Project Management

Managing Money Q&A (Part 4): Why do projects go over budget?

From the The Money Files Blog
by
A blog that looks at all aspects of project and program finances from budgets, estimating and accounting to getting a pay rise and managing contracts. Written by Elizabeth Harrin from RebelsGuideToPM.com.

About this Blog

RSS

Recent Posts

How to learn AI the sensible way

Making sense of project cost reports

How real PM mentoring actually works

The Accidental Product Manager: What project managers need to know

How healthy are your project finances?

Categories

accounting, agile, ai, appraisals, Artificial Intelligence, audit, Backlog, Benchmarking, benefits, Benefits Management, Benefits Realization, Bias, books, budget, Business Case, business case, business case, Career Development, Career Development, carnival, case study, Change Management, checklist, collaboration tools, communication, Communications Management, competition, complex projects, Conferences, config management, consultancy, contingency, contracts, corporate finance, corporate finance, cost, Cost Management, cost management, credit crunch, CRM, data, data security, debate, Decision Making, delegating, digite, earned value, Education, Energy and Utilities, Estimating, events, FAQ, financial management, financial management, forecasting, future, GDPR, general, Goals, Governance, green, Information Technology, Innovation, insurance, interviews, it, Knowledge Management, Leadership, Lessons Learned, measuring performance, Mentoring, merger, methods, metrics, multiple projects, negotiating, Networking, news, Olympics, organization, Organizational Culture, outsourcing, personal finance, Planning, pmi, PMO, PMO, Portfolio Management, portfolio management, presentations, privacy policy, process, procurement, product management, productivity, Program Management, project closure, project data, project delivery, Project Success, project testing, prototyping, qualifications, Quality, quality, Quarterly Review, records, recruitment, reports, requirements, research, resilience, Resource Management, resources, risk, Risk Management, ROI, salaries, Schedule Management, Scheduling, scope, Scope Management, security, small projects, Social Impact, social impact, social media, software, software, software, Stakeholder Management, stakeholders, Strategy, success factors, supplier management, team, Teams, testing, testing, timesheets, tips, training, transparency, trends, value management, vendors, video, virtual teams, workflow

Date

linkedin twitter facebook Request to reuse this  


CalculatorIt was a while ago now that I gave a webinar on managing money on projects, but it is taking a long time to answer all the questions that I didn’t get round to doing during the live session.  Thanks to all the fabulous participants, who asked such brilliant questions!  I am still trawling through them hoping to answer them all, and here is today’s batch of managing money Q&A.  

What is the difference between the contingency and a reserve?

Nothing.  Call it whatever you want.  The idea behind both contingency and a reserve is to have a pot of money put aside in case of unforeseen developments.  Regardless of what you call it, you can’t draw on it as a matter of course.  Accessing the contingency fund is only done with the permission of the sponsor – it’s not there for you to use as a buffer because you haven’t managed to keep the project costs on track.

If you choose the biggest number in the range of total project cost, would you then use that as the basis for applying a percentage as contingency?

What you are talking about here is presenting budget figures as a range to key stakeholders during the decision making process.  This is a great idea, and it encourages people at the early stages of a project to take into account the fact that the planning is not yet completely finished.  If you then want to apply a percentage amount as contingency – say, 10% - choose the biggest number in the range. So if your budget prediction is a range of £250k to £280k, you would work out 10% contingency as 10% of £280k, giving you £28k.  You can always hand your contingency back if you don’t need it, or reforecast it to a more accurate level later.

How we can handle project cost in a software product development company where the same resources are being used both for Development and production support and trouble shooting the issues of the live product?

Timesheets!  The project costs you must be referring to here are resource costs.  All other costs could be attributed directly to the cost of brining a new product to market, like buying a new server to host it on or marketing for new clients.  Accurately predicting and monitoring resource costs on a project are going to be hard unless you know how your teams are spending their time. Get them to do timesheets for a couple of months to get a baseline of what percent of their time is spent on support and troubleshooting.  This will give you a basis on which to forecast going forward.

On the other hand, if you aren’t worried enough now to be tracking time and working out how much effort your teams put into managing projects, why do you want to going forward?  Consider the reasons why knowing this information is important to you before going to the effort of introducing a time recording system that won’t give you all the data you need to make useful business decisions.

Would you say an initial budget has a +/- % deviation and encourage revisiting the initial estimate to reduce the deviation or wait till you expect to exceed initial budget?

Never wait until you expect to exceed the initial budget to reforecast.  Typically, project budgets are reforecasted at the same time as the rest of the company accounts are reforecasted, so once a quarter is normal, if the project is large or costly.  You can set points in the project lifecycle where it is sensible for you to revisit the costs.  For example, after the first phase, or once the development is complete could both be good examples of where it is an appropriate time to look again at your projections.  

I would say a budget has a +/-% deviation, and I think this is a good habit for sponsors to get into – they should be used to looking at ranges of numbers, and you can then revisit this estimate to reduce the deviation once more detail is known.

What are the reasons for going over budget and how can I control it early?

Where do I start?!  Here are some reasons:  poor estimating, equipment costing more than you first thought, forgetting to add in the tax (I’ve done that), not calculating formulae properly so your sums are wrong before you start (done that too), a risk materialising and not having budgeted for problem resolution, resources costing more than you thought i.e. having to pay for overtime or weekend working. The list goes on, and I’m sure you have your own suggestions of why projects go over budget.

Mainly it all comes down to poor monitoring and control.   If you have estimated accurately, keep the project on track, manage the resources effectively, and forecast estimate to complete properly, you should at least have an early warning that you are going to go over budget, and you can address this appropriately.  That could be through increasing the budget, using the contingency fund, trimming down the scope or dropping the quality of some deliverables, or through other means.

Read Part 1 here
Read Part 2 here
Read Part 3 here

You can see the whole presentation online here, via a recording of the webinar.  I’ll have some more Q&A for you soon!
 


Posted on: August 06, 2010 04:45 PM | Permalink

Comments (1)

Please login or join to subscribe to this item
avatar
Kwiyuh Michael Wepngong
Community Champion
Financial Management Specialist | US Peace Corps Yaounde, Centre, Cameroon
Thanks

Please Login/Register to leave a comment.