, in many organisations, including those where I have worked, it isn’t always necessary to track time. You create a project estimate at the beginning that states how many hours etc are needed from a resource in order to secure that resource, but after that, people are simply expected to manage their own time and the project is expected to conclude on the day you said it would. Timesheets don’t feature.

So, moving from this loose ‘we make a guess at how long things will take and go from there’ environment to one where you are expected to submit project reports with variance figures each week can be quite a challenge!

Luckily, the maths is not complicated and while it might seem daunting (especially if the numbers are big), variance is easy to track.

Budget variance

Here’s how to calculate budget variance.

Variance = Actuals + forecast – budget

In other words, you add up what you’ve spent so far with what you still have left to go, and compare that the original approved budget. The difference is the variance and shows whether you are under or over spent.

At the very beginning of the project the actuals are zero as you haven’t done anything yet. Each reporting period, simply pop the actuals into the right column and adjust the forecast down. Assuming you are on track, that is!

If you aren’t on track to hit your original estimates, you should be reforecasting the still-to-do work and noting those figures in the forecast column. Forecasts can change for lots of reasons including:

  • The team created estimates that were based on assumptions that haven’t held true
  • The team wasn’t very good at estimating
  • More work has been added to the project as the result of a change request
  • Work has been removed from the project as the result of a change request
  • Resources have changed and now you are working with someone less experienced who will take longer to do the tasks
  • Something else!

If you keep your forecast and actuals columns up to date, the rest is easy!

Tolerance

Normally there would be some tolerance agreed for the variance. For example, being under or over by 10% of the budget is OK but anything over that needs escalating to management or a change request etc.

Setting tolerance with your project sponsor will prevent you from having nightmares every time your project report says you are a few percentage points over budget.

How to get started

Make a spreadsheet that has the various columns. The simplest way is to have one column per field (actuals, forecast, budget, variance) and note the figures overall. As you get comfortable doing that, you might want to break them down by month to get a better idea of how things are tracking over time.

Once you’ve played with your project’s figures and have put together a spreadsheet to track them yourself (I recommend doing that instead of starting from someone else’s template so you can see how they fit together and what sums sit behind the columns) then you’ll get used to working out the numbers in this way.

I’m not a maths whizz by any means and I can manage it, so I’m sure you can too!

Posted on: February 24, 2022 06:19 AM | Permalink

Comments (5)

Please login or join to subscribe to this item
More than interesting and simple. Thank you.

Thanks Elizabeth.... So useful! just a question, what factors can be considered in setting a budget tolerance?

@Kwiyuh. Good question. I have written about budget tolerance in the past: https://www.projectmanagement.com/blog-post/3487/Managing-Money-Q-A--Part-6-?blogName=The-Money-Files&posting=3487 Basically, it's a way of managing risk, so whatever you think is appropriate to offset the risk involved with not knowing the exact figures. It's parameters within which you have freedom to act, so on some projects it might be zero. On others there might be a lot of flexibility.

Excellent one!!! Thanks for simple maths correlation

Thanks

Please Login/Register to leave a comment.

ADVERTISEMENTS

Work like you don't need the money, love like you've never been hurt, and dance like there's nobody watching.

ADVERTISEMENT

Sponsors