Project Management

The Money Files

by
A blog that looks at all aspects of project and program finances from budgets, estimating and accounting to getting a pay rise and managing contracts. Written by Elizabeth Harrin from RebelsGuideToPM.com.

About this Blog

RSS

Recent Posts

Who really owns the project budget? Clarifying financial accountability

How to learn AI the sensible way

Making sense of project cost reports

How real PM mentoring actually works

The Accidental Product Manager: What project managers need to know

Categories

accounting, agile, ai, appraisals, Artificial Intelligence, audit, Backlog, Benchmarking, benefits, Benefits Management, Benefits Realization, Bias, books, budget, Business Case, business case, business case, Career Development, Career Development, carnival, case study, Change Management, checklist, collaboration tools, communication, Communications Management, competition, complex projects, Conferences, config management, consultancy, contingency, contracts, corporate finance, corporate finance, cost, Cost Management, cost management, credit crunch, CRM, data, data security, debate, Decision Making, delegating, digite, earned value, Education, Energy and Utilities, Estimating, events, FAQ, financial management, financial management, forecasting, future, GDPR, general, Goals, Governance, green, Information Technology, Innovation, insurance, interviews, it, Knowledge Management, Leadership, Lessons Learned, measuring performance, Mentoring, merger, methods, metrics, multiple projects, negotiating, Networking, news, Olympics, organization, Organizational Culture, outsourcing, personal finance, Planning, pmi, PMO, PMO, Portfolio Management, portfolio management, presentations, privacy policy, process, procurement, product management, productivity, Program Management, project closure, project data, project delivery, Project Success, project testing, prototyping, qualifications, Quality, quality, Quarterly Review, records, recruitment, reports, requirements, research, resilience, Resource Management, resources, risk, Risk Management, ROI, salaries, Schedule Management, Scheduling, scope, Scope Management, security, small projects, Social Impact, social impact, social media, software, software, software, Stakeholder Management, stakeholders, Strategy, success factors, supplier management, team, Teams, testing, testing, timesheets, tips, training, transparency, trends, value management, vendors, video, virtual teams, workflow

Date

3 Ways to Talk About the Accuracy of Estimates [Video]

Categories: Estimating

linkedin twitter facebook Request to reuse this  

Project estimating is something we have to do a lot. And being good at estimating generally means being accurate in the estimate. That doesn’t mean you have to get your budget figures defined to the nearest penny. But you do have to work out your numbers robustly and present them in a way that is clear to stakeholders. They need to understand how you are using the numbers and what they are looking at.

There are three ways to talk about the accuracy of estimates:

  1. Rough order of magnitude
  2. Budget estimate
  3. Definitive estimate

Find out more about how these different types of estimates are defined and calculated using ranges in this short video.

Read more articles about estimating.

Pin for later reading:

Posted on: March 04, 2019 09:00 AM | Permalink | Comments (7)

How To Facilitate an Estimating Session

Categories: Estimating

linkedin twitter facebook Request to reuse this  

estimating meeting

So you need to estimate some work for your project? Great. Project managers need estimates to help with planning, scheduling and budgeting. Estimates are useful things. But how do you get there?

Estimates come from talking to people. Even if you use scenario-based software or modelling tools, you have to talk to people to get the parameters set up correctly. The easiest way to do this is to run an estimating session.

Here’s how to facilitate the meeting so you get the outcome you need.

1. Get the right people in the room

First, get the right people in the room.

I’d recommend having separate meetings with separate groups of colleagues. There’s nothing more boring than having to sit in a meeting where people are estimating tasks that have nothing to do with your work, waiting around for your chance to talk about how long your work is going to take. If you don’t need everyone there together, split them up.

You need to have people who have the knowledge to contribute to the estimating process. These will be people who:

  • Have done the exact same tasks before
  • Have done very similar tasks before
  • Know a lot about the subject matter
  • Manage people who do the tasks
  • Have been involved in projects where these exact same tasks or similar tasks were done.

Your meeting attendees don’t have to hit every item on that list, but they should be knowledgeable and helpful to the ultimate goal of the meeting, which is to come up with estimates for your project plan. And that brings us on to…

2. Have clear outcomes

You can have a loose agenda, but you need to have clear outcomes. What are you estimating: the whole workstream or a particular phase? A set of tasks for the coming month?

Are you estimating time or money or both? If it’s time, do you want to get duration or effort out of the meeting (or both)?

If you are clear about what you need to achieve before the meeting closes, you are more likely to get there.

Keep bringing people back to the ultimate goals of the meeting and reminding people what you need from them. You can keep the meeting on track far better with clear goals – and generally, people want to be out of a meeting room as soon as possible!

3. Agree the techniques or approach

What tools, methods, approach and techniques are you going to use? People often get hung up at this stage because the language is off-putting. Is chatting with your expert peers really a technique? The PMBOK® Guide – Sixth Edition would describe this as Expert Judgement.

All this step means is work out how you are going to do the estimating. Make sure everyone understands how it is going to happen. For example, if you are using Monte Carlo simulation, then you’ve got software and a process for doing it. If you are making up the estimates based on a set of sticky notes on the wall and a long debate ending with a guesstimate, that’s fine too. Just get everyone on the same page.

Have an open conversation about how vague you are prepared for the estimates to be, and at what point they would be firmed up. How are you going to track confidence levels? (Are you going to note down confidence levels at all?) Sorting out things like this at the beginning of the meeting will ensure everyone understands the context for the estimate and can explain it to others when they leave the room.

If part of your approach requires looking at past project data (a very handy and robust way to estimate similar tasks) then I’d suggest you have that ready and accessible. Run a few reports or download some planned/actual data before the meeting so you don’t have to waste time in the session itself trying to find the figures you need.

4. Do the estimating

Now you come to the part where you have to do the estimating. You’ve got the right people. They know why they are there and what you need to get out of the session.

Now talk to them. Use the tools you’ve decided on. Run simulations, stick sticky notes on the wall. Pull up holiday calendars and plan around vacation time.

This part is the bulk of your meeting. Go through each item and estimate it. Make sure everyone has a chance to contribute. If you notice disagreements in the estimating process, try a technique like three-point estimating to bring most and least likely scenarios together in a way your experts can agree on.

5. Document and use the estimates

Document how you got to the estimate. You might think you’ll remember, but in three years, when someone asks you to run an estimating session for their project, trust me, you won’t remember exactly how you arrived at the end result. Sometimes I don’t even remember how an estimate was calculated and we only worked it out a few months ago.

Write down your assumptions and the constraints you took into account when coming up with the final figures. Note the confidence levels and anything else you considered when you were discussing the estimate.

Finally, all you have to do is use the estimates. Incorporate the outcomes into your project schedule or budget. Look at what impact that has. Update resource calendars and any other documentation that might change as a result of the new numbers.

Then get on and deliver those tasks!

Posted on: March 02, 2019 01:44 PM | Permalink | Comments (7)

Deep Dive: Project Schedule Management: Sequence Activities

Categories: Scheduling

linkedin twitter facebook Request to reuse this  

Today’s deep dive into the PMBOK Guide®-- Sixth Edition is into the third part of Project Schedule Management: the Sequence Activities process. I’m going to call out the differences between this process and what we used to have in the PMBOK Guide® -- Fifth Edition.

We’ve already planned for the work (see part 1 of this Deep Dive) and defined the activities (see part 2).

Sequence Activities Process

This is the third process in the Knowledge Area. We’re still in the Planning process group.

This process is about putting the activities you’ve already defined into a logical sequence. The main output is your network diagram, which shows how tasks link. However, I don’t think I’ve ever created a network diagram for a project. I’ve certainly sequenced activities, but I’ve never done it in such a formal way. A few sticky notes on some flip chart paper or just common sense as I’m putting the Gantt chart together tend to be the way I go about it. I’m sure there are projects that would benefit from a detailed network diagram, and I don’t doubt that it is a useful tool.

I’m from the school of thought that says don’t do things for the sake of them, just because the book says so, as long as you get the right result. I expect earlier in my career I spent more time checking the order of activities before defining my schedule, but now it all seems to happen as part of an integrated afternoon of planning.

Back to the detail of this process…

Inputs

There are quite a few changes to the Inputs between the PMBOK Guide® -- Fifth Edition and Sixth Editions. Having said that, in essence the main change is that the detailed list of documents has been removed, and replaced with the generic Project Management Plan and Project Documents. These are nice catch all inputs that also allow a more broad interpretation of what needs to be considered for activity sequencing.

Tools & Techniques

The only change to the Tools and Techniques is the addition of your project management information system. In other words, PMI acknowledges that you probably won’t create a network diagram using paper and pens.

Your PMIS is most likely an integrated project scheduling tool. If it does Gantt charts, it probably does network diagrams too, so you can print one out to prove you have it if ever you need it. I have looked at network diagrams in Microsoft Project before, so despite not actively putting them together as a distinct step before scheduling, I have found them useful for a visual representation of the project overall, especially when some activities look out of sequence or I can’t work out how the dependencies should look.

Software is helpful for:

  • Planning, organising and switching round activities so they appear in the right sequence
  • Managing dependencies, leads, lags and logical connections (plus making these connections visual on the Gantt chart and in the network diagram)
  • Helping you make the best choice for the dependencies used – I find that as there are options, I’m more likely to use the options, instead of always plumping for the Start to Finish type
  • Saving time. No one’s got time to produce a network diagram or project schedule from scratch, have they?

Outputs

There are no new outputs. Nice and easy. It’s all as it was before.

You’d expect this process to be followed by Estimate Activity Resources, but that’s actually been moved to the Resource Management Knowledge Area.

That means next time I’ll be looking at Estimate Activity Durations.

Pin for later reading:

Posted on: March 02, 2019 01:43 PM | Permalink | Comments (7)

3 Ways Processes Add Risk to Projects [Video]

Categories: risk

linkedin twitter facebook Request to reuse this  

The processes you have for project management – or lack of them – can add significant risk to your project. But you don’t often find them called out on the risk log.

Poor processes can add time delays, extra steps and confusion. They contribute to poor communication and overspending. They impact project quality. In short, processes that aren’t optimal can hinder your ability to deliver a decent outcome for the project.

Unfortunately, processes are often constrained by the company you are in. If you are mandated to follow certain processes, you have little flexibility to do anything about them. That’s not a good situation to be in – ideally you should be able to tailor the process to the size and complexity of your project.

I’ve highlighted three of the main process-related factors that influence risk on your project in the video below.

Read more articles about risk.

Pin for later reading:

Posted on: February 12, 2019 09:00 AM | Permalink | Comments (9)

3 Principles for Project Metrics

Categories: metrics

linkedin twitter facebook Request to reuse this  

How often have you looked at a set of data points and wondered what the… point was of capturing them at all? I’ve seen PMOs with measures for how many projects were closed in a month but not measures for whether those closed projects were done on time and on budget, for example. Sometimes I think our desire to catalogue and record everything goes a little bit too far. There isn’t any point in capturing data that no one cares about.

This graphic shows three core principles for creating and using metrics. They are universally applicable but good for project managers because we have to think up (and then find ways to track) KPIs and success criteria measures for our projects. And if you’re in a PMO role, you must have a bunch of data points you are collecting too – I wonder how many of them make it into the reports you produce for stakeholders? And then how many stakeholders actually read and care about them?

For more on the topic of what makes a good measure for your project, take a look at this article, which digs into some examples and how to make sure that you are creating measures that are useful, in more detail.