Once you’ve ticked ‘mitigate’ as your risk management approach, you then have to think up ways to actually do that. What could you do to make the impact or likelihood of the risk less? Here are 4 options for reducing the risk – they won’t work on every risk, but they are general directions to consider when you’re wondering what to do to lighten the load for the project. And they are pretty easy to implement too, so that’s a bonus.
1. Start small
One of the easiest risk mitigation strategies is to start small. Consider prototypes, models, pilots. Think about how you can avoid a big bang launch and deliver results incrementally instead.
This works well as an approach if your project is using new technology, a new supplier, or is changing something sensitive, like a business critical process.
It doesn’t always work: on one large project I worked on we planned to deliver site by site, rolling out the new software and processes to groups at a time. But it didn’t work: for accounting reasons we had to maintain the integrity of the financial records and go big bang.
However, as a starting point, doing test runs and phased delivery is a good approach to mitigating all kinds of risk.
2. Schedule testing time
How many projects have you worked on where you’ve had enough time for testing? I’m embarrassed to say that plenty of my projects have ended up with testing time being squeezed.
As a project manager, you can control the schedule and double the amount of testing time planned (or whatever allocation of testing you feel appropriate, given input from the people involved in the work). That should give you long enough to wheedle out the bugs, which is another way of mitigating go live risks.
3. Add contingency to the schedule and budget
Explicit contingency is ‘extra’ time that is designed to offset risk: the risk of not knowing what you are doing, or whether it will work!
Manage uncertainty by adding a buffer to the duration of scheduled activities (or at phase level) and also to the budget.
I prefer contingency to be explicitly called out as an additional 10% of the budget and appropriate length for schedule contingency. Document what your approach will be in your schedule management plan and financial management plan.
4. Understand the guardrails for the project
Guardrails are like boundaries; tolerances for what freedom of action you have on the project. When you know where you have wiggle room and where you do not, you can make better decisions. Ultimately, your course of action to mitigate a risk should become easier because you know where you can save time and effort and where you cannot, because doing so will push you outside the guardrails.
When you’re working out what is the best course of action for a risk, think about where those boundaries lie and what options you have to work within them. That can help you decide whether your course of action requires an escalation or whether the team can manage without input from other layers of governance.
The right approach for risk mitigation depends on what the risk is, the risk appetite of your project and organisation, and what resources you have available to you. However, the above ideas are a starting point. What other common approaches do you use to mitigate project risks? Let us know in the comments!